Highway 101 work on schedule to be finished next fall

Project to replace five culverts

PORT ANGELES — Bridge construction on U.S. Highway 101 east of Port Angeles is on budget and on schedule to be completed next fall, a state Department of Transportation official said.

The $35.6 million project will replace five defective fish culverts with two full-span bridges or larger concrete-box culverts to improve fish migration in Bagley and Siebert creeks and their tributaries.

“It’s a huge benefit for salmon restoration,” WSDOT spokeswoman Tina Werner said in a Wednesday interview.

“The potential habitat gain for the fish is estimated at 41 miles, so this will be a big environmental win.”

The two-year project is part of WSDOT’s ongoing effort to improve fish passage under state or federal highways. Bagley and Siebert creeks support chinook and coho salmon, steelhead and bull trout.

Scarsella Brothers, Inc. of Kent, WSDOT’s primary contractor, broke ground on the project in May.

Highway traffic will continue to be funneled into one lane at the creeks until the work is complete. The temporary 45 mph speed limit will remain in effect though next fall.

“We’re very appreciative of the public’s patience, and we’re excited that work has progressed well,” Werner said.

There were 23 collisions investigated on U.S. Highway 101 through the four-mile construction zone from April 1 though Thursday, down from 24 during the same period in 2019, according to State Patrol statistics.

There had been 544 speed violations issued the project area since April 1, down from 667 during the same dates in 2019.

“We appreciate the cooperation of the motorists who have adhered to the temporary speed reduction within the active construction zone throughout the project,” said Trooper Chelsea Hodgson, State Patrol spokeswoman.

“Troopers have patrolled the area during the project to make sure both those who are driving through, as well as the crews working the project, are safe.”

“We can never stress enough for drivers to always slow down and pay extra attention in those areas for a variety of reasons,” Hodgson added. “Traffic patterns are often changed, lanes are narrowed and crews are actively working alongside flowing traffic.”

WSDOT is under a 2013 federal court injunction to remove state-owned culverts that impede salmon migration in much of Western Washington by 2030.

Werner said the existing culverts have “significant barriers” related to water velocity.

“We try to bundle many of these barriers in one contract to reduce construction fatigue for drivers so that we’re not having to come back year after year after year,” Werner said in a telephone interview.

Crews this week were working on abutment walls and foundations for the western half of the Bagley Creek bridge. Girders for the bridge are scheduled to be delivered during the second week of November, Werner said.

Three miles to the east, crews were wrapping up soil stabilization work along Siebert Creek.

“They’re going to continue work through the winter,” Werner said.

“Our crews will be able to maintain current travel flow, which is a single lane in each direction.”

The project was designed to maintain traffic flow on U.S. Highway 101. Drivers may encounter brief, intermittent closures when the bridge girders are delivered, Werner said.

In-water work will take place next summer during an eight-week fish window.

“At that time, Siebert (Creek) bridge will be up and the retaining walls will be done,” Werner said.

“That’s when our crews will go in, and they’re going to remove the old, outdated culverts. They’ll be removing those and doing a lot of stream-bed restoration with our biology teams.”

Updates on the Bagley and Siebert Creek fish barrier replacements will be posted on the WSDOT website, wsdot.wa.gov.

“This is a huge restoration project for DOT, and we are doing everything we can to make sure that the contractor stays on schedule, and we’re looking forward to having this project wrapped up next fall,” Werner said.

“We appreciate everyone’s patience.”

________

Reporter Rob Ollikainen can be reached at rollikainen@peninsuladailynews.com.

More in News

Ben Hecht, a geologist with environmental consulting firm Landau Associates, takes a sample of raw drinking water taken at the city of Port Angeles’ ranney collector on Saturday at the Elwha River, downstream from Friday’s tanker crash that dumped petroleum products into Indian Creek west of Port Angeles. (Keith Thorpe/Peninsula Daily News)
‘Do not drink’ order given for Port Angeles water customers

Bottled water available Sunday at two locations

Foundation donates $1 million to hospital

Recipients include residency program, scholarships and cancer care center

A former teacher, Larry Jeffryes moved to Sequim with his wife in 2013. He was appointed to the Sequim School Board in September 2019, elected by voters in November of that year and was elected again in 2023. Before his resignation, Jeffryes’ term was set to go through November 2027. (Larry Jeffryes)
Sequim school board director resigns after six years in seat

District opens process to apply for position

Members of the musical group Soupbones, from left, Ed Schmid of Port Angeles, Ron Munro of Sequim, Carly List of Port Angeles and Hugh Starks of Sequim, perform at a Good Trouble community gathering and picnic on Thursday at Erickson Playfield in Port Angeles. Organizers of the event, one of numerous gatherings across the United States, decided to forego conventional politics while commemorating the life of civil rights activist John Lewis. (Keith Thorpe/Peninsula Daily News)
Good trouble rally

Members of the musical group Soupbones, from left, Ed Schmid of Port… Continue reading

State funds to benefit coastal habitat

Clallam, Jefferson awarded $1.6M

Artists Heather Sparks, left, and Zeo Boekbinder set up a stencil of a fern leaf in an effort to decorate an otherwise-drab concrete roadside divider along Race Street south of Lauridsen Boulevard on Wednesday in Port Angeles. The divider work was part of a larger project to beautify the Race Street corridor from Eighth Street to Hurricane Ridge Road, which included improved traffic lanes, pedestrian and bicycle lanes and decorative lighting. Long-term plans call for similar improvements to Race Street, extending to First and Front streets. (Keith Thorpe/Peninsula Daily News)
A touch of color

Artists Heather Sparks, left, and Zeo Boekbinder set up a stencil of… Continue reading

A tanker truck overturned into Indian Creek west of Port Angeles, according to the State Patrol and the state Department of Transportation. U.S. Highway 101 was closed Friday afternoon at milepost 238 near Herrick Road, and traffic was being diverted to state Highway 112. (Katherine Weatherwax via X)
Highway 101 reopens after tanker truck overturns into creek

Port Angeles asks utility customers to conserve water

Lisa Hansen of Port Angeles, center, takes a cellphone photo of her son, Cooper Hansen, 3, as Hansen’s mother, Tracy Hansen, right, looks on during a warm day at Hollywood Beach on the Port Angeles waterfront on Wednesday. The trio were enjoying a sunny summer afternoon next to the water. (Keith Thorpe/Peninsula Daily News)
Picture perfect

Lisa Hansen of Port Angeles, center, takes a cellphone photo of her… Continue reading

Claim against First Fed alleges $100M fraud

First Fed plans to ‘vigorously defend’ loans

Olympic Medical Center CEO says Medicaid cuts will hit hard

Darryl Wolfe tells board entire state will feel impact

Joseph Wilson, left, and Kevin Streett.
Jefferson PUD names new general manager

Wilson comes with 30 years of experience