At long last: Port Angeles to be whole again with new bridges

PORT ANGELES — After 1¬½ years of disruption of a major arterial through town, some four months of delays, and $24.6 million, the two bridges linking Eighth Street will open on Tuesday.

The bridges — which span the two ravines where the Tumwater and Valley creeks flow — will open to pedestrians at about 9 a.m.

It will open to vehicles at 2 p.m., after a brief ceremony at the intersection of Eighth and Cherry streets.

“Around City Hall, we are all celebrating,” said Port Angeles city spokeswoman Teresa Pierce, as she announced the reopening date on Friday.

“I don’t care if they have a procession,” said Steven Bridge, owner of three businesses between the two bridges — an area that has been isolated since work began.

“Just give me my traffic back.”

Traffic across the two ravines has been rerouted throughout town since 70-year-old wooden spans were demolished to allow them to be replaced by concrete structures.

The Tumwater Creek bridge was closed on Aug. 20, 2007. Its twin, the Valley Creek bridge, was closed on Sept. 24, 2007.

The new concrete bridges ¬­– which are 47 feet wide with two 12-foot lanes, two 5-foot bicycle lanes, two 6.5-foot sidewalks and two pedestrian viewpoints — replace the former trestle bridges built in 1936.

The project — initially expected to be completed last November — cost $21.6 million in state Department of Transportation grants and $3 million in city funds.

Glenn Cutler, city public works director, said on Saturday that the construction cost of the concrete bridges is between $18 million and $20 million.

The additional costs are of design and construction management, which is shared by the city and DOT, he said.

The city began planning for replacing the trestle bridges in 2003.

The new bridges were originally going to be made out of steel, but the design was changed because of the rising costs of that material.

Steel bridges would have raised construction costs over the $20 million limit for construction that was set by DOT.

Banner and first vehicles

Pierce said that, during the Tuesday ceremony, a long paper banner made by children in the city’s recreation programs will be cut to signal the opening of the bridges to vehicle traffic.

She said on Friday that it hadn’t been determined who will speak.

The first vehicles over the bridges will be a 1956 Los Angeles police car — offered by Sequim resident George Marsh — and the city’s newest police car and fire truck that will drive across the bridges from the ceremony.

The point is to represent the past and the present, Pierce said.

More work, more money

Although the bridges will be open, the work isn’t finished.

Since about the beginning of the year, the opening of the bridges has been delayed by concrete sealer application, and addition of a railing.

The railing was finished earlier this month.

Application of sealer — which protects the concrete from moisture and ensures easier removal of graffiti — still must be completed.

Applying the sealer requires a minimum air temperature of 35 degrees, less than 85 percent humidity and a dew point of no more than five points more than the minimal air temperature.

Completing the sealer-work with good weather will take about 10 days.

One bridge will be closed at a time while that is done — probably in late spring or early summer.

Cutler said on Friday that Parsons and the city agreed late Thursday afternoon to open the bridges before crews from Long Painting of Kent finish painting the sealer onto the bridges.

Doing so requires the city to modify its contract with Parsons.

Modifying the contract will cost the city $10,000, Cutler said.

Cutler said Parsons will cover any costs over that figure. He added that the additional costs will exceed $10,000.

“We’re sharing in the effort to get the bridges open,” he said.

Cutler said changes to Parsons’ contract have not been finalized.

The City Council will have to approve of the changes to the contract even though the bridges will open before its next meeting.

Cutler said he expects a contract amendment to be available for council consideration at its March 17 meeting.

Earlier delay

Before the sealer held up bridge work, delay was prompted by poor soil on the west side of the Tumwater Creek bridge, Cutler said in November.

That required a redesign of a foundation abutment that resulted in extending the contract with Parsons RCI Inc. of Sumner for 45 working days at a cost of $90,000.

Cutler said the city will also have to increase the cost of its contract with the project manager, Exeltech Consulting, Inc., because the project has gone on longer than anticipated.

But completing the sealer-work later this year will not require any additional cost to Exeltech’s contract because the company will not be on site during that time, he said.

Cutler said a figure has not been determined.

The city’s contract with Exeltech is for $1.94 million.

________

Reporter Tom Callis can be reached at 360-417-3532 or at tom.callis@peninsuladailynews.com.

More in News

Search and rescue teams locate deceased man

A deceased man was located following search and rescue… Continue reading

Anita La Salle, kneeling in the center, poses with her family of son, daughters, son-in-law and grandkids, all from Port Townsend, after spending Saturday on a scavenger hunt and celebrating a reunion to welcome a long-lost family member who hasn’t been seen in more than 50 years. The hunt originated at the Port Townsend Goodwill, where they each had to buy matching clothes, and took them to various venues around Port Townsend culminating at the anchor at Fort Worden State Park. This is the first Christmas they have all been together as a family. (Steve Mullensky/for Peninsula Daily News)
Family reunion

Anita La Salle, kneeling in the center, poses with her family of… Continue reading

Clallam seeking to extend contracts

Pacts would impact criminal justice in Port Angeles, Sequim

John Nutter.
Olympic Medical Center board commissioner dies at age 54

Nutter, police officer of year in 2010, also worked for hospital, port

State Patrol: Four injured after driver falls asleep at wheel

Four people were injured after a driver fell asleep… Continue reading

ODT near Hill Street reopens after landslide

The Olympic Discovery Trail between Hill Street and Marine… Continue reading

Justice Loftus holds up a dinosaur mask he received at the Winter Wishes assembly. He said he plans to use it to play with his younger brother. (Matthew Nash/Olympic Peninsula News Group)
Sequim High School assembly grants students’ requests

Annual assembly provides gifts via leadership class

Deb Carlson, president of the Sequim-Dungeness Hospital Guild, presents a check for $9,585 to Deputy Police Chief John Southard and City Manager Matt Huish to help purchase three automated external defibrillators (AEDs) for three new vehicles and new AED pads and first aid supplies for the full fleet. (Matthew Nash/Olympic Peninsula News Group)
Guild marks $2.5M in support for medical needs

Shop donations reopen in February, sales in March

Marylaura Ramponi stands by an excavator donated for geotechnical work at Sequim School District by Jamestown Excavating. She donated $1 million for the naming rights of the Ramponi Center for Technical Excellence, a career and technical education building that will be built in conjunction with new buildings at Sequim High School. (Matthew Nash/Olympic Peninsula News Group)
Progress begins on CTE building

Ramponi Center could be done by early 2028

Weekly flight operations scheduled

There will be field carrier landing practice operations for aircraft… Continue reading

Volunteers serve up a full breakfast on Christmas morning, for the Third Community Breakfast at the Fred Lewis Scout Cabin in Port Townsend put on by the Reach Out Community Organization, a homeless advocacy program. A full breakfast was served to about 150 people during the morning. On the serving line are, from the back, Rose Maerone, Marie France and Susan Papps. (Steve Mullensky/for Peninsula Daily News)
Festive breakfast

Volunteers serve up a full breakfast on Christmas morning, for the Third… Continue reading

Growler analysis report complete

Environmental Impact Statement and recommendations released