Trump officials blamed for slowing down nuke site cleanup

Budget cuts proposed at same time estimated cost has tripled

  • By Nicholas K. Geranios The Associated Press
  • Tuesday, April 9, 2019 1:30am
  • News

By Nicholas K. Geranios

The Associated Press

SPOKANE — The slow pace of cleaning up the nation’s largest cache of radioactive waste left over from the production of nuclear weapons is frustrating Washington state officials from both major political parties, who blame the Trump administration for not doing more.

The U.S. Department of Energy recently proposed hundreds of millions of dollars in budget cuts for cleaning up the vast Hanford Nuclear Reservation in southeastern Washington, even though the estimated cost of the cleanup has at least tripled and could reach more than $600 billion.

“That’s a huge, huge cost increase,” said Tom Carpenter, director of the watchdog group Hanford Challenge.

At a recent hearing in Washington, D.C., Democratic Sen. Patty Murray questioned Energy Secretary Rick Perry’s assertion that his agency can still meet a legally binding cleanup schedule despite the proposed budget cuts.

Much of the site’s aging infrastructure is deteriorating, including underground waste storage tanks and tunnels.

The Energy Department issued a report in January that raised the remaining cost of Hanford’s environmental cleanup to between $323 billion and $677 billion, with the work lasting until 2079 or 2102, depending on which estimate proves true.

That is much higher than the previous estimate of $107 billion in costs to complete the cleanup by 2066.

That is “a pretty shocking number,” Perry told members of the House Appropriations Committee late last month.

Shortly after the higher estimates were revealed, the Trump administration proposed a $416 million cut in its budget for Hanford that would reduce it from about $2.5 billion for the fiscal year ending Sept. 30 to $2.1 billion for the next fiscal year that starts Oct. 1.

Republican U.S. Rep. Dan Newhouse, whose district encompasses the site, said the administration’s “budget request numbers would fall short of fulfilling the federal government’s obligation to clean up the Hanford site.”

U.S. Sen. Ron Wyden, an Oregon Democrat, estimated it will take 300 years to clean up the site under the Trump administration’s proposed budget.

“Trump’s combination of bad math and shifty wordplay adds up to tragicomic incompetence,” said Wyden, a frequent critic of efforts to clean up the site.

Washington state officials have said previously — even before the cuts were announced — that the federal government has not provided enough funding to meet annual cleanup costs. They have suggested that at least $3 billion annually is needed.

“We believe that the lack of adequate funding translates into a longer, more drawn-out cleanup, and that in turn is a significant factor in the increased cost of the total cleanup,” said Alex Smith, manager of nuclear waste programs for the Washington Department of Ecology.

Hanford was created by the Manhattan Project during World War II as the nation raced to build atomic bombs. The plutonium for the atomic bomb dropped on Nagasaki, Japan, at the end of the war was made at the site, which then produced about 70 percent of the plutonium for the U.S. Cold War arsenal.

That left the country’s largest volume of radioactive waste at the site about half the size of Rhode Island, where the most dangerous 56 million gallons of waste is stored in 177 giant underground tanks, some of which have leaked.

The site has around 10,000 workers and is the main economic force for the cities of Richland, Pasco and Kennewick, located 200 miles east of Seattle.

Carpenter said he suspected the larger cleanup cost estimate followed by the Trump administration announcement on the proposed Hanford budget cut could be part of a larger government plan to limit the cleanup’s scope.

He pointed out that the Energy Department mounted a campaign in recent years to reclassify much of Hanford’s dangerous high-level waste as low-level, which would reduce cleanup costs.

Washington officials want “to walk away from Hanford and the cleanup. They want to put concrete in the tanks and walk away,” he said.

Perry said the Trump administration will keep promises for continued cleanup work.

“We give you our commitment that, not only are we going to be working efficiently, but we’re going to be working timely,” Perry said at the congressional hearing.

More in News

Milan Pohl of Port Angeles points out the features of a greenhouse he built to cover a portion of his plot at the Fifth Street Community Garden in Port Angeles. Pohl said on Friday that the greenhouse and a twin structure on an adjoining bed would be used to grow eggplant, peppers and other heat-loving plants. (Keith Thorpe/Peninsula Daily News)
Community garden plot

Milan Pohl of Port Angeles points out the features of a greenhouse… Continue reading

x
Nominations open for Community Service awards

Forms due March 25; event scheduled for May 1

Influenza numbers trending down in Clallam, Jefferson counties

Public health officer says it’s not too late for vaccine

NOAA lease in Port Angeles on list of terminations

A lease held by the National Oceanic and Atmospheric… Continue reading

Tyler Leisten.
Leisten gradutes from basic law enforcement academy

Tyler Leisten has graduated from the Washington State Basic… Continue reading

Nicole Merrigan, owner of Strait Up Foam Fun, left, talks with Carol Koenig of Sequim during Thursday’s Clallam County Job Fair at Vern Burton Community Center in Port Angeles. About two dozen prospective employers took part in the event, hosted by the Greater Port Angeles Chamber of Commerce. (Keith Thorpe/Peninsula Daily News)
Job fair

Nicole Merrigan, owner of Strait Up Foam Fun, left, talks with Carol… Continue reading

Funding from the state Department of Commerce will be matched with private donations to fix the Upper Hoh Road this spring, Gov. Bob Ferguson said Thursday. (Olympic National Park)
State funds to repair Hoh Road

Private donations to match Commerce grant

Grant would help Port of Port Townsend with larger vessels

Two-phase project intended to increase efficiency

Port Angeles City Manager Nathan West gives his annual presentation on the state of the city on Wednesday to the Greater Port Angeles Chamber of Commerce at the Red Lion Hotel. (Keith Thorpe/Peninsula Daily News)
Port Angeles’ efforts on housing, homelessness top annual address

Manager provides State of the City comments to chamber

Master Gardener Honey Niemann of Port Townsend trims a barberry bush on Wednesday to keep it from infringing on the daffodils blooming at Master Gardener Park at the corner of 10th Street and Sims Way in Port Townsend. (Steve Mullensky/for Peninsula Daily News)
Signs of spring

Master Gardener Honey Niemann of Port Townsend trims a barberry bush on… Continue reading