Neah Bay dock work of $13 million expected to be finished this summer

NEAH BAY — Work on $13 million in dock improvements should be almost completed by the beginning of August as the tribe’s decrepit commercial pier is replaced, Port of Neah Bay Director Bob Buckingham said last week.

The dock work is of vital importance to the Makah fishing fleet, he said.

The work is the first phase of a two-part project that includes an additional $6 million in moorage improvements to support an expanded role for oil-spill-and-response vessels, which already dock there, said Chad Bowechop, Makah affairs manager.

For construction on Phase 2, which is scheduled to begin in 2015, funding help is sought from the shipping companies that ply the Strait of Juan de Fuca.

First phase

The first phase entails construction of a 410-foot dock that has a two-lane trestle for vehicles, a 130-foot pier, an icehouse, expanded ice production and a warehouse that includes offices.

When completed, it will allow for sorting, packing and shipping directly from the dock aboard semi-trailers that cannot now safely traverse the fragile pier.

The ice-house may not be completed by the end of August, Buckingham said.

Building costs had been estimated at $7.6 million, but a low bid of $10.4 million was awarded to Jacksonville, Fla.-based Manson Construction, Buckingham said.

He said design, engineering and other “soft” costs have upped Phase 1’s price tag to more than $13 million.

Funding includes a $1 million federal Economic Development Administration Grant awarded almost two years ago in May 2012.

“There were several community meetings to determine what the best replacement was to serve today’s needs,” he said.

Delays also were caused by failed efforts to obtain federal dollars, Bowechop said.

“What we are finding is that because of the widening of the Panama Canal, all federal money is going to improving East Coast infrastructure.”

Half-completed

Manson was given the go-ahead to begin construction Dec. 26, and the dock is about half completed, Buckingham said.

Serious injuries sustained by a driver whose forklift broke through the dock “did expedite construction on it,” he added.

The dock, more than 60 years old, provides moorage for about 70 tribal and non-tribal vessels and is meant to allow storage and transferal to semi-trucks on the pier.

But it had become so unsafe that semi-truck traffic has not been allowed on it for eight years, tribal Chairman Timothy Greene told a U.S. House of Representatives House appropriations subcommittee April 24, 2013.

“This commercial dock represents over $6 million in fish landings annually, which are shipped around the country and internationally,” he said.

“It supports about half the working-age population of Neah Bay and over 100 minority-owned enterprises.”

Bowechop said the tribe continues seeking funds from the federal government and also is looking to shipping companies to foot the bill.

“Now that we have invested $10 million of our own money, we are inviting the industry to chip in for the rest of the dock, the approximately $6 million,” he said.

“We are trying our best to convince the industry that in order to meet your federal response standards, you need to help us invest in the infrastructure, that portion of the dock that’s dedicated to moorage and stationing of the response assets.”

Those assets include two 80-foot and 100-foot oil-spill-response vessels, associated smaller aluminum craft of 20 to 30 feet, and barges.

“One of the main efficiencies has been oil storage, and now we are talking about larger barges,” Bowechop said.

________

Senior Staff Writer Paul Gottlieb can be reached at 360-452-2345, ext. 5060, or at pgottlieb@peninsuladailynews.com.

More in News

School measures, fire district propositions passing

Port Townsend and Brinnon school district measures were passing… Continue reading

Port of Port Townsend Harbormaster Kristian Ferrero, right, watches as a crew from Seattle Global Diving and Salvage work to remove a derelict catamaran that was stuck in the sand for weeks on a beach at the Water Front Inn on Washington Street in Port Townsend. The boat had been sunk off of Indian Point for weeks before a series of storms pushed it to this beach last week. (Steve Mullensky/for Peninsula Daily News)
Derelict boat removal

Port of Port Townsend Harbormaster Kristian Ferrero, right, watches as a crew… Continue reading

Rob Birman has served as Centrum’s executive director for 14 years. When the arts nonprofit completes its search for its next leader, Birman will transition into a role focused on capital fundraising and overseeing capital projects for buildings Centrum oversees. (Centrum)
Centrum signs lease to remain at Fort Worden for next 35 years

Executive director will transition into role focused on fundraising

Clallam approves contracts with several agencies

Funding for reimbursement, equipment replacement

Mark and Linda Secord have been named Marrowstone Island Citizens of the Year for 2025.
Secords named Marrowstone Island citizens of year

Mark and Linda Secord have been chosen as Marrowstone… Continue reading

The members of the 2026 Rhody Festival royalty are, from left, Princess Payton Frank, Queen Lorelei Turner and 2025 Queen Taylor Frank. The 2026 queen was crowned by the outgoing queen during a ceremony at Chimacum High School on Saturday. (Steve Mullensky/for Peninsula Daily News)
Rhody coronation

The members of the 2026 Rhody Festival royalty are, from left, Princess… Continue reading

Jefferson considering new site for solid waste

Commissioners direct further exploration

Public feedback still shaping Clallam ordinance on RV usage

Community Development department set to move sections of its proposal

Jen Colmore, Sequim Food Bank’s community engagement coordinator, has been hired as the executive director. She will start in her new role after outgoing director Andra Smith starts as executive director of the Washington Food Coalition later this month. (Sequim Food Bank)
Sequim Food Bank hires new executive director

Sequim organization tabs engagement coordinator

Sara Nicholls, executive director of the Dungeness Valley Health and Wellness Clinic, also known as the Sequim Free Clinic, inspects food items that are free to any patient who needs them. Soroptimist International of Sequim sponsors the food pantry, she said. (Austin James)
Sequim Free Clinic to celebrate 25th year

Volunteer-driven nonprofit will reach quarter-century mark in October

Weekly flight operations scheduled

Field carrier landing practice operations will take place for aircraft… Continue reading

“Angel” Alleacya Boulia, 26, of St. Louis, Mo., was last seen shopping in Port Angeles on Nov. 17, National Park Service officials said. Her rented vehicle was located Nov. 30 at the Sol Duc trailhead in Olympic National Park. (National Park Service)
Body of missing person found in Sol Duc Valley

Remains believed to be St. Louis woman