Point Hudson Marina project delayed at least a year

QUILCENE — Construction of a Point Hudson Marina moorage and facilities improvement project must wait at least a year because Port of Port Townsend officials have hit snags involving dredging and timing.

The result, said Port Executive Director Larry Crockett, is delaying construction until after the 2006 Wooden Boat Festival.

“People say, ‘I thought you are going to have all the dock in this winter,”‘ Crockett told Port commissioners Wednesday.

“Well, this is Washington state and we have to do certain permits.”

Process taking longer

During a Port commissioners meeting at the Quilcene Harbor Yacht Club on Quilcene Bay, Deputy Director Jim Pivarnik said Corps of Engineers approval of dredging proposed near the marina entrance was taking far longer than anticipated.

“What we thought would be a 30-day process has turned into a four-month process,” Pivarnik said.

The Corps of Engineers must review Port engineers’ proposal, plus marina dredge samples were required, said Pivarnik.

He added that the work delay could not all be blamed on the Corps of Engineers.

The Port also faces time constraints to schedule work, with the Wooden Boat Festival this September and visitor traffic to the marina popular with boaters throughout Puget Sound.

“We have a small window of opportunity to accommodate the customers,” Pivarnik said.

While construction is stalled, Pivarnik and Crockett said they would work with the Port’s Marina Committee about cost issues facing the project’s proposed amenities.

Port Finance Director Don Taylor said securing bond financing is also an issue, with the possibility of selling bonds this fall.

Taylor said with interest rates low, the Port could take advantage of the current bond market to refinance the project.

The marina currently has 45 boat slips and 800 feet of linear docks.

The new marina would add docks and have about 1,000 linear feet of moorage, with additional moorage for boats 40 feet long or less.

More in News

Mark Gregson.
Interim hospital CEO praises partnership, legacy

Gregson says goal is to solidify pact with UW Medicine in coming months

Jefferson County Auditor Brenda Huntingford, right, watches as clerk Ronnie Swafford loads a stack of ballots that were delivered from the post office on Tuesday into a machine that checks for signatures. The special election has measures affecting the Port Townsend and Brinnon school districts as well as East Jefferson Fire Rescue. (Steve Mullensky/for Peninsula Daily News)
Jefferson County voters supporting school district measures, fire lid lifts

Port Townsend approving 20-year, $99.25 million construction bond

Port of Port Townsend Harbormaster Kristian Ferrero, right, watches as a crew from Seattle Global Diving and Salvage work to remove a derelict catamaran that was stuck in the sand for weeks on a beach at the Water Front Inn on Washington Street in Port Townsend. The boat had been sunk off of Indian Point for weeks before a series of storms pushed it to this beach last week. (Steve Mullensky/for Peninsula Daily News)
Derelict boat removal

Port of Port Townsend Harbormaster Kristian Ferrero, right, watches as a crew… Continue reading

Rob Birman has served as Centrum’s executive director for 14 years. When the arts nonprofit completes its search for its next leader, Birman will transition into a role focused on capital fundraising and overseeing capital projects for buildings Centrum oversees. (Centrum)
Centrum signs lease to remain at Fort Worden for next 35 years

Executive director will transition into role focused on fundraising

Clallam approves contracts with several agencies

Funding for reimbursement, equipment replacement

Mark and Linda Secord have been named Marrowstone Island Citizens of the Year for 2025.
Secords named Marrowstone Island citizens of year

Mark and Linda Secord have been chosen as Marrowstone… Continue reading

The members of the 2026 Rhody Festival royalty are, from left, Princess Payton Frank, Queen Lorelei Turner and 2025 Queen Taylor Frank. The 2026 queen was crowned by the outgoing queen during a ceremony at Chimacum High School on Saturday. (Steve Mullensky/for Peninsula Daily News)
Rhody coronation

The members of the 2026 Rhody Festival royalty are, from left, Princess… Continue reading

Jefferson considering new site for solid waste

Commissioners direct further exploration

Public feedback still shaping Clallam ordinance on RV usage

Community Development department set to move sections of its proposal

Jen Colmore, Sequim Food Bank’s community engagement coordinator, has been hired as the executive director. She will start in her new role after outgoing director Andra Smith starts as executive director of the Washington Food Coalition later this month. (Sequim Food Bank)
Sequim Food Bank hires new executive director

Sequim organization tabs engagement coordinator

Sara Nicholls, executive director of the Dungeness Valley Health and Wellness Clinic, also known as the Sequim Free Clinic, inspects food items that are free to any patient who needs them. Soroptimist International of Sequim sponsors the food pantry, she said. (Austin James)
Sequim Free Clinic to celebrate 25th year

Volunteer-driven nonprofit will reach quarter-century mark in October

Weekly flight operations scheduled

Field carrier landing practice operations will take place for aircraft… Continue reading