Environmental groups want work halted on Snake River dams

By Keith Ridler

The Associated Press

BOISE, Idaho — Environmental groups are asking a federal court to halt 11 infrastructure projects on four lower Snake River dams in Washington state that could ultimately be removed if a pending review determines the dams need to come out to help salmon.

The 45-page notice filed late Monday in Portland, Ore., estimates the cost of the projects at $110 million.

The National Wildlife Federation and the other groups in a separate 29-page filing also late Monday asked that the federal government be ordered to spill more water in the spring over the four Snake River dams and four more on the Columbia River to help migrating salmon.

A federal judge ruled in May that the U.S. government hasn’t done enough to improve Northwest salmon runs and ordered an environmental impact statement that’s due out in 2021, urging officials to consider removing the dams.

The environmental groups contend that infrastructure improvements shouldn’t be allowed at the dams during the review.

“These kinds of investments should be suspended to ensure a level playing field for all of the alternatives agencies must consider, including the alternative of lower Snake River dam removal,” Kevin Lewis of Idaho Rivers United said in a statement.

The review process is being conducted under the National Environmental Policy Act, or NEPA, an umbrella law that covers the Endangered Species Act.

Thirteen species of salmon and steelhead on the Columbia and Snake rivers have been listed as federally protected over the past 25 years. Four of the listed species are found in Idaho.

The Snake River dams cited in the documents are Ice Harbor, Lower Monumental, Little Goose and Lower Granite. They’re the four lowest dams on the 1,000-mile-long Snake River, itself a tributary to the Columbia River.

The four dams are managed by the U.S. Army Corps of Engineers and were built in the 1960s and 1970s.

Officials with the federal agency didn’t return a call from The Associated Press.

Northwest River Partners, which represents a coalition of businesses and river users and has intervened on the side of the federal government, is against removing the dams.

“We need to keep investing in critical infrastructure like the Snake River dams,” said Terry Flores, director of the Portland-based group.

“We need to keep them well maintained so we can keep the lights on and keep people safe and warm, and the economy running.”

The $110 million listed in the document filed Monday is an estimate by the environmental groups that said the Army Corps of Engineers declined to provide precise numbers.

The groups say more than half of the money is being spent on Ice Harbor Dam and includes new turbine blades.

“The Corps is continuing to commit major capital resources to restoring and extending the useful life of the four lower Snake River dams without hesitation or pause,” the court document states.

The groups say the expenditures could be used to argue the dams shouldn’t be removed.

More in News

John Brewer.
Former editor and publisher of PDN dies

John Brewer, 76, was instrumental in community

Randy Perry and Judy Reandeau Stipe, volunteer executive director of Sequim Museum & Arts, hold aloft a banner from "The Boys in the Boat" film Perry purchased and is loaning to the museum. (Michael Dashiell/Olympic Peninsula News Group)
‘Boys in the Boat’ banner to be loaned to museum

Sequim man purchases item shown in film at auction

Charisse Deschenes, first hired by the city of Sequim in 2014, departed this week after 10 years in various roles, including most recently deputy city manager/community and economic development director. (City of Sequim)
Deputy manager leaves Sequim

Community, economic development position open

Hoko River project seeks salmon recovery and habitat restoration

Salmon coaltion takes lead in collaboration with Makah, Lower Elwha tribes

Clallam Transit’s zero-fare program off to successful start

Ridership is up and problems are down, general manager says

Motor rider airlifted to Seattle hospital after wreck

A Gig Harbor man was airlifted to a Seattle hospital… Continue reading

Traffic light project to begin Monday

Work crews from Titan Earthwork, LLC will begin a… Continue reading

From left to right are Indigo Gould, Hazel Windstorm, Eli Hill, Stuart Dow, Mateu Yearian and Hugh Wentzel.
Port Townsend Knowledge Bowl team wins consecutive state championships

The Knowledge Bowl team from Port Townsend High School has… Continue reading

Bob Edgington of 2 Grade LLC excavating, which donated its resources, pulls dirt from around the base of an orca sculpture at the Dream Playground at Erickson Playfield on Thursday during site preparation to rebuild the Port Angeles play facility, which was partially destroyed by an arson fire on Dec. 20. A community build for the replacement playground is scheduled for May 15-19 with numerous volunteer slots available. Signups are available at https://www.signupgenius.com/go/904084DA4AC23A5F85-47934048-dream#/. (Keith Thorpe/Peninsula Daily News)
Site preparation at Dream Playground

Bob Edgington of 2 Grade LLC excavating, which donated its resources, pulls… Continue reading

Rayonier Inc. is selling more than 115,000 acres in four units across the West Olympic Peninsula last week as the company looks to sell $1 billion worth of assets. (Courtesy photo / Rayonier Inc.)
Rayonier to sell West End timberland

Plans call for debt restructuring; bids due in June

Port Angeles port approves contract for Maritime Trade Center bid

Utilities installation, paving part of project at 18-acre site