Timeline told on Port of Port Angeles’ Maritime Trade Center

Construction slated to begin this May

PORT ANGELES — The Port of Port Angeles is entering Phase 2 of development of the Maritime Trade Center on the former PenPly/KPly site, with bidding scheduled to open March 26, according to Director of Engineering Chris Hartman.

Hartman spoke to commissioners Connie Beauvais and Steve Burke at the port’s Tuesday meeting. Commissioner Coleen McAleer had an excused absence.

Construction is anticipated to begin in May and be completed by December, Hartman said.

The scope of work on the 18-acre site includes grading; construction of new water and sewer mains; construction of a stormwater collection, conveyance and treatment facility; and installation of a new asphalt access road.

The port allocated $10.232 million in its 2024 capital budget for the project; it will pay $3.5 million of the cost, with $6.732 million coming from a U.S. Department of Commerce Economic Development Administration grant.

“It has the potential of being developed into five separate lease blocks throughout the site,” Hartman said. “Outside of that, there’s some general laydown and other boat repair areas.”

The port chose to focus on building out infrastructure, with particular attention to stormwater management, when it had to scale back the original design to meet its budget, Hartman said. The port received a total grant amount of $11.034 million.

“The original cost estimates were done in 2019, and we got awarded the grant in 2022,” Hartman said. “Now that we’re going into construction in 2024, all of those prices have just continued to far outpace traditional yearly escalations.”

The price to complete the project as originally planned would be about $18 million, he said.

Among the cost savings were shortening a road on the site so it accesses just three of the five lease lots, and replacing a good deal of proposed asphalt surfacing with crushed rock.

“What would be the ramifications of truck traffic where it’s unpaved, like going over the cargo area?” Beauvais asked. “Are you taking into consideration what that would do to the stormwater infrastructure?”

Hartman said that concern would likely need to be addressed at some point.

“If you had a bunch of heavy haul on the gravel site and then onto pavement, you’re going to track out a lot of sediment that gets washed into the storm drains,” he said. “If there was a specific cargo [like chips] that was being considered, you might have to come in back in and do additional paving.”

The port is still in the process of talking to businesses and gauging interest in the site, so it wanted to remain open to ideas about layout and not get ahead of what individual clients might need, Executive Director Paul Jarkiewicz said.

“It leaves us a lot of flexibility to do a number of different things,” Jarkiewicz said. “We want to remain flexible and make the site operative so a tenant can build itself or the port can build to suit.”

The port has been able to realize cost savings by doing some of the work itself, such as removing and breaking up old concrete foundations on the site.

“The more of that we can do, the more we’re going to save,” facilities maintenance supervisor Wilson Easton said.

Easton said port staff found “logs galore” left over from a state Department of Ecology dredging project in 2014 during which 53,765 tons of contaminated soil had been excavated and removed. Some of the logs could be chipped, he said, while others soaked with creosote would have to be taken to a transfer station.

Port commissioners unanimously approved the $50,000 purchase of a pre-fabricated 40-foot by 72-foot pole building kit that facilities maintenance will for use for equipment storage. Facilities maintenance staff will construct the building.

________

Reporter Paula Hunt can be reached at paula.hunt@peninsuladailynews.com.

More in News

No injuries following fire at McKinley paper mill

A fire broke out late Monday night at the… Continue reading

August Gala, 2, of Port Angeles spins an idle wheel of a truck belonging to Bruch & Bruch Construction during Saturday’s Touch a Truck event at Queen of Angeles School in Port Angeles. The event, hosted by the school’s parent-teacher organization, allowed youngsters and adults to visit and climb aboard a variety of construction, public safety and utility vehicles. (Keith Thorpe/Peninsula Daily News)
Touch a Truck

August Gala, 2, of Port Angeles spins an idle wheel of a… Continue reading

Man who allegedly broke into Brinnon homes with rifle to be in court

Coccia, 44, arrested by Mason County sheriff’s deputies

Port of Port Angeles reports strong March revenue

Marine trades site ready for contractor to install utilities

Chef to speak at Studium Generale East

Chef Arran Stark will present a healthy cooking demonstration… Continue reading

Two-lane bypass to be paved Tuesday night

Work crews will begin paving a two-lane bypass near Discovery… Continue reading

Woman recovered from water off Neah Bay coast

An unidentified woman was recovered by the Neah Bay… Continue reading

Noah Glaude, executive director of the North Olympic Library System, welcomes a crowd to the ceremonial groundbreaking of the Sequim Library expansion on Wednesday. (Michael Dashiell/Olympic Peninsula News Group)
Sequim library breaks ground

3,800-square-foot expansion expected to be complete by spring 2025

Citizen of the Year Susie Brandelius with the Forks Chamber of Commerce Executive Director Lissy Andros, who caught up with Brandelius on Monday to present her award and flowers. (Christi Baron/Olympic Peninsula News Group)
Forks chamber celebrates community awards

Citizen, volunteer, business of the year lauded

Flight operations set for this week

There will be field carrier landing practice operations for aircraft… Continue reading

Brinnon man in custody after search

A Brinnon man who was wanted after allegedly breaking into… Continue reading