Jefferson: Airport taxiway, hangar construction delayed

PORT TOWNSEND — Although construction of new taxiways and hangar sites at Jefferson County International Airport is delayed until spring, infrastructure preparation work is expected to occur by year’s end, a Port of Port Townsend official said Thursday.

“I question whether we are going to be building a taxiway and hangars until next year,” Port Deputy Director Jim Pivarnik told Port commissioners on Wednesday.

However, Pivarnik said he spoke to U.S. Corps of Engineers officials Thursday who assured him permits will be arranged by the end of September.

Three weeks ago, the corps determined that the project would be “touching a wetland at the airport,” said Pivarnik.

Specifically, a drainage ditch running north and south under the center of the airport’s tarmac was determined to be a “jurisdictional wetlands.”

In the past, the Port had been allowed to fill in 1.3 acres to pave the runway.

Pivarnik said that Port staff did not realize the fill had taken place in 1997, when the corps turned up permit documentation revealing that action.

More in News

Climate action group is guiding reduction goals

Reduced emmissions require reduced transportation footprint

County, Port Angeles to rebid public safety building

Three bids rejected due to issue with electrical contractor

Aliya Gillet, the 2025 Clallam County Fair queen, crowns Keira Headrick as the 2026 queen during a ceremony on Saturday at the Clallam County Fairgrounds. At left is princess Julianna Getzin and at right is princess Jasmine Green. The other princesses, not pictured, are Makenzie Taylor, Molly Beeman and Tish Hamilton. (Dave Logan/for Peninsula Daily News)
Clallam County royalty crowned for annual fair

Silent auction raises funds for scholarships

Port Angeles Community Award recipients gather after Saturday night’s annual awards gala. From left, they are Frances Charles, Lower Elwha Klallam Tribe, Organization of the Year; Kyla Magner, Country Aire, Business of the Year; Amy Burghart and Doug Burghart, Mighty Pine Brewing, Emerging Business of the Year; Rick Ross, Educator of the Year; Kayla Fairchild, Young Leader of the Year; John Fox, Citizen of the Year. (Paula Hunt/Peninsula Daily News)
Community leaders honored at annual awards banquet

Fox named Citizen of Year for support of athletic events

Clallam County commissioners consider options for Owens

Supporters advocate for late state justice

Respiratory viruses are rising on the Peninsula

Health officer attributes increase to mutation of type of flu in circulation

Deadline for Olympic Medical Center board position is Thursday

The deadline to submit an application for the Position… Continue reading

No weekly flight operations scheduled this week

No field carrier landing practice operations are scheduled for aircraft… Continue reading

Some power restored after tree falls into line near Morse Creek

Power has been restored to most customers after a… Continue reading

Wendy Rae Johnson waves to cars on the north side of U.S. Highway 101 in Port Angeles on Saturday during a demonstration against U.S. Immigration and Customs Enforcement operations in Minnesota. On the other side of the highway is the Peninsula Handmaids in red robes and hoods. (Dave Logan/for Peninsula Daily News)
ICE protest

Wendy Rae Johnson waves to cars on the north side of U.S.… Continue reading

Jamestown Salish Seasons, a psychiatric evaluation and treatment clinic owned and operated by the Jamestown S’Klallam Tribe, tentatively will open this summer and offer 16 beds for voluntary patients with acute psychiatric symptoms. (Jamestown S’Klallam Tribe)
Jamestown’s evaluation and treatment clinic slated to open this summer

Administrators say facility is first tribe-owned, operated in state

North Olympic Library System staff closed the Sequim temporary library on Sunday to move operations back to the Sequim Avenue branch that has been under construction since April 2024. (North Olympic Library System)
Sequim Library closer to reopening date

Limited hours offered for holds, pickups until construction is complete