Construction crews work to rebuild the Rialto Beach jetty as seen from across the Quillayute River from LaPush. (Lonnie Archibald)

Construction crews work to rebuild the Rialto Beach jetty as seen from across the Quillayute River from LaPush. (Lonnie Archibald)

Work underway on damaged section of Rialto revetment at La Push

U.S. Army Corps of Engineers estimates that the repairs on the 300-foot-long section of the protective jetty will be finished in about three weeks.

LA PUSH — Work continues on a 300-foot-long damaged section of the Rialto revetment near La Push, with the U.S. Army Corps of Engineers estimating repairs will be completed in about three weeks.

Coastal revetments are sloping structures placed on banks or cliffs that absorb the energy of incoming water in order to prevent erosion. The damaged barrier is essentially a rocky jetty that protects La Push.

A 300-foot-long stretch of the revetment has failed on the west side, according to the Corps, and only the underlying gravel berm remains.

So far, the project is slated to cost about $1.6 million, said Patricia C. Graesser, U.S. Army Corps of Engineers public affairs supervisor for the Greater Seattle area.

The repairs are being conducted by Bruch & Bruch Construction Inc. of Port Angeles, Columbia Granite LLC of Olympia, and SEA Construction LLC of Raymond.

“A crew of three from the Corps is overseeing repairs to the revetment and expect to complete work in the next few weeks,” Graesser said.

It isn’t clear exactly when or how the revetment was damaged, but officials believe winter storms last year were likely the cause, said Bill Dowell, U.S. Army Corp of Engineers spokesperson.

Noticed in spring

The damage was first noticed in late March or early April of this year, he said.

Before construction crews and heavy equipment could access the revetment, a damaged stretch of Mora Road in Olympic National Park — the only access road to the site — needed to be repaired and widened, Graesser said.

A Corps team began widening the road Oct. 14 to allow trucks to haul material to the revetment for the needed repairs.

As of Friday, contractors were delivering stone to the site that will be used to strengthen the barrier, Graesser said.

The 3,000-foot-long revetment was built in 1974 and last rehabilitated after a breach in 1996, Graesser said.

The structure’s crest in the damaged area is between four and six feet lower than the design elevation and adjacent structure elevation, according to the Corps. Given the revetment’s condition, if no action was taken a breach in the damaged area would be highly probable.

Emergency repair efforts were prompted by a series of storms that arrived in the Pacific Northwest beginning Oct. 13, according to Graesser.

If the revetment had been breached during the storms, it could have exposed the Quileute reservation riverward shoreline, Coast Guard Station, training wall and Quileute Marina to direct wave action, Graesser said.

A training wall is an artificial embankment or wall for directing the course of a stream or river, in this case the Quillayute River, which runs to the east of Rialto Beach.

The training wall is not designed to protect the marina or other facilities from wave action and likely would have been destroyed if exposed to ocean waves and debris, Graesser said.

Because the marina is the only safe harbor for 60 miles along the Pacific Ocean, the Corps initiated emergency repairs to the revetment, Graesser said.

“Because of the threat of a breach, we received emergency funding to address the immediate threat,” she said.

“Additional work will still be required after storm season.”

The threat underscores efforts by the Quileute tribe to move much of its community. Much of the reservation — including the existing school site adjacent to First Beach, the Quileute Tribal Center, the Quileute Senior Center and many homes — is directly in the path of possible tsunamis or flooding from the Quillayute River, according to the Quileute tribe.

________

Features Editor Chris McDaniel can be reached at 360-452-2345, ext. 56650, or at cmcdaniel@peninsuladailynews.com.

Reporter Jesse Major contributed to this report.

Road closed signs are set up at the Mora Ranger Station on the Mora Road as the road from that point on to Rialto Beach is closed due to work being done on the rialto Beach jetty. (Lonnie Archibald)

Road closed signs are set up at the Mora Ranger Station on the Mora Road as the road from that point on to Rialto Beach is closed due to work being done on the rialto Beach jetty. (Lonnie Archibald)

More in News

C.J. Conrad and Chris Orr of A&R Solar take solar panels from a lift on top of the Port Angeles Senior and Community Center on Peabody Street to be installed on the roof. The 117 panels are mostly made of silicone and will provide electrical power to the center. The crew members are each tied in with ropes to prevent any problems on the slippery slanted roof. The panels are 42 inches by 62 inches and weigh about 16 pounds. (Dave Logan/for Peninsula Daily News)
Solar installation

C.J. Conrad and Chris Orr of A&R Solar take solar panels from… Continue reading

Port Townsend Food Co-op board president resigns

Rowe cites unresolved tensions, calls for change

Recompete projects aim to close gap for workers in prime age

Goals include reducing barriers, creating up to 1,300 jobs

Carrie Heaton.
Governor appoints Heaton to PC trustees

Five-member board governs college’s policy, strategic planning

Finalists named for Port Angeles community awards

The Port Angeles Chamber of Commerce will announce the… Continue reading

Fort Worden Hospitality ceasing operations

No longer viable amid PDA financial and legal challenges

Phyllis Becker of Port Hadlock, foreground, and Wendy Davis of Port Townsend, volunteers with the Jefferson County Trash Task Force, pick up litter along Discovery Road on Sunday during the first trash pickup of the year. (Steve Mullensky/for Peninsula Daily News)
Litter patrol

Phyllis Becker of Port Hadlock, foreground, and Wendy Davis of Port Townsend,… Continue reading

Jefferson County defers oversight role for homelessness grant

OlyCAP will continue to be lead agency for Commerce funding

Members of Trail Life USA, a boys Christian adventure organization, salute the burning retired flags and holiday wreaths from veterans’ graves. This joint flag retirement and wreath burning ceremony took place Saturday at the Bekkevar farm in Blyn. (Emma Maple/Peninsula Daily News)
Flags, veterans’ wreaths retired at ceremony

Boys, girls organizations attend event at farm

One person taken to hospital after three-car collision

Two people were injured following a three-car collision on… Continue reading

Jefferson Conservation District seeking board candidates

The Jefferson County Conservation District is accepting applications for… Continue reading