Judge Brent Basden upheld a decision on Jan. 27 in Clallam County Superior Court that developer Ruth Brothers Enterprises, LLC., of Kent, must follow the City of Sequim’s conditions that a second access point must be created before construction can begin on 71 new homes in Jennie’s Meadow’s second and third phases. (Matthew Nash/Olympic Peninsula News Group)

Judge Brent Basden upheld a decision on Jan. 27 in Clallam County Superior Court that developer Ruth Brothers Enterprises, LLC., of Kent, must follow the City of Sequim’s conditions that a second access point must be created before construction can begin on 71 new homes in Jennie’s Meadow’s second and third phases. (Matthew Nash/Olympic Peninsula News Group)

Judge backs Sequim on subdivision decision

Developer cannot proceed without second entrance/exit installed

SEQUIM — A Clallam County Superior Court ruling keeps future phases of the Jennie’s Meadow subdivision in Sequim at a standstill for the foreseeable future.

On Jan. 27, Judge Brent Basden upheld the Sequim City Council’s May 2019 decision to deny a variance request from developer Ruth Brothers Enterprise, LLC, of Kent, to use Jennie’s Boulevard off North Priest Road to access the subdivision’s proposed 71 homes for Phases B and C.

Council members approved the two phases’ preliminary major subdivision on the west side of the Sequim city limits in 2019, but with conditions. Among them were that the Ruth Brothers owners need to prove their legal right to use Jennie’s Boulevard, and they must develop a second ingress/egress for the development.

The developer appealed in June 2019, saying the decision lacked “substantial evidence” and that it violated the Ruth Brothers’ constitutional rights.

Basden wrote in his decision that Washington state’s land use law “provides a clear standard to be applied by the city council in considering the appropriateness of a variance request.”

He wrote, “There is substantial evidence under RCW 36.70C.130(I) that supports the city’s denial of the requested variance. As such, it is also the case that the denial was not arbitrary and capricious.”

Basden reiterated the city’s 2018 municipal code, which reads, in part: “Each subdivision must have at least two points of access, except for those minor subdivisions or sort plats with four or fewer lots.”

The Jennie’s Meadow Phase A Homeowner’s Association (JMHA) also opposed the variance request because the organization felt a second entry and exit point was required under current city code.

City municipal code 17.32.110 states that subdivisions between four and 30 lots must have at least two points of access if separated by a minimum 10-foot-wide landscape area and encompass two, 20-foot-wide drive lanes.

Jennie’s Meadow residents testified before the city council in 2019 that if construction was allowed, equipment would use Jennie’s Boulevard as its main entry and exit point and travel down the hill and through a roundabout without a second entrance.

Fred Inman, chair for Jennie’s Meadow’s board of directors, said the developer didn’t have the right to use the road for development, and needed to demonstrate its right to use the road.

“We’re pleased the court supported the city’s decision,” Inman said.

City attorney Kristina Nelson-Gross shared a similar sentiment: “We’re pleased the court upheld the council’s decision.”

Attorney Craig Miller for Ruth Brothers stated many reasons for the land use appeal. He said the variance request was based on the wrong requirements (subdivision rather than zoning ordinance), and that the city’s code did not require two entrances/exits in 2005, when Phase A was approved by city council.

Miller had no comment on Basden’s decision or if Ruth Brothers’ owners sought a follow-up action to the ruling.

At a Jan. 11 hearing, Miller said the city’s ordinance “is a bit of a mess” and that, since Phase A was approved, the ordinance has been amended many times and the variance request was not heard by a hearing examiner as originally instructed.

Miller said Nelson-Gross was “making up all kinds of new conditions” and alleged that there’s no language saying Jennie’s Boulevard cannot be used as an access.

He added that, because developers aren’t dealing with public streets, they must acquire rights for access, and “it’s not easy to go to acquire an easement.”

In 2019, Scott Headrick, an engineer on the project working with Zenovic & Associates, Inc., said that Ruth Brothers’ owners explored other entrance options, but neighboring homeowners didn’t want to connect to the city, or the developers’ options were too costly.

Colette Kostelec, attorney for the homeowners association, said at the Jan. 11 hearing that the developer and their representatives never say “a secondary access is impossible” and homeowners interpreted it as a “dollar incentive thing.”

“The applicant needs to show the city there is no other alternative,” Kostelec said.

She added, “It’s important to have a second access point for construction (because) you don’t want construction vehicles going down Jennie’s Boulevard. That’s going to be a nightmare.”

With 89 homes in Phase A, including single-family homes in the lower portion and townhomes in the upper portion of the development, Basden asked if it would be in violation of city code with one way in and out if the issue were before the city now.

Nelson-Gross said she didn’t work with the city in 2005 so she didn’t know the circumstances behind the approval of Phase A, but “if that subdivision was presented today, we would not allow it.”

________

Matthew Nash is a reporter with the Olympic Peninsula News Group, which is composed of Sound Publishing newspapers Peninsula Daily News, Sequim Gazette and Forks Forum. Reach him at [email protected].

More in News

Seattle hospital to refuse some patients due to capacity

Harborview Medical Center in Seattle will temporarily… Continue reading

PHOTO BY: Susan Doupé
CAPTION: Priya Jayadev is the new executive director for Volunteer Hospice of Clallam County.
New executive director for Volunteer Hospice of Clallam County

Volunteer Hospice of Clallam County has hired Supriya “Priya” Jayadev as its… Continue reading

Steve Mullensky/for Peninsula Daily News
The Port Townsend City Council seeks to sell the Cherry Street property that had been barged over from Canada  five years ago to become affordable housing.
Port Townsend aims to sell Cherry Street housing project

Stalled for years, affordable housing project all but adandoned

Layla Franson, 15, and Jackson, her 10-year-old Quarter Horse, are competing in 4H at the Jefferson County Fair this weekend. Like many counties across the state, Jefferson County has seen a decline in the numbers of youths enrolled in 4H after the COVID lockdown and is actively seeking to reboot its program. (Paula Hunt/Peninsula Daily News)
Jefferson County Fair back after two-year hiatus

4H looks for bounceback after restrictions eased

Housing, opioids topics at county meetings

Meetings across Clallam, Jeffersom counties

Keith Thorpe/Peninsula Daily News
Fair Queen Allison Pettit, front, and Queen's Court Sophia Lawson, shown on Aug. 6 on their parade float in the Joyce Daze Wild Blackberry Festival, will preside over the Clallam County Fair starting on Thursday in Port Angeles.
Clallam County Fair back in 2022

Four days of grandstand events, music, food and fun start Thursday

Keith Thorpe/Peninsula Daily News
Scaffolding covers a section of the sidewalk in the 100 block of West First Street to support workers as they upgrade the the facade on Lee Plaza.
Affordable housing units get upgrades

Scaffolding in downtown Port Angeles evidence of one of several PHA projects

Lower Dungeness: Towne Road and Levee Trail closed

Towne Road and the adjacent Dungeness Levee Trail are currently… Continue reading

Most Read