Work begins again on The Gateway

PORT ANGELES — After three months of little or no activity, workers returned Wednesday to complete The Gateway.

Completion of the downtown $14.7 million transportation center, a joint project of the city of Port Angeles and Clallam Transit, had been on hold since November — when it was scheduled to be completed — while a crack in a foundation wall was analyzed.

The city gave Primo Construction the go-ahead to finish the project on Friday after an independent engineering review declared that it can be safely finished.

The project could be finished in three to four weeks, if all goes well, said Roland Ordona, site superintendent.

The independent engineering review from Berger/Abam Engineers Inc. of Federal Way determined that the cause of the cracking was stress placed on a reinforcing steel beam, said Glenn Cutler, city public works director.

He said repairs for the wall, and determination of who is liable for the problem, have not been decided.

Cutler said a report from Krei Architecture, which designed The Gateway, and its sub-contractor, Bright Engineering, will make that determination.

He said he expects it within seven to 10 days.

The project — at Front and Lincoln streets and Railroad Avenue — includes a transit center, parking garage, pavilion and police substation.

It is paid for with $8.1 million in state and federal grants, $6.1 million in city funds and $500,000 from Clallam Transit.

Glad to get it done

Ordona was happy to be back at work on Wednesday.

“Oh, I’m so glad to be doing something,” he said. “I’m glad to be getting it done, glad we got OK’d to finish.”

The work on Wednesday consisted of pouring 12 cubic yards of concrete on a pedestrian bridge and ramp.

Pouring of the concrete on the bridge, ramp and plaza floor are the last major items that need to be done before the project is completed.

That work has been on hold since September, when cracking underneath a horizontal support beam in the eastern foundation wall of the pavilion –where the plaza is located — was discovered.

Ordona said the concrete pouring can be completed in 2¬½ weeks if weather is cooperative.

The air temperature has to be at least 35 degrees, he said, for the concrete to cure.

It also can’t rain.

Workers on Wednesday were using heating blankets and portable heaters to ensure that the concrete cures.

Ordona said the final work will be the installation of railing on the plaza. That will be done in about a week after the concrete cures.

Crack

The crack in the foundation occurred because of the “post-tensioning process” used in the horizontal concrete beams that support the pavilion, Cutler said.

In this method, intended to add strength, steel wires within the concrete are pulled taut.

Cutler said that the wall was not able to flex when this occurred.

Nathan West, city economic and community development director, said the city did not receive answers from Krei to questions relating to the cause of the cracking, and he has not received an explanation as to why the architecture firm could not address that issue.

“I have no explanation from Krei at this point,” he said.

West said the city’s primary goal was ensuring that the project meets the building code standards and is therefore safe to complete.

“We’re happy it is going in that direction,” he said.

Berger/Abam Engineers Inc. was hired by Clallam Transit’s attorney, Craig Miller, in December.

Miller has said he hired Berger/Abam to provide engineering and legal consultation and declined to elaborate further.

Terry Weed, Clallam Transit general manager, has cited attorney-client privilege when declining to provide any additional information on the subject.

City Manager Kent Myers, West and Cutler have all said they can’t comment on Berger/Abam’s contract with Miller.

“We didn’t need to have an explanation from him,” Cutler said. “He works for Clallam Transit.”

Miller said last week that Berger/Abam has billed him $13,815 for services, and he will ask for reimbursement from the Clallam Transit board at its Feb. 16 meeting.

If the board approves reimbursement, the money would have to come from the city because of its interlocal agreement for the project with Clallam Transit.

The agreement says that the city would cover additional costs if Clallam Transit has spent its grant funding and $500,000 contribution.

Weed has said those funds have been spent.

Money spent

City Finance Director Yvonne Ziomkowski said in November that the project had exceeded its $13.8 million estimate but had not gone over its $14.7 million budget.

Additional costs to The Gateway, because of the delay, will be determined by the cost of engineering consultation with Berger/Abam and Zenovic and Associates, which is the city’s consultant, the cost of repairing the wall and additional work for Primo.

Although Primo ran out of contracted working days in November, Ordona said the company won’t seek much additional reimbursement.

Ordona said Primo will seek compensation for the cost of time and materials related to conducting the concrete pouring in the winter rather than in September, when it was scheduled, but not for additional working days.

________

Reporter Tom Callis can be reached at 360-417-3532 or at tom.callis@peninsuladailynews.com.

More in News

Mark Gregson.
Interim hospital CEO praises partnership, legacy

Gregson says goal is to solidify pact with UW Medicine in coming months

Jefferson County Auditor Brenda Huntingford, right, watches as clerk Ronnie Swafford loads a stack of ballots that were delivered from the post office on Tuesday into a machine that checks for signatures. The special election has measures affecting the Port Townsend and Brinnon school districts as well as East Jefferson Fire Rescue. (Steve Mullensky/for Peninsula Daily News)
Jefferson County voters supporting school district measures, fire lid lifts

Port Townsend approving 20-year, $99.25 million construction bond

Port of Port Townsend Harbormaster Kristian Ferrero, right, watches as a crew from Seattle Global Diving and Salvage work to remove a derelict catamaran that was stuck in the sand for weeks on a beach at the Water Front Inn on Washington Street in Port Townsend. The boat had been sunk off of Indian Point for weeks before a series of storms pushed it to this beach last week. (Steve Mullensky/for Peninsula Daily News)
Derelict boat removal

Port of Port Townsend Harbormaster Kristian Ferrero, right, watches as a crew… Continue reading

Rob Birman has served as Centrum’s executive director for 14 years. When the arts nonprofit completes its search for its next leader, Birman will transition into a role focused on capital fundraising and overseeing capital projects for buildings Centrum oversees. (Centrum)
Centrum signs lease to remain at Fort Worden for next 35 years

Executive director will transition into role focused on fundraising

Clallam approves contracts with several agencies

Funding for reimbursement, equipment replacement

Mark and Linda Secord have been named Marrowstone Island Citizens of the Year for 2025.
Secords named Marrowstone Island citizens of year

Mark and Linda Secord have been chosen as Marrowstone… Continue reading

The members of the 2026 Rhody Festival royalty are, from left, Princess Payton Frank, Queen Lorelei Turner and 2025 Queen Taylor Frank. The 2026 queen was crowned by the outgoing queen during a ceremony at Chimacum High School on Saturday. (Steve Mullensky/for Peninsula Daily News)
Rhody coronation

The members of the 2026 Rhody Festival royalty are, from left, Princess… Continue reading

Jefferson considering new site for solid waste

Commissioners direct further exploration

Public feedback still shaping Clallam ordinance on RV usage

Community Development department set to move sections of its proposal

Jen Colmore, Sequim Food Bank’s community engagement coordinator, has been hired as the executive director. She will start in her new role after outgoing director Andra Smith starts as executive director of the Washington Food Coalition later this month. (Sequim Food Bank)
Sequim Food Bank hires new executive director

Sequim organization tabs engagement coordinator

Sara Nicholls, executive director of the Dungeness Valley Health and Wellness Clinic, also known as the Sequim Free Clinic, inspects food items that are free to any patient who needs them. Soroptimist International of Sequim sponsors the food pantry, she said. (Austin James)
Sequim Free Clinic to celebrate 25th year

Volunteer-driven nonprofit will reach quarter-century mark in October

Weekly flight operations scheduled

Field carrier landing practice operations will take place for aircraft… Continue reading