The expansion of Jefferson Healthcare hospital in Port Townsend has been delayed due to rising cost estimates. — Joe Smillie/Peninsula Daily News

The expansion of Jefferson Healthcare hospital in Port Townsend has been delayed due to rising cost estimates. — Joe Smillie/Peninsula Daily News

Jefferson Healthcare hospital delays $20 million expansion in light of increasing cost estimates

PORT TOWNSEND –– Jefferson Healthcare hospital officials say a boom in Seattle construction has raised the cost of building to the point that they must delay their $20 million expansion project.

Mike Glenn, the hospital’s CEO, said Wednesday the Jefferson Healthcare commission agreed April 16 to put off the project by three months after learning that the cost of building a new emergency and specialty services building was well over estimates.

That means construction that was targeted to begin this fall will not begin until spring of 2015 at the earliest.

“Between the last two cost estimates, there was a significant increase,” Glenn said.

“That’s due, we believe, to the Seattle construction market heating up.”

CollinsWoerman, the Seattle architecture firm enlisted to design the new building, reported estimates on construction were as high as $18 million.

The hospital had planned $15.7 million for construction, Glenn said.

With equipment, furniture, taxes and design and permit costs, the overall project would cost as much as $22 million.

The new 50,000-square-foot wing would include upgrades to the emergency room and make more room for the oncology, orthopedics and cardiology departments.

It would also give the hospital a new entrance on Sheridan Street.

The hospital commission approved the expansion in October 2013 after the hospital secured a 3.5 percent loan from the U.S. Department of Agriculture to fund $15.6 million of the project.

Glenn said the hospital plans to secure a separate loan to fund the balance.

The hospital does not plan to ask voters to fund the project through a property tax levy, Glenn said.

Hospital staff, along with the architects, now will review the project to see where they may find savings in building materials.

“Ultimately, this is going to be a good exercise because it’s going to make us revisit nearly every construction detail,” Glenn said.

“If you’re looking at a $16 million project, even a 10 percent reduction is significant.”

An example of such a change could be switching from a brick facade to a cheaper masonry facade.

“There’s probably hundreds of those decisions we are going to be reviewing as we sort of value-engineer the project,” Glenn said.

That review likely will be brought back to the hospital board in the fall.

Glenn said bids could be requested toward the end of this year, with groundbreaking in March of 2015.

In that case, completion would be pushed back from the end of 2015 to the summer of 2016.

________

Sequim-Dungeness Valley Editor Joe Smillie can be reached at 360-681-2390, ext. 5052, or at jsmillie@peninsuladailynews.com.

More in News

Dan Willis of Port Townsend, a docent at the Point Wilson Lighthouse at Fort Worden State Park, conducts a tour for interested visitors on Thursday. The lighthouse was built in 1878 when Congress approved $8,000 for the light and foghorns. Although the facility is still an active U.S. Coast Guard station, the equipment is monitored and operated remotely and no keepers are present. Regular tours on Saturdays and Sundays will resume in May. (Steve Mullensky/for Peninsula Daily News)
Lighthouse tour

Dan Willis of Port Townsend, a docent at the Point Wilson Lighthouse… Continue reading

EMT Teresa DeRousie, center, was recognized for her long service to Clallam County Fire District 2. Presenting the award were Deputy Fire Chief Kevin Denton, left, and Chief Jake Patterson. (Clallam County Fire District 2)
Clallam 2 Fire Rescue hosts awards banquet

Clallam 2 Fire-Rescue recognized career and volunteer members during… Continue reading

Construction set to begin on new marine life center in Port Angeles

Groundbreaking event scheduled for April 8 at Pebble Beach Park

A seal pops its head out of the water as a dory rower propels his craft in the calm waters of the Salish Sea. Whidbey Island is in the distance. Today’s high temperature is forecast to be in the low 50s with partly cloudy skies. Rain is set to return this weekend. (Steve Mullensky/for Peninsula Daily News)
Rowing on the Strait

A seal pops its head out of the water as a dory… Continue reading

Fire protection may impact insurance rates

New protection class considers nuanced data

The view looking south from Hurricane Ridge, where variable winter weather has limited snow coverage and contributed to pauses in snow sports operations in recent weeks. (Washington’s National Park Fund)
Lack of snow has impact at Hurricane Ridge

Water equivalent well below average for February

Port Angeles secures grant to aid in salmon recovery

State Department of Commerce to provide city with $109,000

Tickets still available for United Way of Clallam County fundraiser

Pajamas are encouraged, teddy bears are optional and comfort… Continue reading

Interviews set for hospital board

At least seven candidates up for commissioner seat

Port Angeles asks for fee to cover lodging tax contracts

Resolution sent to committee for administrative costs

Climate action group is guiding reduction goals

Reduced emmissions require reduced transportation footprint