The Polar Resolution, an oil tanker from Long Beach, Calif., moors Thursday at the Port of Port Angeles-owned Terminal 1, where $4.9 million in improvements were recently completed. (Jesse Major/Peninsula Daily News)

The Polar Resolution, an oil tanker from Long Beach, Calif., moors Thursday at the Port of Port Angeles-owned Terminal 1, where $4.9 million in improvements were recently completed. (Jesse Major/Peninsula Daily News)

Port of Port Angeles completes repairs of Terminal 1

PORT ANGELES — The Port of Port Angeles has completed nearly $5 million in repairs and improvements on Terminal 1, its oldest piece of infrastructure.

During the $4.9 million project, crews replaced more than 380 wooden piles with coated steel piles, contracted a new barge dolphin and made major repairs to the head tie dolphin, said Chris Hartman, director of engineering.

Dolphins are mooring points not attached to the dock.

The dock was built in 1927 and many of the pilings were nearly 90 years old.

“Terminal 1 is the port’s oldest piece of infrastructure,” Hartman said. “It’s why the port was created in the first place.”

The terminal is primarily used for topside repairs of oil tankers, typically traveling between Alaska and California, he said.

“The biggest customers are oil tankers,” he said. “They come down here when they need work done, anything other than coming out of water.”

Vigor Industrial, a shipbuilding and ship repair company with 12 locations in the Pacific Northwest and Alaska, uses the terminal to repair ships that don’t need to go into dry dock, Hartman said.

“Terminal 1 is an extremely important piece of infrastructure to marine repair companies here in Port Angeles,” he said. “That piece of infrastructure is vital for them.”

The project was first approved in July of 2015 and reached substantial completion Oct. 31 of this year.

Work was originally anticipated to be finished by the end of March, but there were numerous delays in procuring steel piling.

The contractor also encountered extremely dense soil conditions when installing piling for the new barge dolphin.

A list of punch list items was completed in late November, and port commissioners officially put the project to rest Monday.

The port replaced the wood piles with steel piles primarily for environmental reasons, Hartman said.

“When it was originally constructed, they used creosote coating so they could last,” he said. “That’s no longer allowed.”

Hartman said there are other approved coats for wood piles but that it made more sense to choose steel, which lasts much longer.

The project was partially funded by a $1,500,000 grant from the U.S. Department of Commerce.

The port paid $850,670.38 out of pocket in 2015 and another $2,528,256.55 this year, for a total of $3,378,926.93.

The port budgeted $3 million toward the project this year. Even with more than $375,000 in change orders, the project came in roughly $475,000 under budget.

“We were anticipating [extra costs], it being as old of a structure as it is,” Hartman said. “You anticipate finding additional repairs.

“We put a significant contingency on top of it to be sure we were covered.”

That 7.8 percent increase from change orders came after crews found more things that needed repairs and as some damage was caused during construction.

Among those repairs was for dock damage on Terminal 3 after a ship went in too hard, Hartman said. Terminal 3 is the port’s loading dock and is adjacent to Terminal 1.

________

Reporter Jesse Major can be reached at 360-452-2345, ext. 56250, or at jmajor@peninsuladailynews.com.

More in News

Dan Willis of Port Townsend, a docent at the Point Wilson Lighthouse at Fort Worden State Park, conducts a tour for interested visitors on Thursday. The lighthouse was built in 1878 when Congress approved $8,000 for the light and foghorns. Although the facility is still an active U.S. Coast Guard station, the equipment is monitored and operated remotely and no keepers are present. Regular tours on Saturdays and Sundays will resume in May. (Steve Mullensky/for Peninsula Daily News)
Lighthouse tour

Dan Willis of Port Townsend, a docent at the Point Wilson Lighthouse… Continue reading

EMT Teresa DeRousie, center, was recognized for her long service to Clallam County Fire District 2. Presenting the award were Deputy Fire Chief Kevin Denton, left, and Chief Jake Patterson. (Clallam County Fire District 2)
Clallam 2 Fire Rescue hosts awards banquet

Clallam 2 Fire-Rescue recognized career and volunteer members during… Continue reading

Construction set to begin on new marine life center in Port Angeles

Groundbreaking event scheduled for April 8 at Pebble Beach Park

A seal pops its head out of the water as a dory rower propels his craft in the calm waters of the Salish Sea. Whidbey Island is in the distance. Today’s high temperature is forecast to be in the low 50s with partly cloudy skies. Rain is set to return this weekend. (Steve Mullensky/for Peninsula Daily News)
Rowing on the Strait

A seal pops its head out of the water as a dory… Continue reading

Fire protection may impact insurance rates

New protection class considers nuanced data

The view looking south from Hurricane Ridge, where variable winter weather has limited snow coverage and contributed to pauses in snow sports operations in recent weeks. (Washington’s National Park Fund)
Lack of snow has impact at Hurricane Ridge

Water equivalent well below average for February

Port Angeles secures grant to aid in salmon recovery

State Department of Commerce to provide city with $109,000

Tickets still available for United Way of Clallam County fundraiser

Pajamas are encouraged, teddy bears are optional and comfort… Continue reading

Interviews set for hospital board

At least seven candidates up for commissioner seat

Port Angeles asks for fee to cover lodging tax contracts

Resolution sent to committee for administrative costs

Climate action group is guiding reduction goals

Reduced emmissions require reduced transportation footprint