Phone cable snafu: Downtown Port Townsend work completion date pushed back again

PORT TOWNSEND — A delay in telephone cable delivery will push the expected completion of the Taylor Street renovation project back at least a few weeks.

Work on Taylor Street between Washington Street and Union Wharf originally was expected to be completed by the end of May, but that date was pushed back to the end of this month.

Now it is not expected to be finished until sometime in July, according to officials for both the city of Port Townsend and the phone service provider.

City Manager David Timmons said the delay will not affect the reopening of Taylor Street to vehicle traffic, still expected to occur later this month.

One layer of asphalt is still required, along with the marking of parking spaces on both sides of the street.

Timmons said telephone vendor CenturyLink informed the city last week that the necessary cable would not be available in time for the planned removal of utility poles on the west side of the street.

All but two of the poles on the east side, which held electrical and cable television wires, were removed Friday.

The conduits for the telephone cables were put in place when the sidewalk was replaced during the renovation project, which began in February.

Timmons was on location Friday and expressed frustration about the delay.

“They’ve known for months that we were going to need this cable,” he said.

“We’ve had meeting after meeting after meeting, so you’d think they would have gotten the cable.

”They just forgot to order it.”

CenturyLink spokesman Jan Kampbell contradicted this, saying the company could not order the cable until it had notice of the exact quantity needed.

That was supplied by the city at the end of May, she said.

“As soon as we received the information from the city, we placed the order,” she said.

“It should be here any day now.”

Once the cable arrives, it will be threaded through the conduit.

The existing phone cables then will be disconnected and hooked up to the new cables, which will cause a short interruption in phone service.

CenturyLink will then remove the poles, which they own.

There is one electrical cable on the west side of the street that will be rerouted at that time, Timmons said.

Kampbell said she thought the poles would be removed in early July.

The city project is estimated to cost a total of $3.5 million: $2 million for sidewalk and street repair — 87 percent of which is covered by federal grants — and $1.5 million for the placement of utility lines underground, which is a cost borne entirely by the city.

Even as Timmons expressed displeasure about the delay, several people congratulated him for the work that has been done so far.

“It’s a fabulous project,” said Port Townsend Film Festival Executive Director Janette Force.

“It’s such a visual relief, even as it is now.”

________

Jefferson County Reporter Charlie Bermant can be reached at 360-385-2335 or at charlie.bermant@peninsuladailynews.com.

More in News

Holiday lights reflect off the water at Boat Haven in Port Angeles. (Dave Logan/for Peninsula Daily News)
Holiday reflections

Holiday lights reflect off the water at Boat Haven in Port Angeles.… Continue reading

Clallam extends public defense

Contract agreement is through February

Celebration of life set Super Bowl Sunday

Messages continue to arrive for John Nutter

Committee members sought for ‘For’ and ‘Against’ statements

The Clallam County commissioners are seeking county residents to… Continue reading

Search and rescue teams locate deceased man

A deceased man was located following search and rescue… Continue reading

Anita La Salle, kneeling in the center, poses with her family of son, daughters, son-in-law and grandkids, all from Port Townsend, after spending Saturday on a scavenger hunt and celebrating a reunion to welcome a long-lost family member who hasn’t been seen in more than 50 years. The hunt originated at the Port Townsend Goodwill, where they each had to buy matching clothes, and took them to various venues around Port Townsend culminating at the anchor at Fort Worden State Park. This is the first Christmas they have all been together as a family. (Steve Mullensky/for Peninsula Daily News)
Family reunion

Anita La Salle, kneeling in the center, poses with her family of… Continue reading

Clallam seeking to extend contracts

Pacts would impact criminal justice in Port Angeles, Sequim

John Nutter.
Olympic Medical Center board commissioner dies at age 54

Nutter, police officer of year in 2010, also worked for hospital, port

State Patrol: Four injured after driver falls asleep at wheel

Four people were injured after a driver fell asleep… Continue reading

ODT near Hill Street reopens after landslide

The Olympic Discovery Trail between Hill Street and Marine… Continue reading

Justice Loftus holds up a dinosaur mask he received at the Winter Wishes assembly. He said he plans to use it to play with his younger brother. (Matthew Nash/Olympic Peninsula News Group)
Sequim High School assembly grants students’ requests

Annual assembly provides gifts via leadership class

Deb Carlson, president of the Sequim-Dungeness Hospital Guild, presents a check for $9,585 to Deputy Police Chief John Southard and City Manager Matt Huish to help purchase three automated external defibrillators (AEDs) for three new vehicles and new AED pads and first aid supplies for the full fleet. (Matthew Nash/Olympic Peninsula News Group)
Guild marks $2.5M in support for medical needs

Shop donations reopen in February, sales in March