How bad is the gateway problem? Meeting this week to study crack in support wall

PORT ANGELES — Key parties in the design and construction of The Gateway transit center will study cracking in a foundation wall this week to determine how long the multimillion-dollar project remains on hold.

The financial implications of recent delays in construction of The Gateway are yet to be known, said Glenn Cutler, Port Angeles city public works director.

Completion of the project is on hold while engineers determine if cracking in the eastern foundation wall of the pavilion means that the structure, which is the roof of a parking garage, can’t support a planned second pour of concrete.

Cutler said on Friday that he is “cautiously optimistic” that the project will be completed in early- to mid-December.

The project, which began in June 2007, was expected to be completed this month. Its initial completion date was early September.

Cutler said the project at this time remains within its $14.7 million budget, which includes a contingency fund for cost overruns.

The Gateway is a joint project between the city of Port Angeles and Clallam Transit, which has $8.16 million in state and federal grant funding.

Design features

It includes a bus stop, parking garage, a pavilion, a four-faced clock tower, a break room for bus drivers, an office for downtown police officers and rest rooms.

The Gateway is located between Front and First streets and Lincoln and Laurel streets in downtown Port Angeles.

At their monthly meeting Thursday, representatives from the city of Port Angeles, Clallam Transit, Krei Architecture and Primo Construction are expected to determine if the cracking represents a structural problem.

Cutler said he will have a better idea of how this delay will affect the cost of the project after next week.

“I don’t know what, if anything, will be the financial impacts on the project,” he said.

“I don’t want to speculate either.”

Cutler said Krei, which is responsible for the design of The Gateway, has told the city that the cracking will not be a problem, but the city is using its own staff and engineering consultants to confirm it.

“They indicated to us that it is acceptable, and we can continue to work,” he said.

“But we don’t just accept that as, it’s OK. We are doing our due diligence to verify. It’s almost like a peer review.”

Cutler said the city consults with the engineering firm Zenovic and Associates in Port Angeles on these issues.

If a structural problem is discovered, Cutler said he couldn’t estimate how long the project would take to complete.

Process

The cracking occurred as a result of a technique known as “post tensioning” that is used in the horizontal concrete beam that supports the pavilion over parking spaces underneath, he said.

Steel wires within the concrete are pulled taunt, which gives the structure more support.

Cutler said this allows the structure to span a larger area and support more weight.

“Cracking is not unusual in this case,” he said.

Cutler said that about everything has been completed, except for the second pour of concrete on the pavilion floor.

The last pour will provide a slope for water drainage and a pattern for the pavilion floor.

Cutler said that poor weather shouldn’t delay pouring the concrete, as long as it doesn’t rain too hard.

In August, the City Council approved paying Krei an additional $90,960 for continuing its design and architectural review services during the delays.

________

Reporter Tom Callis can be reached at 360-417-3532 or tom.callis@peninsuladailynews.com.

More in News

Dan Willis of Port Townsend, a docent at the Point Wilson Lighthouse at Fort Worden State Park, conducts a tour for interested visitors on Thursday. The lighthouse was built in 1878 when Congress approved $8,000 for the light and foghorns. Although the facility is still an active U.S. Coast Guard station, the equipment is monitored and operated remotely and no keepers are present. Regular tours on Saturdays and Sundays will resume in May. (Steve Mullensky/for Peninsula Daily News)
Lighthouse tour

Dan Willis of Port Townsend, a docent at the Point Wilson Lighthouse… Continue reading

EMT Teresa DeRousie, center, was recognized for her long service to Clallam County Fire District 2. Presenting the award were Deputy Fire Chief Kevin Denton, left, and Chief Jake Patterson. (Clallam County Fire District 2)
Clallam 2 Fire Rescue hosts awards banquet

Clallam 2 Fire-Rescue recognized career and volunteer members during… Continue reading

Construction set to begin on new marine life center in Port Angeles

Groundbreaking event scheduled for April 8 at Pebble Beach Park

A seal pops its head out of the water as a dory rower propels his craft in the calm waters of the Salish Sea. Whidbey Island is in the distance. Today’s high temperature is forecast to be in the low 50s with partly cloudy skies. Rain is set to return this weekend. (Steve Mullensky/for Peninsula Daily News)
Rowing on the Strait

A seal pops its head out of the water as a dory… Continue reading

Fire protection may impact insurance rates

New protection class considers nuanced data

The view looking south from Hurricane Ridge, where variable winter weather has limited snow coverage and contributed to pauses in snow sports operations in recent weeks. (Washington’s National Park Fund)
Lack of snow has impact at Hurricane Ridge

Water equivalent well below average for February

Port Angeles secures grant to aid in salmon recovery

State Department of Commerce to provide city with $109,000

Tickets still available for United Way of Clallam County fundraiser

Pajamas are encouraged, teddy bears are optional and comfort… Continue reading

Interviews set for hospital board

At least seven candidates up for commissioner seat

Port Angeles asks for fee to cover lodging tax contracts

Resolution sent to committee for administrative costs

Climate action group is guiding reduction goals

Reduced emmissions require reduced transportation footprint