It’s all logs over the dam: Work begins on jam caused by preliminary dam removal operations

PORT ANGELES — Workers in two 16-foot motorboats began uncoupling a 10-acre flotilla of logs on Lake Mills on Friday and Saturday.

For about four hours, they nudged the logs toward a current that carried the debris through a gate in the Glines Canyon Dam.

There, a curling torrent of water hurled the logs 210 feet from the top of the edifice down to the comparatively passive Elwha River.

Federal Bureau of Reclamation workers are untangling several hundred logs that are putting pressure on a log boom that protects the dam’s spillway from debris and potential failure, said Kevin Yancy, Elwha Dam power plant supervisor.

If the boom broke, the debris could clog up the spillway, sending water over the top of the dam in an uncontrolled release of water that no one wants to see.

“We could have spillway failure with all that there and have a lot of water going downriver that we weren’t planning on dumping,” Yancy said.

“That’s a key concern with dam safety,” he said. “That’s why the log booms are in place there.”

During the project, which is expected to take several days, Lake Mills will remain open for recreation.

The schedule for breaking up the log jam will be dependent on water flow that must be fed by sufficient snowpack in the Olympics, Yancy said.

On Friday, 5,000 cubic feet a second roiled through the gate.

That equals 2.25 million gallons a minute, Yancy said.

Bureau of Reclamation workers clear the lake annually of woody debris.

But this year, the number of nuisance logs dramatically increased after a delta at the mouth of Lake Mills was cleared last fall.

The 37-acre delta, which gradually built up after Glines Canyon Dam was built on the Elwha River in 1927, was shaved of alder trees and a channel dug through it to release sediment as part of the $351 million Elwha River Restoration project.

The project includes tearing down the Glines Canyon Dam and its sister dam, the Elwha Dam, farther downriver beginning in September.

About 90 percent of the logs that are putting pressure on the boom are from the delta-clearing project, Yancy said Friday.

He stood on top of the wind- and rain-swept dam near the spillway while his boat-borne Bureau of Reclamation colleagues, dwarfed by the floating mass of wood, separated the logs.

Trees plucked from the delta still have their root wads intact, making the job this year even more difficult.

“They’re are all tied together like this,” Yancy said, knitting his rubber-gloved fingers together.

“To push that apart is quite a challenge,” he said.

For most of Friday morning, workers armed with a chain saw and 18-foot pike poles fought 20-knot winds, cutting through large logs and clearing a path to the main boom gate.

They finally opened it, allowing the debris to float toward its 20-story free fall.

Some of these logs will hang up on the river’s shoreline.

But many will float about nine miles downriver to Lake Aldwell, bumping up against the smaller, 108-foot Elwha Dam to be flung once again over a giant wall.

“In a week or so, we’re going to have to go to the lower dam and do the same thing,” Yancy said.

________

Senior staff writer Paul Gottlieb can be reached at 360-417-3536 or at paul.gottlieb@peninsuladailynews.com.

More in News

Dan Willis of Port Townsend, a docent at the Point Wilson Lighthouse at Fort Worden State Park, conducts a tour for interested visitors on Thursday. The lighthouse was built in 1878 when Congress approved $8,000 for the light and foghorns. Although the facility is still an active U.S. Coast Guard station, the equipment is monitored and operated remotely and no keepers are present. Regular tours on Saturdays and Sundays will resume in May. (Steve Mullensky/for Peninsula Daily News)
Lighthouse tour

Dan Willis of Port Townsend, a docent at the Point Wilson Lighthouse… Continue reading

EMT Teresa DeRousie, center, was recognized for her long service to Clallam County Fire District 2. Presenting the award were Deputy Fire Chief Kevin Denton, left, and Chief Jake Patterson. (Clallam County Fire District 2)
Clallam 2 Fire Rescue hosts awards banquet

Clallam 2 Fire-Rescue recognized career and volunteer members during… Continue reading

Construction set to begin on new marine life center in Port Angeles

Groundbreaking event scheduled for April 8 at Pebble Beach Park

A seal pops its head out of the water as a dory rower propels his craft in the calm waters of the Salish Sea. Whidbey Island is in the distance. Today’s high temperature is forecast to be in the low 50s with partly cloudy skies. Rain is set to return this weekend. (Steve Mullensky/for Peninsula Daily News)
Rowing on the Strait

A seal pops its head out of the water as a dory… Continue reading

Fire protection may impact insurance rates

New protection class considers nuanced data

The view looking south from Hurricane Ridge, where variable winter weather has limited snow coverage and contributed to pauses in snow sports operations in recent weeks. (Washington’s National Park Fund)
Lack of snow has impact at Hurricane Ridge

Water equivalent well below average for February

Port Angeles secures grant to aid in salmon recovery

State Department of Commerce to provide city with $109,000

Tickets still available for United Way of Clallam County fundraiser

Pajamas are encouraged, teddy bears are optional and comfort… Continue reading

Interviews set for hospital board

At least seven candidates up for commissioner seat

Port Angeles asks for fee to cover lodging tax contracts

Resolution sent to committee for administrative costs

Climate action group is guiding reduction goals

Reduced emmissions require reduced transportation footprint