UPDATE: Hurricane Ridge Road closed six weeks during Heart O’ the Season

PORT ANGELES — Hurricane Ridge Road will remain closed for an estimated six weeks, Olympic National Park officials said today following an inspection by Federal Highway Administration engineers.

The engineers and park officials inspected an active washout just north of Heart O’ the Hills campground where 100 feet of road crumbled into the Ennis Creek valley.

Park officials, including Superintendent Karen Gustin, met with the three engineers late today to plan for reconstruction of the road.

Barb Maynes, Olympic National Park spokeswoman, said the work will begin no later than Friday.

“We’ll be removing the existing fill that is still there and replacing the fill with a more suitable material,” Maynes said.

The muddy fill that undercut both lanes of the only access route to the mile-high recreation spot 17 miles south of Port Angeles will be replaced by a rocky, gravel substance that is less prone to slides, Maynes said.

A culvert will be replaced with a larger culvert, and the road will reopen in about six weeks, Maynes said.

A Federal Highways Administration geotechnical engineer will assess the site Thursday to confirm details of the repair design, Gustin said.

“We are pleased to report that plans are coming together quickly and we expect to have a contractor in place to begin repair work no later than this Friday,” Gustin said in a prepared statement.

“We understand the importance of Hurricane Ridge to our region and we are fully committed to reopening the road as quickly as possible.

“We are also committed to repairing the road in a way that absolutely minimizes the chances of this happening again.”

Heavy rains triggered the slide that began Saturday about five miles south of Port Angeles. Water is visible inside the soils.

The road bed was on fill used to build Hurricane Ridge Road about 52 years ago.

Access is cut off to the Heart O’ the Hills campground as well as to Hurricane Ridge. The roadway is blocked to all traffic, including pedestrians bicycles and stock.

Ordinarily, if weather permits, the road to the popular snowplay area is open on weekends and holidays.

Maynes declined to say how much the project is estimated to cost because it has not gone to bid.

She said the park is investigating possible detours around the slide but specific routes are not known.

“The possibility of an interim access is being discussed,” Maynes said.

Repairs to the road will be greatly anticipated by skiers, snowboarders and snowshoers who use the facilities at Hurricane Ridge.

The Hurricane Ridge Ski and Snowboard School was scheduled to begin classes Jan. 30-31. Snowshoe outings have been going on for several weekends.

Craig Hofer, manager of the Hurricane Ridge ski area, said the last few weeks of the season could be salvaged is the project is finished in six weeks.

However, he doubts that the project will be finished in six weeks because of the weather.

“I wish they would come up with a temporary detour,” Hofer said. “I don’t really understand.”

Russ Morrison, operations director for the ski area, said on Tuesday he was hopeful for a temporary solution.

“We need to get access as soon a possible,” he said. “We have thousands of people who ski and take lessons.”

The roadbed travels parallel to the headwaters of Ennis Creek, which flows north to Port Angeles and empties into the Strait of Juan de Fuca next to the site of the former Rayonier Inc. pulp mill.

Maynes addressed the Port Angeles Rotary Club’s noon luncheon on Wednesday and, in response to a question, said there’s no indication that any of the slipout will affect the creek farther north.

The washout is just south of the intersection to homes around Lake Dawn, a small community near the national park boundary. Access to Lake Dawn is unaffected by the closure.

Craig Ritchie, Sequim city attorney and Lake Dawn resident, said he and his neighbors are not concerned about the possibility of rerouting Hurricane Ridge Road traffic onto Lake Dawn Road because it wouldn’t make sense to do so.

“I don’t think anybody’s thought about it,” Ritchie said.

During a $12 million project that was completed in November 2008, Hurricane Ridge Road was repaired in three areas damaged by storms. The 12-mile stretch between Heart O’ the Hills and Hurricane Ridge — above the slide area — was resurfaced.

———-

Reporter Rob Ollikainen can be reached at 360-417-3537 or at rob.ollikainen@peninsuladailynews.com.

More in News

Kelly and Dan Freeman of Port Ludlow examine a 1958 Edsel on display during Friday evening’s 29th annual Ruddell Cruise-In at Ruddell Auto in Port Angeles. The event featured hundreds of antique and vintage automobiles from across the region as well as food, music and other activities. (Keith Thorpe/Peninsula Daily News)
Classic show

Kelly and Dan Freeman of Port Ludlow examine a 1958 Edsel on… Continue reading

Sequim School District officials report it could take upwards of 2 1/2 years to break ground on a new elementary school. Voters approved a $146 million, 20-year construction bond in a Feb. 11 special election that includes a new elementary school, renovated high school and more. (Matthew Nash/Olympic Peninsula News Group)
Sequim schools eye bond timeline

Bigger projects may be 2 years away

Sequim volunteer Emily Westcott has led the flower basket program along Washington Street since 1996. This year she’s retired to focus on other endeavors, and the city of Sequim and the Sequim School District will continue the partnership. Westcott is still seeking donations for downtown Sequim Christmas decorations through the Sequim-Dungeness Valley Chamber of Commerce. (Matthew Nash/Olympic Peninsula News Group)
Sequim flower basket program shifts to city, school partnership

Westcott retires, plans to keep decorating downtown for Christmas

Clallam first in state to implement jail healthcare program

County eligible to apply for Medicare reimbursement for services

Writers to converge in Port Townsend to work on craft

Free readings open to the public next week

Firefighters extinguish blaze in fifth-floor hotel room

Firefighters from East Jefferson Fire Rescue and Navy Region… Continue reading

Mowing operation scheduled along Lake Crescent on Tuesday

Work crews from the state Department of Transportation will… Continue reading

EYE ON THE PENINSULA: County commissioners set to meet next week

Meetings across the North Olympic Peninsula

Peninsula Behavioral Health head discusses the fallout from federal bill

Anticipated cuts to Medicaid could devastate rural communities like Clallam County, leading… Continue reading

Tool library to open in Port Townsend

Drills, saws and more available to borrow

Fire restriction implemented on federal lands

Olympic National Forest and Olympic National Park have restricted campfires… Continue reading