Herb Beck Marina improvements in the works

New concrete boat launch among the plans

QUILCENE — The Port of Port Townsend and engineers from Reid Middleton presented three concepts for the Herb Beck Marina boat launch replacement project for about 15 people at a community meeting at Quilcene Community Center.

Representatives from the port also offered updates on plans for dredging the marina channel, upgrading its bathroom, and the status of creating an RV campground on the property at the March 7 meeting.

The centerpiece of all three concepts is the construction of a 155-foot-long, 13-foot-wide new concrete boat ramp with a 155-foot-long, 6-foot-wide boarding float. All of the concepts would involve removing the existing concrete ramp, creating a new approach wedge and installing a new aluminum gangway.

The most notable differences were the orientation of the new ramp, which would affect the width of the passageway between it and the existing dock, and the extent of site work required.

In Concept One, the boarding float would be attached to the north side of the launch ramp. The entry to the new ramp would be angled away from the existing concrete ramp, creating a more straightforward access for boaters, leaving 28 feet between the new ramp and the dock.

“This makes the most sense, but it’s more site work,” Blaine McRae of Reid Middleton said.

In Concept Two, the boat launch ramp and boarding float would be constructed on the footprint of the old concrete ramp. The boarding float would be on the south side of the launch ramp, leaving 27 feet between the ramp and the dock.

Concept Three, like Concept Two, imagined the boarding float would be on the south side of the new boat launch ramp. The ramp would be constructed close to the footprint of the old concrete ramp. The existing concrete wall next to the old concrete launch would be removed and replaced with sheet pile, which would require grading. A distance of 24 feet, 6 inches would remain between the ramp and the dock.

The new ramp would be slightly longer than the existing ramp and its 12 to 14 percent angle would be less steep and thus safer.

The earliest start date for the project budgeted at $2.136 million would be July 2025.

Deputy Director Eric Toews said Concept One is likely the most costly of the three options due to the extent of site work required. Concept Two would probably be the least expensive and Concept Three would fall somewhere in the middle, he said.

“This doesn’t create more capacity,” Toews said of the launch replacement project. “It keeps what we have and increases functionality for users.”

Herb Beck tenants have said they want to see more port action to clean out the marina’s channel, which was last dredged in 2010. Director of Capital Projects Matt Klontz called the dredging “one of the more complex projects” on the port’s to-do list. He estimated about 2,300 cubic yards of material needed to be removed and that permitting would take from six months to a year.

The port is considering obtaining dredging equipment so staff could remove the backlog of material, rather than hiring an outside contractor. Having its own equipment would also enable to better establish and keep to a regular maintenance program, Klontz said.

A remodel of the marina bathroom that is used by marina tenants and campground visitors is part of the overall marina project and will likely occur in 2026, Klontz said. In addition to an overall upgrade, the bathroom will be ADA compliant. Klontz said the port has not yet made a decision about whether it will open the bathroom to the general public.

Klontz also gave a short update on plans to upgrade the campground on the west side of the port’s marina property where the Jefferson County Public Utility District will construct eight RV campsites.

The RV sites would be reserved for individuals working on installation of its $51 million high-speed fiber corridor project. The intention is that, when the project is completed, the port would resume possession of the upgraded campground area for income generation.

The project is still in the process of being permitted, Klontz said, and stormwater and septic design will need to be completed before any work starts.

________

Reporter Paula Hunt can be reached at paula.hunt@peninsuladailynews.com.

More in News

Kathy Downer takes the oath office for Sequim City Council seat No. 1 on Jan. 8, 2024, in the council chambers. She plans to resign from council this month after three-plus years to spend time with family. (Matthew Nash/Olympic Peninsula News Group file)
Sequim council member to resign

Downer unseated former mayor in 2023 election

If a construction bond is approved, Sequim High School’s open campus could be enclosed to increase safety and update the older facility, Sequim School District staff said. (Matthew Nash/Olympic Peninsula News Group)
Ballots for Sequim schools’ bond, levy measures to be mailed Jan. 22

Helen Haller Elementary would be replaced, if successful

Stakeholders and community leaders stand together for the ceremonial groundbreaking of Habitat for Humanity of Clallam County's Lyon's Landing property in Carlsborg on Dec. 23. (Habitat for Humanity of Clallam County)
Habitat breaks ground at Carlsborg development

Lyon’s Landing planning to host 45 homes

Weekly flight operations scheduled

There will be field carrier landing practice operations for aircraft… Continue reading

Students from Mutsu City, Japan, and Port Angeles sit in a Stevens Middle School classroom eating lunch before the culture fair on Tuesday. To pass the time, they decided to have a drawing contest between themselves. (Rob Edwards)
Japanese students visit Port Angeles as part of sister city program

Mutsu students tour area’s landmarks, stay with host families

Jefferson PUD picks search firm for general manager

Commissioners select national co-op association

Port of Port Townsend hopes to sell the Elmore

First step will be to have the vessel inspected

f
Readers break $100K in donations to Home Fund

Donations can be made for community grants this spring

Threat against Port Angeles high school resolved, school district says

Principal credits partnerships with law enforcement agencies

Man flown to hospital after log truck rolls over

A Hoquiam man was airlifted to a Seattle hospital after… Continue reading

Increased police presence expected at Port Angeles High School on Friday

An increased police presence is expected at Port Angeles… Continue reading