$164,800 to design footbridge? Port Angeles public works director defends cost, company’s history

PORT ANGELES — The city’s public works director found himself on the ropes at this week’s City Council meeting defending the allotment of $5.68 million in contracts to Exeltech Consulting Inc. over the last seven years and the use of the Lacey-based company for another upcoming project.

The questions over the use of the firm — which has overseen the construction of the Eighth Street bridges and The Gateway transit center — arose Tuesday when a proposed $164,800 contract for the design of a pedestrian bridge raised a few eyebrows.

“This seems like an awful lot of money for a pedestrian footbridge,” commented Council member Max Mania after the contract with Exeltech was pulled out of the consent agenda for discussion.

“It really seems excessive,” said Council member Cherie Kidd.

The council approved the contract in a 4-3 vote — with Kidd, Mania and Brad Collins opposed — after Public Works and Utilities Director Glenn Cutler defended the price tag.

Cutler said the bridge, which will be part of the Olympic Discovery Trail, will be 200 feet long and cross a 40-foot ravine over Dry Creek once it’s completed by the end of the year.

It will also carry a sewer line that will connect the Lower Elwha Klallam tribe to the city’s sewer system and electrical lines for two new treatment plants associated with the National Park Service’s Elwha Dam removal project.

When addressing concerns over the cost of the new contract Tuesday, he said that he was also surprised by the cost at first glance, and acknowledged, as Kidd pointed out, the bridge’s design will be about 25 percent of the bridge’s $673,100 total cost.

State grant funding and contributions from the tribe and Peninsula Trails Coalition will cover most of that cost, with the city’s total contribution coming in at about $230,000.

“I had similar questions as Kidd had when it was first brought to me on what the fee was,” said Cutler, referring to Exeltech’s contract.

He said that the “rule of thumb” is that the design cost for a construction project will be about 15 percent of the total budget.

But, Cutler added, overhead expenses tend to make up a larger portion of the budget for smaller projects such as this one. After vetting the contract, he said he was comfortable with its price tag.

Reason for contract

Council members Mania, Kidd, Collins and Pat Downie also questioned why the city needs to pay someone else to do this work and why some of Exeltech’s previous contracts did not stick to their original amount.

When addressing the reason for the contract, Cutler said it’s an issue of staffing — the city can’t afford the additional engineers.

He said the city interviewed two other applicants, Berger/Abam Engineering, Inc. and Claussen Engineering, for the contract, and Exeltech was determined to be the most qualified.

No bids were taken. Cutler said state law prohibits bids on “professional services.”

He also defended the allotment of construction management contracts to Exeltech for the Eighth Street bridges, The Gateway, and last year’s Peabody Street reconstruction projects after Collins questioned the ability of the company to come in under budget.

“I’m troubled by this decision I have to make tonight,” Collins said.

“It appears to me from past projects, that this firm has reaped cost overruns.”

Collins was referring to the construction of the Eighth Street bridges and The Gateway.

With the bridges, Exeltech’s original contract was for $2.7 million in 2006 and included bridge design and construction management.

Additional jobs

At the end of the project, the contract ended up being $4.94 million after the project timeline was lengthened and Exeltech was given additional jobs to complete.

Some of the additional work included redoing the design of the bridges once the city chose to use concrete rather than steel; designing a “wetland mitigation” plan; conducting a traffic analysis; the creation and monitoring of a storm water pollution prevention plan; and several other “unanticipated” documentation requirements, according to the eight contract amendments.

Due to additional work and a seven-month delay on construction of The Gateway, Exeltech’s contract for construction management of that project started at about $450,000 in 2007 and ended up being about $650,000.

Cutler acknowledged that there had been contract amendments with both projects, but he feels that they were justified.

The two bridges, which Cutler said were together ranked eighth in Roads and Bridges magazine’s list of top 10 bridge projects of 2008, were complete in February 2009, about three months passed the original deadline of November 2008. The Gateway was also scheduled to be completed the same month, but wasn’t open until June 2009.

Cutler didn’t blame Exeltech for the delays, and said the city needed to pay them more to cover additional work.

Completion of the bridges was first pushed back 45 days by “poor” soil at one end of a bridge and later by weather-related delays as the project pushed into winter.

The Gateway was delayed due to cracks that developed underneath a horizontal support beam.

Cutler told the PDN that Exeltech can’t be blamed for that delay, since the cracks developed due to a failure in design and the company began managing construction after the design had been approved.

Exeltech was also paid $50,650 for management of the Peabody Street reconstruction project; $53,500 as an engineering consultant for designing a wider Lauridsen Boulevard bridge near Race Street; and $15,840 to help the city put together a large grant application.

Exeltech could not be reached for comment Wednesday.

________

Reporter Tom Callis can be reached at 360-417-3532 or at tom.callis@peninsuladailynews.com.

More in News

Remains in shoe determined to belong to a bear

A shoe found earlier this week on the beach at… Continue reading

Patrick Zolpi-Mikols, a park aide with Fort Worden State Park, gathers and removes leaves covering the storm drains after an atmospheric river rainstorm early Wednesday morning in Port Townsend. A flood warning was issued by the National Weather Service until 11:11 a.m. today for the Elwha River at the McDonald Bridge in Clallam County. With the flood stage at 20 feet, the Elwha River was projected to rise to 23.3 feet late Wednesday afternoon and then fall below flood stage just after midnight. (Steve Mullensky/for Peninsula Daily News)
Cleaning storm drains

Patrick Zolpi-Mikols, a park aide with Fort Worden State Park, gathers and… Continue reading

Woman files suit against city of Port Angeles

Document alleges denial of constitutional rights

State report shows clean audit of Port of Port Angeles finances

Commissioners review five-year strategic plan

Port Townsend School District’s Food Service Director Shannon Gray in the Salish Coast production garden’s hoop house. (Elijah Sussman/Peninsula Daily News)
Port Townsend schools’ food program thriving

Staff growing produce, cooking meals from scratch

Brake failure leads to collision on west end of Hood Canal Bridge

A semi-truck towing a garbage truck suffered brake failure and… Continue reading

A two-car collision at U.S. Highway 101 and state Highway 112 partially blocked traffic for more than an hour on Tuesday. One person was transported to Olympic Medical Center, Clallam 2 Fire-Rescue said. (Clallam 2 Fire-Rescue)
Collision blocks traffic at highways 101, 112

One person was transported to Olympic Medical Center following… Continue reading

Library system to host gift-wrapping workshops

The North Olympic Library System will host free “Wrap… Continue reading

Shoe with human remains found on Sequim beach

A shoe containing human remains was found on the beach… Continue reading

Sue Bahl walks with an umbrella on West Eighth Street on Monday. Heavy rainfall up to 8 inches over the past several days has increased the threat of landslides in Western Washington, according to the National Weather Service. A flood watch also has been issued until 4 p.m. Friday for portions of northwest and west central Washington, including Clallam and Jefferson counties. Sharp rises in rivers, especially those flowing off the Olympics and Cascades, are expected, the National Weather Service said. (Dave Logan/for Peninsula Daily News)
Atmospheric river

Sue Bahl walks with an umbrella on West Eighth Street on Monday.… Continue reading

Clallam board approves budget, homelessness task force funds

County OKs eight proposals for housing, assistance

Five-year plan to address Jefferson County homelessness

Action steps assigned to jurisdictions, providers