Lowered speed limit safer on U.S. Highway 101, Sequim chamber audience told

SEQUIM –– Reduced speeds in the construction zone of the widening project of U.S. Highway 101 between Sequim and Port Angeles have made the construction zone safer, state Department of Transportation officials said Tuesday.

DOT chiefs briefed an audience of more than 50 people at the Sequim-Dungeness Valley Chamber of Commerce luncheon at SunLand Golf & Country Club.

Speed limits were lowered in May to 45 mph through the construction zone after several vehicle collisions occurred early in the project, including one that killed Bryan Crawford of Port Angeles, 52.

DOT originally had planned to leave the speed limit at 55 mph, but Moore said plans changed after it was realized that people slowing to watch the earth movers at work had led to other drivers suddenly having to slow down.

“There’s less skidding now, and it just feels safer out there,” said Jerry Moore, engineer for the project, who is based in Port Angeles.

The $27.1 million project, being built by Kent-based Scarsella Bros., will replace the last stretch of two-lane highway between Sequim and Port Angeles with four lanes of divided highway between Kitchen-Dick and Shore roads.

On schedule

Ken Dayton, regional administrator for DOT, said Scarsella’s progress on the job is ahead of schedule and under budget.

“We have a very aggressive contractor that’s doing a very, very good job out there,” Dayton said.

Half of the raw land for the new lanes is close to subgrade, meaning it soon will have the base rock laid on it.

The project also includes two new bridges over McDonald Creek.

Moore said the four support pillars are finished, and girders soon will be laid on the bridge, which replaces a decaying 1939 timber trestle.

Once complete, likely in October, traffic will switch to the south lanes across the bridge to allow crews to build another new bridge in the existing north lanes.

Dayton noted DOT had trouble securing funding to replace the McDonald Creek bridge, which was not scheduled for replacement for another two years.

“We just kept telling them that we couldn’t give them a four-lane highway only to take it back to two lanes two years later,” Dayton said.

“But there’s not really a holistic look at the state’s transportation system sometimes.”

4 lanes and a median

When finished in the fall of 2014, the four 12-foot-wide travel lanes will be separated by a 40-foot grass median.

The widening has been in the DOT’s playbook since the Sequim bypass was engineered in 1990, Moore said.

Access to several county roads that intersect with the highway will be changed.

Instead of turning left onto the highway, drivers will be directed onto six “indirect left” U-turns to get on the highway, similar to the one east of Deer Park Road east of Port Angeles.

________

Sequim-Dungeness Valley Editor Joe Smillie can be reached at 360-681-2390, ext. 5052, or at jsmillie@peninsuladailynews.com.

More in News

Shoe with human remains found on Sequim beach

A shoe containing human remains was found on the beach… Continue reading

Sue Bahl walks with an umbrella on West Eighth Street on Monday. Heavy rainfall up to 8 inches over the past several days has increased the threat of landslides in Western Washington, according to the National Weather Service. A flood watch also has been issued until 4 p.m. Friday for portions of northwest and west central Washington, including Clallam and Jefferson counties. Sharp rises in rivers, especially those flowing off the Olympics and Cascades, are expected, the National Weather Service said. (Dave Logan/for Peninsula Daily News)
Atmospheric river

Sue Bahl walks with an umbrella on West Eighth Street on Monday.… Continue reading

Clallam board approves budget, homelessness task force funds

County OKs eight proposals for housing, assistance

Five-year plan to address Jefferson County homelessness

Action steps assigned to jurisdictions, providers

Navy security exercise slated for Wednesday at Indian Island

Naval Magazine Indian Island will conduct a security training… Continue reading

Santa greets well wishers who showed up at Haller Fountain in Port Townsend on Saturday to witness the lighting of the community Christmas tree. About four hundred fans of all ages turned out for the annual event. (Steve Mullensky/for Peninsula Daily News)
Community celebration

Santa greets well wishers who showed up at Haller Fountain in Port… Continue reading

WSDOT updates highway projects

Hood Canal work expected in spring

Jefferson County is expected to make cuts to staff, services

$5.2M deficit brought down to $1.1M; vote expected on Dec. 22

Wreaths Across America tribute slated for Saturday

The Michael Trebert Chapter of the Daughters of the… Continue reading

Body found in Bogachiel River likely missing fisherman

A body recovered from the Bogachiel River this weekend is… Continue reading

Sequim’s 2026 budget is about 11 percent less than this year with fewer capital projects and a new cap on municipal funding. Staffing will increase by 1.1 full-time-equivalent employees following retirements, position changes and new hires. (Matthew Nash/Olympic Peninsula News Group)
Sequim approves $51.6M budget

Utility increases to continue for five years

Santa Claus, the Grinch and career and volunteers with Clallam County Fire District 3, IAFF Local 2933 and the Community Emergency Response Team (CERT) will accept food and toy donations this week as part of Santa’s Toy and Food Fire Brigade in Sequim. The food and toy drive will end on Friday at Sequim Walmart with donations accepted from 9 a.m. to 9 p.m., and Santa arriving to hand out candy canes and take photos from 5 p.m. to 8 p.m. (Matthew Nash/Olympic Peninsula News Group)
Toys, food to highlight Sequim Santa Brigade

Program will culminate Friday with booth at Walmart location