Substation failure causes Port Townsend power outage

PORT TOWNSEND — Electrical power lost Wednesday night was restored to about 4,000 customers within the Port Townsend city limit by about 1:30 a.m. Thursday.

Power was out for about three hours after three voltage regulators at the Kearney Street substation failed, according to Jim Parker, Jefferson County Public Utility District general manager.

Replaced next week?

The regulators failed simply because of age, Parker said, and will be replaced at a cost of about $75,000, hopefully sometime next week.

The first calls about the outage came in at 10:30 p.m., he said.

Power service for the affected area, which included downtown and uptown Port Townsend as well as the fairgrounds area and North Beach, was transferred to the Hastings Street substation.

The switch took more time than it ordinarily would have because of repairs already in progress at the Hastings Street facility, Parker said.

During the closure of the Hastings Street substation, power for the customers it served was divided between the Kearney Street and Irondale facilities.

The area south of Safeway and along Hastings Avenue did not lose power because it was hooked up to the Irondale facility, Parker said.

The three failed voltage regulators were contained in one unit weighing about 30,000 pounds.

They will be replaced by three smaller standalone units, each of which weighs about 3,500 pounds.

All materials are on hand. The delay is because the PUD must secure a crane large enough to lift the failed unit.

The replacement with the smaller units means that “in the future if they fail, we can pull them out with our own equipment,” Parker said.

The outage left the downtown area dark, with several restaurants closing early.

Several people gathered in the moonlight on the beach near Better Living Through Coffee, with some of them taking part in a moonlight swim.

A small number of customers were in the Uptown Pub drinking by candlelight and being entertained by Dave Sheehan on an acoustic guitar.

Facebook exchange

Some power customers took to Facebook to exchange information about the incident.

Parker said among the calls he received was one person asking if the outage had been caused by a solar flare, while another theorized it was the result of a terrorist attack to commemorate the 9/11 emergency.

In the case of an outage, PUD customers are asked to phone 360-385-5800 for information.

________

Jefferson County Editor Charlie Bermant can be reached at 360-385-2335 or cbermant@peninsuladailynews.com.

More in News

Search and rescue teams locate deceased man

A deceased man was located following search and rescue… Continue reading

Anita La Salle, kneeling in the center, poses with her family of son, daughters, son-in-law and grandkids, all from Port Townsend, after spending Saturday on a scavenger hunt and celebrating a reunion to welcome a long-lost family member who hasn’t been seen in more than 50 years. The hunt originated at the Port Townsend Goodwill, where they each had to buy matching clothes, and took them to various venues around Port Townsend culminating at the anchor at Fort Worden State Park. This is the first Christmas they have all been together as a family. (Steve Mullensky/for Peninsula Daily News)
Family reunion

Anita La Salle, kneeling in the center, poses with her family of… Continue reading

Clallam seeking to extend contracts

Pacts would impact criminal justice in Port Angeles, Sequim

John Nutter.
Olympic Medical Center board commissioner dies at age 54

Nutter, police officer of year in 2010, also worked for hospital, port

State Patrol: Four injured after driver falls asleep at wheel

Four people were injured after a driver fell asleep… Continue reading

ODT near Hill Street reopens after landslide

The Olympic Discovery Trail between Hill Street and Marine… Continue reading

Justice Loftus holds up a dinosaur mask he received at the Winter Wishes assembly. He said he plans to use it to play with his younger brother. (Matthew Nash/Olympic Peninsula News Group)
Sequim High School assembly grants students’ requests

Annual assembly provides gifts via leadership class

Deb Carlson, president of the Sequim-Dungeness Hospital Guild, presents a check for $9,585 to Deputy Police Chief John Southard and City Manager Matt Huish to help purchase three automated external defibrillators (AEDs) for three new vehicles and new AED pads and first aid supplies for the full fleet. (Matthew Nash/Olympic Peninsula News Group)
Guild marks $2.5M in support for medical needs

Shop donations reopen in February, sales in March

Marylaura Ramponi stands by an excavator donated for geotechnical work at Sequim School District by Jamestown Excavating. She donated $1 million for the naming rights of the Ramponi Center for Technical Excellence, a career and technical education building that will be built in conjunction with new buildings at Sequim High School. (Matthew Nash/Olympic Peninsula News Group)
Progress begins on CTE building

Ramponi Center could be done by early 2028

Weekly flight operations scheduled

There will be field carrier landing practice operations for aircraft… Continue reading

Volunteers serve up a full breakfast on Christmas morning, for the Third Community Breakfast at the Fred Lewis Scout Cabin in Port Townsend put on by the Reach Out Community Organization, a homeless advocacy program. A full breakfast was served to about 150 people during the morning. On the serving line are, from the back, Rose Maerone, Marie France and Susan Papps. (Steve Mullensky/for Peninsula Daily News)
Festive breakfast

Volunteers serve up a full breakfast on Christmas morning, for the Third… Continue reading

Growler analysis report complete

Environmental Impact Statement and recommendations released