Neighbors shocked by piles of dirt from U.S. 101 widening

SEQUIM — Ed Telenick is bothered by a massive mound of dirt from a state project to widen a portion of U.S. Highway 101 that has replaced a wooded valley across from his home on Sherburne Road.

“I call it Mount Sherburne,” Telenick said at his home about 6 miles west of Sequim. “And every day, it’s gotten a little bit bigger.”

Scarsella Bros., the Kent-based contractor building two new lanes on the highway for the state, pays Port Angeles-based DelHur Industries to dump leftover dirt on the 15-acre property owned by DelHur.

“We needed a home for our dirt. They wanted it,” said Bob Scarsella, vice president of Scarsella Bros., who declined to comment on how much DelHur is being paid.

DelHur officials did not return repeated requests for comment.

Scarsella Bros. has been working since April on a $27.1 million state Department of Transportation project that will widen the last 3.5-mile stretch of the two-lane highway between Sequim and Port Angeles to four lanes. The project is expected to be completed next year.

For most of the spring and summer, excavators and dump trucks have been removing earth for the new lanes and hauling it to the Sherburne Road site, which sits south of the highway almost exactly at the midpoint of the widening project.

In an environmental analysis of the project, the state and federal departments of Transportation estimated that 234,800 cubic yards of dirt cut from hills and 62,000 cubic yards of fill would be exported from the highway project.

Scarsella said the plan is to dump about 125,000 cubic yards of dirt from the highway project at the Sherburne Road site.

Scarsella has another dump site permitted to hold 50,000 cubic yards of dirt behind the old Midway Metals shop at 258010 U.S. Highway 101, west of Barr Road, said Clallam County senior planner Greg Ballard.

No permit was needed to dump dirt at the Sherburne site, Ballard said.

Telenick said he didn’t know the valley across from his home would be filled in by the sand, loam and clay highway soil until trees started coming down.

“I know the dirt’s got to go somewhere, and I’m as happy about the new lanes on the highway as anybody,” he said.

“But nobody told us this was going to be here, and nobody seems to know how much bigger it’s going to get.”

Telenick is also worried about what may happen to “Mount Sherburne” in the future.

“I asked [DelHur CEO] Sam Hurworth right here what he plans to do with it,” Telenick said at the entrance to the dump site.

“One time, he told me he was going to divide it up and put houses on it.”

“Another time, he told me it was only temporary, that they were going to take the dirt away.”

According to the real estate records on file with the county Treasurer’s Office, DelHur purchased the property for $233,472 in March 2012.

At the end of June this year, the company also purchased properties on Cliff Robinson Road, near the landfill site.

Telenick said other neighbors have expressed concern to him about the dirt pile but are worried that the trees that remain on the property’s border will be cut down if they complain too much.

Disposal of dirt from construction is not part of the state’s concern, said Jerry Moore, project engineer for the state Department of Transportation’s Port Angeles office.

“Once the contractor digs it up, it becomes their dirt, and it’s up to them to find a legal place to get rid of it,” Moore said.

Ballard said the Sherburne Road property is a legal place to dump the dirt under county code.

“That’s a permitted use in our code,” Ballard said.

Because the property is not deemed a critical area, he said, the county had no regulation regarding clearing or grading the land, and DelHur was issued an administrative-use permit for the landfill, which means it didn’t need to notify neighbors or the public.

“These are the rules we have,” Ballard said.

Scarsella said his firm should be finished removing dirt from the new highway portions at the end of the construction season this fall.

Sequim-Dungeness Valley Editor Joe Smillie can be reached at 360-681-2390, ext. 5052, or at jsmillie@peninsuladailynews.com.

More in News

Port Angeles Parks & Recreation Department workers Brooke Keohokaloke, left, and Brian Flores steer a section of floating dock into place at the boat launch on Ediz Hook in Port Angeles on Wednesday. The floats had been removed and stored in a safe location to prevent wave damage from winter storms. (Keith Thorpe/Peninsula Daily News)
Dock in place

Port Angeles Parks & Recreation Department workers Brooke Keohokaloke, left, and Brian… Continue reading

Hospitals are likely to feel state cuts

OMC partners offer specialized care

Clallam jail program results in fewer overdoses

County had been ranked in top three in state

After almost 27 years with Port Townsend Main Street, Mari Mullen plans to step down following the town photo at the end of May. (Eryn Smith/Port Townsend Main Street Program)
Port Townsend Main Street director plans to step down

Award-winning program seeks replacement

Traffic to shift for new bridge

Work crews will shift traffic onto a new bridge over… Continue reading

BPA to discuss West End power outages

The Bonneville Power Administration will meet with area stakeholders to… Continue reading

Duke Sawtel of Olympia trims tree branches that interfere with power lines along Washington Street in Port Townsend. The Asplundh Tree Trimming company was hired by the Jefferson County PUD for the job. (Steve Mullensky/for Peninsula Daily News)
Tree trimming

Duke Sawtel of Olympia trims tree branches that interfere with power lines… Continue reading

Clallam Transit grant for purchase of new buses could be on hold

General manager says he’s retiring, with final day set for Aug. 1

Port Angeles to purchase hybrid, electric vehicles

Goal is to align with climate resiliency plan

Karyn Stillwell cold plunging in Alaska. (Karyn Stillwell)
Advocate to present benefits of cold water plunging

Stillwater cites ‘good stressor,’ adrenaline spikes

Trees to be removed prior to fish passage projects

Contractors are removing trees along U.S. Highway 101 south of… Continue reading

Levi Oravetz, 9, and his father Adam Oravetz put pre-measured rice and lentils into a funnel to be packaged for families in Ecuador. More than 100 volunteers from Independent Bible Church of Port Angeles packed 65,000 meals on Saturday. Almost $23,000 was raised by the church to buy the supplies. (Dave Logan/for Peninsula Daily News)
Meals for Ecuador

Levi Oravetz, 9, and his father Adam Oravetz put pre-measured rice and… Continue reading