Port of Port Angeles approves $1.6 million dredging contract

PORT ANGELES —Port of Port Angeles commissioners have approved a $1.6 million low-bid dredging contract that exceeds the budgeted amount by more than 50 percent — but could be far less depending on transportation costs.

When completed, the deeper waters will make ship captains less hesitant about the possibility of hitting bottom at Terminal 3 in Port Angeles Harbor, a Port of Port Angeles official said Tuesday.

“Over the past 40-plus years, sediment has deposited in the berth, decreasing the berth depth to the point where vessel captains have concerns about touching bottom during low tide,” said port Director of Engineering Chris Hartman in a staff report.

“To compound this issue, over the last ten years there has been a trend for larger bulk cargo vessels with deep drafts.”

Port commissioners learned the project at Terminal 3 already has cost $300,000 for design, sediment-core testing and permitting not included in the agreement that they unanimously approved Tuesday with Stayton, Ore.-based Legacy Contracting.

The cost also could range between $1.3 million and $1.8 million depending upon the amount of polluted sediment that must be trucked to a landfill — likely the privately held Roosevelt Regional Landfill south of Yakima — as opposed to depositing it as fill for the port’s Marine Trades Industrial Park.

The sediment, which contains polychlorinated biphenyls, pesticides, dioxins and metals, includes tributyltin, aromatic hydrocarbons and dioxins/furans that exceeded the Dredged Material Management Program, administered by state and federal agencies.

Those levels makes at least some of that sediment unsuitable for open water disposal, according to the port’s Seattle-based environmental consulting firm, Floyd-Snider.

The project had been budgeted for $1 million that was to be drawn from the capital budget.

Instead, costs will be covered by the operating budget because the port does not own the underlying land, Hartman said.

Hartman said project expenditures that exceed the $1 million budgeted amount will come out of port reserves.

“There are no funding partners or loans,” he said.

Hartman said Thursday the cost exceeded the budgeted amount due to factors including the estimated dredge quantity increasing from 13,000 cubic yards to 15,000 cubic yards.

The $1.6 million contract assumes 3,000 cubic yards, or 5,000 tons, will need to be trucked away.

In addition, an engineer’s estimate that turned out to be low was not completed until after the budget was developed, Hartman said.

“There was a lot of additional soil testing that was not anticipated, not finalized, until after final approval from [the Department of] Ecology,” he said.

The $300,000 for design and other costs came out of 2017-2019 operating funds.

If 5,000 tons are trucked there, it will cost $1.77 million.

If no material is trucked to the landfill, the project will cost $1.27 million.

Legacy’s bid was $500,000 under that of Vancouver, Wash.-based Keiwit Infrastructure West Company, the high bidder among three companies that vied for the project.

American Construction Company Inc. of Tacoma submitted a $1.6 million proposal, just $130,000 more than Legacy’s.

“Legacy’s rate to dredge and haul and dispose on the upland is much lower than Keiwit’s,” Hartman explained to commissioners Steven Burke, Connie Beauvais and Colleen McAleer.

The port’s primary cargo-loading site, built in the late 1960s, was last dredged to minus 45 feet more than four decades ago, in 1978.

Dredging to a depth of minus 45 feet average low tide is scheduled for July 20-Sept. 4, but is permitted for July 15, 2020-Feb. 15, 2021.

According to the contract with Legacy, off-site transportation and disposal of up to 5,000 tons of dredged material will account for $460,000 of the contract, the second highest cost next to $578,000 in dredging and stockpiling costs. Mobilization and demobilization is $395,000.

________

Senior Staff Writer Paul Gottlieb can be reached at 360-452-2345, ext. 55650, or at pgottlieb@peninsuladailynews.com.

More in News

From left to right are Indigo Gould, Hazel Windstorm, Eli Hill, Stuart Dow, Mateu Yearian and Hugh Wentzel.
Port Townsend Knowledge Bowl team wins consecutive state championships

The Knowledge Bowl team from Port Townsend High School has… Continue reading

Bob Edgington of 2 Grade LLC excavating, which donated its resources, pulls dirt from around the base of an orca sculpture at the Dream Playground at Erickson Playfield on Thursday during site preparation to rebuild the Port Angeles play facility, which was partially destroyed by an arson fire on Dec. 20. A community build for the replacement playground is scheduled for May 15-19 with numerous volunteer slots available. Signups are available at https://www.signupgenius.com/go/904084DA4AC23A5F85-47934048-dream#/. (Keith Thorpe/Peninsula Daily News)
Site preparation at Dream Playground

Bob Edgington of 2 Grade LLC excavating, which donated its resources, pulls… Continue reading

Rayonier Inc. is selling more than 115,000 acres in four units across the West Olympic Peninsula last week as the company looks to sell $1 billion worth of assets. (Courtesy photo / Rayonier Inc.)
Rayonier to sell West End timberland

Plans call for debt restructuring; bids due in June

Port Angeles port approves contract for Maritime Trade Center bid

Utilities installation, paving part of project at 18-acre site

Port Angeles to hire personnel to operate day ambulance

The Port Angeles Fire Department will be able to… Continue reading

Port Angeles City Hall parking lot closed for construction

Work crews from Bruch and Bruch Construction, Inc. will… Continue reading

Teen photo contest open for submissions

The Jefferson County Library is accepting submissions for Teen… Continue reading

Letters of inquiry for grant cycle due May 15

The Olympic View Community Foundation and the Seattle Foundation will… Continue reading

Amy DeQuay of Port Angeles, right, signs up for information at a table staffed by Christopher Allen and Mary Sue French of the Port Angeles Arts Council during a Volunteer Fair on Wednesday at Vern Burton Community Center in Port Angeles. The event, organized by the Port Angeles Chamber of Commerce, brought together numerous North Olympic Peninsula agencies that offer people a chance to get involved in their communities. (Keith Thorpe/Peninsula Daily News)
Volunteer fair in Port Angeles

Amy DeQuay of Port Angeles, right, signs up for information at a… Continue reading

Luncheon to raise funds for women with cancer

The Kathleen Sutton Fund will host its third spring… Continue reading

Among those volunteering are rowers from Port Townsend, Port Angeles and Sequim. Pictured from left to right are WendyRae Johnson of Port Angeles; Gail Clark and Lynn Gilles, both of Sequim, Jean Heessels-Petit of Sequim; Christi Jolly, Dennis Miller, Carolyn DeSalvo and Frank DeSalvo, all of Sequim; and Rudy Heessels, Amy Holms and Guy Lawrence, all of Sequim.
Sequim Bay Yacht Club to host opening day ceremonies

The Sequim Bay Yacht Club will host free boat rides… Continue reading

Serve Washington presented service award

Serve Washington presented its Washington State Volunteer Service Award to… Continue reading