Firm racing toward deadline on Port Townsend jetty

Underwater work must be done by Jan. 31

PORT TOWNSEND — The company in charge of constructing the new south jetty at Point Hudson Marina is doubling the number of its crew and shifting to a round-the-clock schedule in order to complete underwater work on the project by the end of the month.

Orion Marine Group is racing to meet a Jan. 29 deadline set by federal and state agency biologists when all in-water work must end. The date is an extension of the original Jan. 15 end-of-work window intended to minimize the impact of construction on salmon and other marine species.

Orion decided to switch to a 24-hour schedule with two crews working six days a week on back-to-back 12-hour shifts last week. The change will not affect the cost of the project, Port of Port Townsend Executive Director Eron Berg said.

“The contractor agreed to complete a scope of work within a time period, so they have control of the site and control of the work week,” Berg said. “It’s really been up to them to decide how they want to perform the work.”

Berg said Orion was finished pile driving but still needed to mount the waling beams and tie rods that help keep the piles in place.

“It’s getting all the steel in and making it secure so they can put that 5,000 tons of rock in,” he said. “Then in the month of February they’ll be able to do anything above the ordinary high water mark.”

Orion began work in September immediately after the Wooden Boat Festival ended. Although the weather has been fairly cooperative, Berg said there were elements of the south jetty that made the project more challenging than the north jetty that was completed ahead of schedule last January.

“It’s physically longer, it’s in deeper water, and there was also prepping to move a bunch of unsuitable material and replacing it with thousands of tons of bedding and armourstone,” Berg said.

Orion also had to bring back an impact hammer to drive about a dozen piles when a hydraulic vibrator was unable to penetrate the shoreline.

Berg said he believed the noise would be minimal, although there have been no complaints so far from neighbors during construction.

After the in-water work window closes, Orion will focus on the above-water portions of the project, like constructing the pedestrian walkway. All work must be completed by March 1, when Point Hudson is scheduled to re-open to marine traffic.

The port plans to hold an event in April to celebrate completion of both the north and south jetty projects.

Funding for the $14 million Point Hudson jetty replacement comes from a combination of federal, state, county and the port’s Industrial Development District levy.

________

Reporter Paula Hunt can be reached at paula.hunt@peninsuladailynews.com.

More in News

Dan Willis of Port Townsend, a docent at the Point Wilson Lighthouse at Fort Worden State Park, conducts a tour for interested visitors on Thursday. The lighthouse was built in 1878 when Congress approved $8,000 for the light and foghorns. Although the facility is still an active U.S. Coast Guard station, the equipment is monitored and operated remotely and no keepers are present. Regular tours on Saturdays and Sundays will resume in May. (Steve Mullensky/for Peninsula Daily News)
Lighthouse tour

Dan Willis of Port Townsend, a docent at the Point Wilson Lighthouse… Continue reading

EMT Teresa DeRousie, center, was recognized for her long service to Clallam County Fire District 2. Presenting the award were Deputy Fire Chief Kevin Denton, left, and Chief Jake Patterson. (Clallam County Fire District 2)
Clallam 2 Fire Rescue hosts awards banquet

Clallam 2 Fire-Rescue recognized career and volunteer members during… Continue reading

Construction set to begin on new marine life center in Port Angeles

Groundbreaking event scheduled for April 8 at Pebble Beach Park

A seal pops its head out of the water as a dory rower propels his craft in the calm waters of the Salish Sea. Whidbey Island is in the distance. Today’s high temperature is forecast to be in the low 50s with partly cloudy skies. Rain is set to return this weekend. (Steve Mullensky/for Peninsula Daily News)
Rowing on the Strait

A seal pops its head out of the water as a dory… Continue reading

Fire protection may impact insurance rates

New protection class considers nuanced data

The view looking south from Hurricane Ridge, where variable winter weather has limited snow coverage and contributed to pauses in snow sports operations in recent weeks. (Washington’s National Park Fund)
Lack of snow has impact at Hurricane Ridge

Water equivalent well below average for February

Port Angeles secures grant to aid in salmon recovery

State Department of Commerce to provide city with $109,000

Tickets still available for United Way of Clallam County fundraiser

Pajamas are encouraged, teddy bears are optional and comfort… Continue reading

Interviews set for hospital board

At least seven candidates up for commissioner seat

Port Angeles asks for fee to cover lodging tax contracts

Resolution sent to committee for administrative costs

Climate action group is guiding reduction goals

Reduced emmissions require reduced transportation footprint