Port: Point Hudson jetty rebuild ahead of schedule

Earlier reopening likely, officials say

An aerial view of the north jetty shows it as it is being rebuilt at the Point Hudson Marina.

An aerial view of the north jetty shows it as it is being rebuilt at the Point Hudson Marina.

PORT TOWNSEND — The rebuild of the jetty at Point Hudson that protects the marina from storms is ahead of schedule, say officials with the Port of Port Townsend.

Capital Facilities Director Matt Klontz said last week that Orion Marine Contractors is a week or 10 days ahead of schedule and that the marina may be able to open earlier than Orion’s March 1 deadline, according to a press release.

Most of the 178 steel piles for the new jetty have been installed, including those that form the protective dogleg, Klontz said.

That means placing the new rock inside the pilings can start earlier than expected.

The marina has been closed since mid-September for the rebuild work. All boats were moved to the Boat Haven Marina or other locations. Only vessels waiting for work by Sea Marine at the head of Point Hudson are in the marina today.

“The placement of pilings has gone very well, without obstructions,” Klontz said, saying that it was due to Orion’s success in pulling out both old creosoted pilings and old stone above and below mud.

It turns out the old pilings weren’t as long as initially thought, he said.

Orion expected to remove a total of 480 tons of old pilings. The actual total was 250 tons.

Another surprise was the muted noise of the project to date, the result of Orion’s use of a vibratory hammer rather than a traditional pile-driver.

“Orion has been great to work with,” Klontz said.

Some of the new thick-walled steel pilings are 60 feet long, Klontz said. All were driven 25 to 30 feet below the mud line of Port Townsend Bay. All are 16 feet above the zero tide level.

The rebuild schedule also has benefited from mostly calm, sunny weather and the timely delivery of materials such as the steel piles.

Once the piles are all in place, the half-ton basalt stones that will fill the inside of the pilings will arrive by barge from Tacoma, the port said in the release.

The rock comes from a quarry near Orting. The huge overhead crane on site will load stones to the halfway point of the pilings, Klontz said in the release. Then tie rods will attach the pilings across the cribbing to one another. Afterwards, the rest of the rock will be loaded in with an excavator.

Orion is working on the north jetty now. The Tacoma-based firm is expected to return in September 2023 to rebuild the south jetty.

The entire project, which was in the works for at least a decade, is expected to cost $14 million, of which half comes from the U.S. Department of Commerce and another $2.5 million from Washington state.

The balance comes from the port’s voter-approved Industrial Development District levy, Jefferson County’s infrastructure fund and the U.S. Fish and Wildlife Service.

The current Point Hudson jetties were built in 1934. Deterioration over the decades has allowed windstorms to sweep through the marina during high winter tides. The marina has 50 boater slips, an annual 5,000 vessel visits and is home to business that employ more than 150 residents.

Matt Klontz, capital projects director for the Port of Port Townsend, surveys the new pilings now in place at the Point Hudson Marina.

Matt Klontz, capital projects director for the Port of Port Townsend, surveys the new pilings now in place at the Point Hudson Marina.

More in News

Dan Willis of Port Townsend, a docent at the Point Wilson Lighthouse at Fort Worden State Park, conducts a tour for interested visitors on Thursday. The lighthouse was built in 1878 when Congress approved $8,000 for the light and foghorns. Although the facility is still an active U.S. Coast Guard station, the equipment is monitored and operated remotely and no keepers are present. Regular tours on Saturdays and Sundays will resume in May. (Steve Mullensky/for Peninsula Daily News)
Lighthouse tour

Dan Willis of Port Townsend, a docent at the Point Wilson Lighthouse… Continue reading

EMT Teresa DeRousie, center, was recognized for her long service to Clallam County Fire District 2. Presenting the award were Deputy Fire Chief Kevin Denton, left, and Chief Jake Patterson. (Clallam County Fire District 2)
Clallam 2 Fire Rescue hosts awards banquet

Clallam 2 Fire-Rescue recognized career and volunteer members during… Continue reading

Construction set to begin on new marine life center in Port Angeles

Groundbreaking event scheduled for April 8 at Pebble Beach Park

A seal pops its head out of the water as a dory rower propels his craft in the calm waters of the Salish Sea. Whidbey Island is in the distance. Today’s high temperature is forecast to be in the low 50s with partly cloudy skies. Rain is set to return this weekend. (Steve Mullensky/for Peninsula Daily News)
Rowing on the Strait

A seal pops its head out of the water as a dory… Continue reading

Fire protection may impact insurance rates

New protection class considers nuanced data

The view looking south from Hurricane Ridge, where variable winter weather has limited snow coverage and contributed to pauses in snow sports operations in recent weeks. (Washington’s National Park Fund)
Lack of snow has impact at Hurricane Ridge

Water equivalent well below average for February

Port Angeles secures grant to aid in salmon recovery

State Department of Commerce to provide city with $109,000

Tickets still available for United Way of Clallam County fundraiser

Pajamas are encouraged, teddy bears are optional and comfort… Continue reading

Interviews set for hospital board

At least seven candidates up for commissioner seat

Port Angeles asks for fee to cover lodging tax contracts

Resolution sent to committee for administrative costs

Climate action group is guiding reduction goals

Reduced emmissions require reduced transportation footprint