Port of Port Townsend approves low bid to update stormwater system

PORT TOWNSEND — Port of Port Townsend commissioners have approved a bid from Olympic Peninsula Construction for work to update the stormwater system in the Boat Haven marina.

The approved bid from Olympic Peninsula Construction of Poulsbo was the lowest by more than $112,000 of the three bids that were received.

The approved bid for $154,617 raised some concern during a commissioners’ meeting last week because it was so much lower than the other two bids. Port staff assured commissioners that they checked Olympic Peninsula Construction’s certifications, business license and insurance to ensure they were reputable.

Port Executive Director Sam Gibboney said Olympic Peninsula also accounted for the port purchasing some of the materials for the project, which allowed for a lower bid.

The entire project will cost the port between $200,000 and $256,000 with the added cost of materials and hiring a project manager to supervise the project.

Gibboney said that because the project is complicated and on a tight timeline, having an onsite manager will ensure the project is completed correctly.

Port staff members plan to present the commissioners with a breakdown on the expected material and management costs at the port commissioners’ next meeting at 9:30 a.m. Wednesday at 333 Benedict St.

Port staff has sent a notice of intent to award to Olympic Peninsula Construction and will begin working on a timeline for the project.

The project would update four in-ground sand filters located around the Boat Haven marina boatyard.

The contract includes the rehabilitation of perimeter filters using media material such as sand and oyster shell, which have been found to be effective at removing metals, staff members said.

Olympic Peninsula Construction also will be responsible for replenishing two Aquip stormwater treatment units with the proprietary media mix, moving one Aquip stormwater treatment unit and correcting various component elevations and sizes to ensure proper hydraulic functioning.

Because the Boat Haven Marina doesn’t sit on a significant grade, the elevations are particularly important to ensure water is flowing the correction direction, Gibboney said.

Gibboney said the contractor understands the port is on a deadline and she is hoping for the entire project to be completed in about five to six weeks.

The port has a Sept. 30 deadline for the project completion as set by the state Department of Ecology. However, Gibboney said Ecology likely will not enforce that deadline if the port has made significant progress on the project.

“I don’t expect any enforcement action or any administrative repercussions if we are still doing work past that Sept. 30 deadline,” Gibboney said.

________

Jefferson County Editor/Reporter Cydney McFarland can be reached at 360-385-2335, ext. 55052, or at cmcfarland@peninsuladailynews.com.

More in News

Overnight bridge closures scheduled

The state Department of Transportation has announced a series of… Continue reading

Fort Worden board to discuss annual report

The Fort Worden Public Development Authority board will discuss… Continue reading

East Jefferson Fire Rescue Chief Bret Black describes the 2,500-gallon wildfire tender located at Marrowstone Fire Station 12 on Marrowstone Island during an open house on Saturday. (Steve Mullensky/for Peninsula Daily News)
Marrowstone Island fire station open for business

Volunteers to staff 1,300-square-foot building

Woman charged in animal cruelty

Jacobsen facing 30 counts from 2021, ‘22

Measures passing for Quilcene schools, Clallam Bay fire

Next ballot count expected by 4 p.m. Thursday

A repair crew performs work on the observation tower at the end of Port Angeles City Pier on Wednesday as part of a project to repair structural deficiencies in the tower, which has been closed to the public since November. The work, being performed by Aberdeen-based Rognlin’s Inc., includes replacement of bottom supports and wood decking, paint removal and repainting of the structure. Work on the $574,000 project is expected to be completed in June. (Keith Thorpe/Peninsula Daily News)
Repairs begin on tower at Port Angeles City Pier

The city of Port Angeles has announced that Roglin’s,… Continue reading

No one injured in Port Angeles car fire

No one was injured in a fire that destroyed… Continue reading

Quilcene schools, Clallam Bay fire district measures passing

Voters in Jefferson and Clallam counties appear to have passed measures for… Continue reading

Tribe seeking funds for hotel

Plans still in works for downtown Port Angeles

Clallam County eyes second set of lodging tax applications

Increase more than doubles support from 2023

Olympic Medical Center reports operating losses

Hospital audit shows $28 million shortfall

Jefferson County joins opioid settlement

Deal with Johnson & Johnson to bring more than $200,000