Timeline told on Port of Port Angeles’ Maritime Trade Center

Construction slated to begin this May

PORT ANGELES — The Port of Port Angeles is entering Phase 2 of development of the Maritime Trade Center on the former PenPly/KPly site, with bidding scheduled to open March 26, according to Director of Engineering Chris Hartman.

Hartman spoke to commissioners Connie Beauvais and Steve Burke at the port’s Tuesday meeting. Commissioner Coleen McAleer had an excused absence.

Construction is anticipated to begin in May and be completed by December, Hartman said.

ADVERTISEMENT
0 seconds of 0 secondsVolume 0%
Press shift question mark to access a list of keyboard shortcuts
00:00
00:00
00:00
 

The scope of work on the 18-acre site includes grading; construction of new water and sewer mains; construction of a stormwater collection, conveyance and treatment facility; and installation of a new asphalt access road.

The port allocated $10.232 million in its 2024 capital budget for the project; it will pay $3.5 million of the cost, with $6.732 million coming from a U.S. Department of Commerce Economic Development Administration grant.

“It has the potential of being developed into five separate lease blocks throughout the site,” Hartman said. “Outside of that, there’s some general laydown and other boat repair areas.”

The port chose to focus on building out infrastructure, with particular attention to stormwater management, when it had to scale back the original design to meet its budget, Hartman said. The port received a total grant amount of $11.034 million.

“The original cost estimates were done in 2019, and we got awarded the grant in 2022,” Hartman said. “Now that we’re going into construction in 2024, all of those prices have just continued to far outpace traditional yearly escalations.”

The price to complete the project as originally planned would be about $18 million, he said.

Among the cost savings were shortening a road on the site so it accesses just three of the five lease lots, and replacing a good deal of proposed asphalt surfacing with crushed rock.

“What would be the ramifications of truck traffic where it’s unpaved, like going over the cargo area?” Beauvais asked. “Are you taking into consideration what that would do to the stormwater infrastructure?”

Hartman said that concern would likely need to be addressed at some point.

“If you had a bunch of heavy haul on the gravel site and then onto pavement, you’re going to track out a lot of sediment that gets washed into the storm drains,” he said. “If there was a specific cargo [like chips] that was being considered, you might have to come in back in and do additional paving.”

The port is still in the process of talking to businesses and gauging interest in the site, so it wanted to remain open to ideas about layout and not get ahead of what individual clients might need, Executive Director Paul Jarkiewicz said.

“It leaves us a lot of flexibility to do a number of different things,” Jarkiewicz said. “We want to remain flexible and make the site operative so a tenant can build itself or the port can build to suit.”

The port has been able to realize cost savings by doing some of the work itself, such as removing and breaking up old concrete foundations on the site.

“The more of that we can do, the more we’re going to save,” facilities maintenance supervisor Wilson Easton said.

Easton said port staff found “logs galore” left over from a state Department of Ecology dredging project in 2014 during which 53,765 tons of contaminated soil had been excavated and removed. Some of the logs could be chipped, he said, while others soaked with creosote would have to be taken to a transfer station.

Port commissioners unanimously approved the $50,000 purchase of a pre-fabricated 40-foot by 72-foot pole building kit that facilities maintenance will for use for equipment storage. Facilities maintenance staff will construct the building.

________

Reporter Paula Hunt can be reached at paula.hunt@peninsuladailynews.com.

More in News

Parker Brocious, 6, from Cedar Hills, Utah, studies tubs containing plankton, krill and other small ocean creatures used by the Port Townsend Marine Science Center for education purposes while on a road trip with his family on Tuesday at Fort Worden State Park. Parker’s father Tyler is at left. (Steve Mullensky/for Peninsula Daily News)
Science education

Parker Brocious, 6, from Cedar Hills, Utah, studies tubs containing plankton, krill… Continue reading

Port Angeles approves lodging tax fund requests

Vacancy on committee brings legal questions

OMC hires family medicine physician

Dr. Calvin Kuo will join hospital in August

Colton Dufour, left, and his mom Cherie Tachell. (Cherie Tachell)
Boy seriously injured following hit-and-run

Condition is stable, but more testing underway for Sequim teenager

Applications open for Forks council seat

The Forks City Council is accepting applications to fill a… Continue reading

Bridge inspections set on Hood Canal

Bridge preservation engineers from the state Department of Transportation will… Continue reading

Port Townsend Farmers Market opens Saturday

Farm-fresh eggs, mexican pastries and smoked fish available

Adella Banning, 6, of Port Angeles pretends to take to the road on a all-terrain vehicle maintained by Clallam County Search and Rescue during Saturday’s Kiwanis Kids Fest at Vern Burton Community Center and a section of adjoining Fourth Street. The event featured numerous public safety displays as well as other youth activities hosted by area community service agencies. (Keith Thorpe/Peninsula Daily News)
Kids Fest

Adella Banning, 6, of Port Angeles pretends to take to the road… Continue reading

Clallam letter details Trump administration impacts

Clallam cites economy, tourism, healthcare

Rhonda Kromm is the new Port Angeles School District assistant superintendent. She replaces Michelle Olsen, the newly hired superintendent.
First bonds issued for develop plans for PAHS, Franklin Elementary

Construction at new Stevens Middle School to start in May

UPS Store closing Port Angeles location

UPS is closing its UPS Customer Center at 3216… Continue reading

Single-lane traffic near Kalaloch Campground

Erosion near Kalaloch Campground has caused a temporary lane closure… Continue reading