Reservoir change short funds

Site requires reconfiguring design

PORT ANGELES — Work on the Dungeness off-channel reservoir continues, but funding is going to be a problem.

The Clallam County Board of Commissioners heard a presentation updating them on the project during their work session meeting Monday morning. During that update, the board was told that to get a final design on the project, they’re about $1.1 million to $1.4 million short.

“To get that final design, we’re going to need more funding,” said Deputy Director Steve Gray.

In October, Clallam County purchased approximately 400 acres from the state Department of Natural Resources along River Road and Happy Valley Road south of U.S. Highway 101 and Sequim. The $1.24 million purchase was paid for with a state grant.

The county plans to build a reservoir on the site as well as a stormwater capture and aquifer recharge infiltration facility. Design work on the reservoir is set back due to potential siesmic activity on the site, which required the preliminary design be reset, Anchor QEA Project Manager David Rice said.

“We’re busy looking at option E1 to move that design forward,” Rice said. Option E1 is a two cell version of the reservoir with pipes running beneath the Bonneville Power Administration’s power easement on the site.

The project is short $119,000 to complete the preliminary design.

“We think there are ways to refine design with assumptions to push capacity up to 1,300 acre feet,” Rice said. “The design can adjust the embankment slopes, top and bottom elevations of reservoir and shift closer to the road. Because the reservoir footprint has shifted, we do need to do a little bit more exploration to understand what the soils are like.”

The next step is to schedule and complete priority borings, which Rice said would likely happen in late summer or early fall.

The design team will also want to take a closer look at landslide hazards on the hillside to the east, according to a slideshow presentation.

Cleanup of the dumpsite which was on the land is set to begin in July and take four to six weeks, project coordinator Rhiana Barkie said.

Savings from the dumpsite cleanup could possibly be used to cover the budget shortfall for the preliminary design, Barkie said.

Construction on the project depends on a FEMA Hazard Mitigation grant for $30 million, which the county has applied for.

Gray said the project is being worked on in phases and that a “Go, no go” point will come when they know if construction is funded.

The goal is to have the design shovel-ready, Gray said.

________

Reporter Emily Hanson can be reached at emily.hanson@peninsuladailynews.com.

More in News

Dan Willis of Port Townsend, a docent at the Point Wilson Lighthouse at Fort Worden State Park, conducts a tour for interested visitors on Thursday. The lighthouse was built in 1878 when Congress approved $8,000 for the light and foghorns. Although the facility is still an active U.S. Coast Guard station, the equipment is monitored and operated remotely and no keepers are present. Regular tours on Saturdays and Sundays will resume in May. (Steve Mullensky/for Peninsula Daily News)
Lighthouse tour

Dan Willis of Port Townsend, a docent at the Point Wilson Lighthouse… Continue reading

EMT Teresa DeRousie, center, was recognized for her long service to Clallam County Fire District 2. Presenting the award were Deputy Fire Chief Kevin Denton, left, and Chief Jake Patterson. (Clallam County Fire District 2)
Clallam 2 Fire Rescue hosts awards banquet

Clallam 2 Fire-Rescue recognized career and volunteer members during… Continue reading

Construction set to begin on new marine life center in Port Angeles

Groundbreaking event scheduled for April 8 at Pebble Beach Park

A seal pops its head out of the water as a dory rower propels his craft in the calm waters of the Salish Sea. Whidbey Island is in the distance. Today’s high temperature is forecast to be in the low 50s with partly cloudy skies. Rain is set to return this weekend. (Steve Mullensky/for Peninsula Daily News)
Rowing on the Strait

A seal pops its head out of the water as a dory… Continue reading

Fire protection may impact insurance rates

New protection class considers nuanced data

The view looking south from Hurricane Ridge, where variable winter weather has limited snow coverage and contributed to pauses in snow sports operations in recent weeks. (Washington’s National Park Fund)
Lack of snow has impact at Hurricane Ridge

Water equivalent well below average for February

Port Angeles secures grant to aid in salmon recovery

State Department of Commerce to provide city with $109,000

Tickets still available for United Way of Clallam County fundraiser

Pajamas are encouraged, teddy bears are optional and comfort… Continue reading

Interviews set for hospital board

At least seven candidates up for commissioner seat

Port Angeles asks for fee to cover lodging tax contracts

Resolution sent to committee for administrative costs

Climate action group is guiding reduction goals

Reduced emmissions require reduced transportation footprint