The Port of Port Townsend Commissioners have approved a bid for construction on the Point Hudson jetty that will cost about $10.2 million. (Peninsula Daily News file)

The Port of Port Townsend Commissioners have approved a bid for construction on the Point Hudson jetty that will cost about $10.2 million. (Peninsula Daily News file)

Port of Port Townsend approves jetty project

Low bid gives flexibility, officials say

The Port of Port Townsend commissioners unanimously approved a construction contract Wednesday for improvements to the Port Hudson breakwater jetty after learning federal grant money had been approved.

Capital Projects Director Matt Klontz told the commission the port had received a low bid from Orion Marine Contractors, Inc. of roughly $10.2 million, well below the engineer’s estimate of $14.3 million.

“It’s a fantastic price,” Klontz said. “This is great news for the port, for the community.”

The port had been awaiting final approval of funding from the U.S. Department of Commerce Economic Development Administration, which is providing 50 percent of the overall costs, according to the meeting’s agenda materials, but Klontz said that approval was given Tuesday.

Port officials were confident the approval would come, Klontz said, and already instructed the contractor to order the steel pilings necessary to complete the projects.

The custom-made pilings require a long time to be delivered, agenda materials said. Ordering the pilings early was essential to getting the materials in time for construction to begin this fall.

Port Executive Director Eron Berg said the process would take place in two five-month stages over two years, each from Sept. 15 to March 1, during which time Port Hudson would essentially be closed. The SEA Marine boatyard will still have limited access to Port Hudson, but all other tenants of the marina would have to remove their vessels, Berg said.

“We won’t have any vessels there because we won’t be able to provide protection,” Berg said.

Port officials reached out to tenants, Berg said, and accommodations were being made at nearby port facilities including the Boat Haven Marina.

“We are maintaining availability so that vessels will have a place to go,” Berg said.

Berg said the contractors would begin their work in September immediately following the city’s Wooden Boat Festival both this year and again next year. The work is expected to be completed by February and the port reopened on March 1, he said.

The low bid allowed the project some financial breathing room, Klontz said, allowing the designers to add additional thickness to the walls.

“Having that additional wall thickness will allow them to stand the test of time,” Klontz said of the jetties.

Commissioner Pete Hanke said the project coming in below budget means port officials are “ahead of the game” in responding to potential added costs.

“It’s outstanding we came in at $10 (million) and change,” Hanke said. “It gives us so much latitude to add in some options if we need to.”

According to the meeting’s documents, anticipating the projected $14 million cost, the port was able to secure roughly $16.2 million in funding for the project, including about $7 million from the federal EDA grant and $3.5 million from the state.

Berg said that money covers additional costs to the project, including materials, planning and design.

“We’re comfortable where we’re at, but it’s too soon to think that money won’t be needed,” Berg said.

Construction was completed in 1936, Peninsula Daily News previously reported, and repairs were made to the breakwater in 1969 and again in 1996. Port officials had been looking into replacing the jetty as far back as 2015, according to the port’s project overview page, but bids for previous iterations of the project had come in too high. The already aging jetty was further damaged in 2018 windstorms.

“Now the fun part can begin,” Klontz said of the project.

________

Reporter Peter Segall can be reached at psegall@soundpublishing.com.

More in News

Dan Willis of Port Townsend, a docent at the Point Wilson Lighthouse at Fort Worden State Park, conducts a tour for interested visitors on Thursday. The lighthouse was built in 1878 when Congress approved $8,000 for the light and foghorns. Although the facility is still an active U.S. Coast Guard station, the equipment is monitored and operated remotely and no keepers are present. Regular tours on Saturdays and Sundays will resume in May. (Steve Mullensky/for Peninsula Daily News)
Lighthouse tour

Dan Willis of Port Townsend, a docent at the Point Wilson Lighthouse… Continue reading

EMT Teresa DeRousie, center, was recognized for her long service to Clallam County Fire District 2. Presenting the award were Deputy Fire Chief Kevin Denton, left, and Chief Jake Patterson. (Clallam County Fire District 2)
Clallam 2 Fire Rescue hosts awards banquet

Clallam 2 Fire-Rescue recognized career and volunteer members during… Continue reading

Construction set to begin on new marine life center in Port Angeles

Groundbreaking event scheduled for April 8 at Pebble Beach Park

A seal pops its head out of the water as a dory rower propels his craft in the calm waters of the Salish Sea. Whidbey Island is in the distance. Today’s high temperature is forecast to be in the low 50s with partly cloudy skies. Rain is set to return this weekend. (Steve Mullensky/for Peninsula Daily News)
Rowing on the Strait

A seal pops its head out of the water as a dory… Continue reading

Fire protection may impact insurance rates

New protection class considers nuanced data

The view looking south from Hurricane Ridge, where variable winter weather has limited snow coverage and contributed to pauses in snow sports operations in recent weeks. (Washington’s National Park Fund)
Lack of snow has impact at Hurricane Ridge

Water equivalent well below average for February

Port Angeles secures grant to aid in salmon recovery

State Department of Commerce to provide city with $109,000

Tickets still available for United Way of Clallam County fundraiser

Pajamas are encouraged, teddy bears are optional and comfort… Continue reading

Interviews set for hospital board

At least seven candidates up for commissioner seat

Port Angeles asks for fee to cover lodging tax contracts

Resolution sent to committee for administrative costs

Climate action group is guiding reduction goals

Reduced emmissions require reduced transportation footprint