Keith Parker

Keith Parker

Port Angeles drainage tank work done; testing continues

PORT ANGELES — When it’s preparing to do its job, the nearly eight-story-high, 14-foot-wide column built in the center of the city’s 5 million-gallon storage tank on Rayonier’s former mill property feels like a rocket about to take off.

Looking down from the top of the concrete structure during a recent test, it sort of looks like one, too.

The column, construction on which wrapped up in December, and the metal gangway leading to it shudder as the structure prepares to release roughly 20 vertical feet of water stored within.

The shaking then stops, and the only noise that can be heard is the water flowing across the bottom of the tank into a moat built around the inside of the tank’s base.

CSO project

From there, it’s taken to the city’s nearby water treatment plant in a process that will eventually play a key role in the city’s $42 million combined sewer overflow, or CSO, project.

“The CSO tank has been successfully tested,” City Engineer Mike Puntenney said.

“The tank works as it was designed to.”

Testing of the tank’s flush column has been underway since the beginning of this month, city project manager James Burke said, and is expected to be wrapped up in the coming week as part of the $16.7 million first phase of the CSO project.

The city expects crews from Ferndale-based IMCO General Construction to be completely off-site by the end of February, Puntenney said.

IMCO has been working since September 2012 on the project, which also snaked new underground stormwater and wastewater lines across the Rayonier Inc. property to downtown Port Angeles.

Tank’s operation

The city anticipates the tank can be operational after permitting for phase one is finished, estimated at between three to six months, Puntenney said.

The tank will not be able to take stormwater and sewage from the downtown area until a new pump station, part of phase two of the CSO project, is built at the west end of Front Street, Puntenney explained.

The city has an application in for a roughly $11 million low-interest state loan for phase two, Puntenney said, which the city expects to hear about in the coming months.

The goal of the CSO project, slated to be completed by 2016, is to increase sewage and stormwater capacity between downtown and the wastewater treatment plant to reduce the number of CSO events that historically have sent untreated sewage into Port Angeles Harbor during heavy storms.

During these times, the tank will take sewage and stormwater from the city’s downtown area and hold it until it can be treated at the nearby treatment plant and released into the harbor, Burke explained.

Flow into tank

Depending on the amount of rainfall, water would flow into the tank at between 5,000 and 20,000 gallons per minute, said Keith Parker, the on-site CSO project manager with Vanir Construction Management Inc.

At the highest flow, that’s enough water to fill Port Angeles’ 200,000-gallon William Shore Memorial Pool once every 10 minutes.

The water in the flush column is released to clear sediment and other residue from the floor of the tank after it has stored sewage and stormwater, Burke said.

The water used to test the flush column has already been treated, Burke said, though the column will use the same water the tank will store to clear the tank’s bottom when officially brought online.

The flushing is triggered automatically after the tank empties, Burke added.

Water cannons

The tower also is equipped with four water cannons city crews will use to spray down the sides of the tank as needed after the tank is drained following a heavy storm.

“Most of our CSO events take place in the wintertime,” Burke said. “The chance of odor is unlikely.”

Parker estimated that water would not be held in the tank for more than a couple of days at the most.

The state Department of Ecology has given the city until 2016 to complete the CSO project or face fines of up to $10,000 for each additional combined sewer overflow that happens after the deadline.

________

Reporter Jeremy Schwartz can be reached at 360-452-2345, ext. 5074, or at jschwartz@peninsuladailynews.com.

More in News

Jefferson County Auditor Brenda Huntingford, right, watches as clerk Ronnie Swafford loads a stack of ballots that were delivered from the post office on Tuesday into a machine that checks for signatures. The special election has measures affecting the Port Townsend and Brinnon school districts as well as East Jefferson Fire Rescue. (Steve Mullensky/for Peninsula Daily News)
Jefferson County voters supporting school district measures, fire lid lifts

Port Townsend approving 20-year, $99.25 million construction bond

Port of Port Townsend Harbormaster Kristian Ferrero, right, watches as a crew from Seattle Global Diving and Salvage work to remove a derelict catamaran that was stuck in the sand for weeks on a beach at the Water Front Inn on Washington Street in Port Townsend. The boat had been sunk off of Indian Point for weeks before a series of storms pushed it to this beach last week. (Steve Mullensky/for Peninsula Daily News)
Derelict boat removal

Port of Port Townsend Harbormaster Kristian Ferrero, right, watches as a crew… Continue reading

Rob Birman has served as Centrum’s executive director for 14 years. When the arts nonprofit completes its search for its next leader, Birman will transition into a role focused on capital fundraising and overseeing capital projects for buildings Centrum oversees. (Centrum)
Centrum signs lease to remain at Fort Worden for next 35 years

Executive director will transition into role focused on fundraising

Clallam approves contracts with several agencies

Funding for reimbursement, equipment replacement

Mark and Linda Secord have been named Marrowstone Island Citizens of the Year for 2025.
Secords named Marrowstone Island citizens of year

Mark and Linda Secord have been chosen as Marrowstone… Continue reading

The members of the 2026 Rhody Festival royalty are, from left, Princess Payton Frank, Queen Lorelei Turner and 2025 Queen Taylor Frank. The 2026 queen was crowned by the outgoing queen during a ceremony at Chimacum High School on Saturday. (Steve Mullensky/for Peninsula Daily News)
Rhody coronation

The members of the 2026 Rhody Festival royalty are, from left, Princess… Continue reading

Jefferson considering new site for solid waste

Commissioners direct further exploration

Public feedback still shaping Clallam ordinance on RV usage

Community Development department set to move sections of its proposal

Jen Colmore, Sequim Food Bank’s community engagement coordinator, has been hired as the executive director. She will start in her new role after outgoing director Andra Smith starts as executive director of the Washington Food Coalition later this month. (Sequim Food Bank)
Sequim Food Bank hires new executive director

Sequim organization tabs engagement coordinator

Sara Nicholls, executive director of the Dungeness Valley Health and Wellness Clinic, also known as the Sequim Free Clinic, inspects food items that are free to any patient who needs them. Soroptimist International of Sequim sponsors the food pantry, she said. (Austin James)
Sequim Free Clinic to celebrate 25th year

Volunteer-driven nonprofit will reach quarter-century mark in October

Weekly flight operations scheduled

Field carrier landing practice operations will take place for aircraft… Continue reading

“Angel” Alleacya Boulia, 26, of St. Louis, Mo., was last seen shopping in Port Angeles on Nov. 17, National Park Service officials said. Her rented vehicle was located Nov. 30 at the Sol Duc trailhead in Olympic National Park. (National Park Service)
Body of missing person found in Sol Duc Valley

Remains believed to be St. Louis woman