First Street paving postponed due to inclement weather forecast

PORT ANGELES — The First Street stormwater project may be slowed by a forecast of inclement weather, but the project remains on track to finish by the end of the month, a city engineer said.

Civil engineer Jim Mahlum said the contractor, Road Construction Northwest Inc., doesn’t plan to pave this week as initially scheduled because of a forecast of cold, wet weather during the evenings.

To lessen the impact on businesses, the city agreed to allow paving only during the evening and twilight hours.

Mahlum said weather has to be dry and no colder than 45 degrees for paving to occur.

The forecast calls for rain and temperatures in the low 40s at night through Saturday.

In the meantime, RCNI is installing new concrete crosswalks that will be stamped with a brick pattern.

But moisture also may be a problem for the concrete, Mahlum acknowledged.

He said he couldn’t estimate how long the weather may impact both the paving and crosswalk installation, but Mahlum added that the contractor still appears on target to finish by May 24.

“If we had perfect days, they would be ahead of schedule,” he said.

RCNI has until the end of June to finish the work.

The project started in late February.

It involved installing a new stormwater pipe between Valley and Laurel streets, which has been completed; paving both lanes of the road; adding bike lanes; and replacing crosswalks.

Valley-Cherry streets

A new crosswalk is being added between Valley and Cherry streets.

The city has budgeted $225,000 for the work, but the city expects the project to cost $2.25 million.

The National Park Service is picking up the rest of the bill because the project is part of its Elwha River restoration effort.

The First Street project is intended to remove enough stormwater from the city’s sewer system to offset the contribution of sewage from the Lower Elwha Klallam reservation.

The tribe will be connected to the city’s sewers because it’s expected that its septic tanks will become unusable as the ground­water level rises when the two Elwha River dams are removed.

That work was supposed to begin in March but has been delayed by up to 60 days. The delay is caused by the permitting process taking longer than expected, the Park Service has said.

The Park Service 
agreed to fund a stormwater disconnect project to offset the impact the additional wastewater would have on the city’s sewage overflow problem.

The sewer system is scheduled to be built summer 2012.

________

Reporter Tom Callis can be reached at 360-417-3532 or at tom.callis@peninsuladailynews.com.

More in News

“Angel” Alleacya Boulia, 26, of St. Louis, Mo., was last seen shopping in Port Angeles on Nov. 17, National Park Service officials said. Her rented vehicle was located Nov. 30 at the Sol Duc trailhead in Olympic National Park. (National Park Service)
Body of missing person found in Sol Duc Valley

Remains believed to be St. Louis woman

Dan Willis of Port Townsend, a docent at the Point Wilson Lighthouse at Fort Worden State Park, conducts a tour for interested visitors on Thursday. The lighthouse was built in 1878 when Congress approved $8,000 for the light and foghorns. Although the facility is still an active U.S. Coast Guard station, the equipment is monitored and operated remotely and no keepers are present. Regular tours on Saturdays and Sundays will resume in May. (Steve Mullensky/for Peninsula Daily News)
Lighthouse tour

Dan Willis of Port Townsend, a docent at the Point Wilson Lighthouse… Continue reading

EMT Teresa DeRousie, center, was recognized for her long service to Clallam County Fire District 2. Presenting the award were Deputy Fire Chief Kevin Denton, left, and Chief Jake Patterson. (Clallam County Fire District 2)
Clallam 2 Fire Rescue hosts awards banquet

Clallam 2 Fire-Rescue recognized career and volunteer members during… Continue reading

Construction set to begin on new marine life center in Port Angeles

Groundbreaking event scheduled for April 8 at Pebble Beach Park

A seal pops its head out of the water as a dory rower propels his craft in the calm waters of the Salish Sea. Whidbey Island is in the distance. Today’s high temperature is forecast to be in the low 50s with partly cloudy skies. Rain is set to return this weekend. (Steve Mullensky/for Peninsula Daily News)
Rowing on the Strait

A seal pops its head out of the water as a dory… Continue reading

Fire protection may impact insurance rates

New protection class considers nuanced data

The view looking south from Hurricane Ridge, where variable winter weather has limited snow coverage and contributed to pauses in snow sports operations in recent weeks. (Washington’s National Park Fund)
Lack of snow has impact at Hurricane Ridge

Water equivalent well below average for February

Port Angeles secures grant to aid in salmon recovery

State Department of Commerce to provide city with $109,000

Tickets still available for United Way of Clallam County fundraiser

Pajamas are encouraged, teddy bears are optional and comfort… Continue reading

Interviews set for hospital board

At least seven candidates up for commissioner seat

Port Angeles asks for fee to cover lodging tax contracts

Resolution sent to committee for administrative costs