Dredging begins at Port of Port Angeles Terminal 3

$1.6 million project to clear way for ships

PORT ANGELES — A $1.6 million dredging project began Wednesday at the Port of Port Angeles’ Terminal 3 primary cargo dock.

Port Director of Engineering Chris Hartman said the six-week underwater excavation, delayed for two months, will make it easier for captains to sidle their ships up to the pier, which, with dolphins, stretches 445 feet.

Hartman said work will include a crane operator lowering cables to the sea floor while guiding a 7-cubic-yard clamshell bucket large enough to fill two-thirds of a standard dump truck.

Two cranes will be used for the project.

The sediment will be deposited on a barge, where it will be dewatered with the aid of wall scuppers, before it’s ladled again onto dump trucks.

Drivers will deposit the silt on port property on the east end of the former KPly plywood mill site on Marine Drive just west of downtown Port Angeles.

Up to 15,000 yards of material will be dropped on about 4 acres of the mostly vacant 18-acre parcel.

An interior orange fence recently was installed to prevent silt-laden runoff from migrating off the property, which will be sectioned off for analyzing the sediment.

“We have a bunch of different areas where we will do stockpiling and analytic testing to ensure it’s clean,” Hartman said.

Silt that meets state Department of Ecology pollution standards will remain and be used as fill material at the site, formerly called the Marine Trades Industrial Park.

To attract tenants, port commissioners recently renamed it the Port Angeles Marine Trades Center.

Material that exceeds Ecology standards will be trucked to the Roosevelt Regional Landfill at the Washington-Oregon border south of Yakima.

The sediment contains varying levels of polychlorinated biphenyls, pesticides, dioxins, metals, tributyltin, aromatic hydrocarbons and dioxins/furans that exceed the standards of the Dredged Material Management Program, administered by state and federal agencies.

Those levels make some of that sediment unsuitable for open-water disposal, according to the port’s Seattle-based environmental consulting firm, Floyd-Snider.

The contract includes the expectation that 3,000 cubic yards, or 5,000 tons, will need to be trucked to Roosevelt.

“We’re hoping to use as much as possible on the site so we don’t have costs for trucking and disposal,” Hartman said.

The dock area will be dug to 45 feet below mean low tide. In some places, up to 7 feet of sediment will be dug up to that depth, allowing vessels to more easily maneuver before unloading, including log ships of up to about 620 feet bound for China.

The port’s description of its pier facilities lists the dockside depth at 36.5 feet.

The area was last dredged to 45 feet in 1978.

Vessel captains have expressed concerns about hitting bottom, Hartman said in an earlier interview.

Once dredging is completed again, hopes are “we do not have to do this again for another 40 years,” Hartman said Wednesday.

The project, originally scheduled for July 20-Sept. 4, was rescheduled to August, but the contractor, Legacy Contracting of Stayton, Ore., encountered delays, including problems securing the barge, Hartman said.

“The timing is not super critical other than it will be more difficult on the contractor as the weather starts to turn to rain,” he said.

“That will cause a lot more cleanup for the contractor.”

Hartman said the delay will not increase the cost to the port.

“The port is protected from that,” he said.

“We were not the cause of the delays.”

Design, sediment-core testing and permitting costs of $300,000 were not included in the contract.

Other costs that were higher than anticipated include an underestimated quantity of sediment to be removed, which increased from 13,000 cubic yards to 15,000 cubic yards, and additional soil testing that had to be conducted.

Costs over $1 million will be drawn from port reserves.

________

Senior Staff Writer Paul Gottlieb can be reached at 360-452-2345, ext. 55650, or at pgottlieb@peninsuladailynews.com.

More in News

KEITH THORPE/PENINSULA DAILY NEWS
June Ward, 10, examines a wooden paddle she is decorating as her father, Jack Ward of Port Angeles, works on his own paddle during a craft-making session on Friday at the Elwha Klallam Heritage Center in Port Angeles. The paddles are among the thousands of gifts being created for participants in the 2025 Tribal Canoe Journey, hosted this year by the Lower Elwha Klallam Tribe. The event begins with the landing of dozens of native canoes at the mouth of the Elwha River on July 31 and continues with five days of celebration on the Lower Elwha reservation west of Port Angeles. As many as 10,000 indigenous peoples are expected to take part. The public is invited to help with giftmaking sessions, scheduled daily from 9 a.m. to 4 p.m. at the Heritage Center.
Canoe paddle crafts

June Ward, 10, examines a wooden paddle she is decorating as her… Continue reading

Ralph Henry Keil and Ginny Grimm.
Long lost sailor to be honored at graduation

An honorary diploma will be presented to the family of… Continue reading

Singers to workshop vocal instruments at Fort Worden

One hundred and fifty singers to join together in song

Jefferson County fire danger risk level to move to high

Designation will prohibit fireworks over Fourth of July weekend

Candidate forums to be presented next week

The League of Women Voters of Clallam County and… Continue reading

Port Townsend City Council candidate forum set for next month

The League of Women Voters of Jefferson County will… Continue reading

Jefferson County to host series of community conversations

Jefferson County will conduct a series of Community Conversations… Continue reading

Denise Thornton of Sequim deadheads roses on a flower display at the Sequim Botanical Garden at the Water Reuse Demonstration Park at Carrie Blake Park on Wednesday in Sequim. Thornton, a volunteer gardener, was taking part in a work party to maintain the beauty of the garden. (Keith Thorpe/Peninsula Daily News)
Rose display

Denise Thornton of Sequim deadheads roses on a flower display at the… Continue reading

Electric rates see big increase

Jefferson proposal approved for 4-year hike

Clallam Transit to receive $4M in grants

Agency to use funds on Strait Shot and other routes

Port Angeles council OKs sidewalk near park

Applicants to receive grant funding for one-third of total cost