PORT ANGELES — The Polar Pioneer­ may be staying in Port Angeles Harbor longer than planned after Seattle’s mayor said his city’s port must apply for a new permit before it can host the oil rig.

The mobile oil rig has been anchored in Port Angeles since April 17 and was scheduled to be towed to Seattle sometime this week.

That is no longer possible because the Seattle Department of Planning and Development has issued a code interpretation stating an additional use permit is required before the Polar Pioneer — and two accompanying tugboats — can moor at the Port of Seattle’s Terminal 5 facility as scheduled, Mayor Ed Murray announced at an environmental group’s breakfast Monday.

The Polar Pioneer had been scheduled to be anchored there briefly before a planned trip north to the Arctic Ocean.

The 400-foot-long, 355-feet-tall rig owned by Transocean Ltd. is being leased by Royal Dutch Shell, the parent company of Shell Oil Co., and is one of two drill rigs the company hopes to use for exploratory drilling this summer in the Chukchi Sea, off Alaska’s northern shore.

After the drilling season is over, plans called for it to return to Seattle’s Terminal 5 where it would be at anchor for at least six months during the winter months.

The Department of Planning and Development announced Monday that storing oil rigs is not included in the 20-year-old permit for Terminal 5.

“It is not a cargo terminal use [as it] is permitted for now,” said Bryan Stevens of the Seattle Department of Planning and Development.

“There are certain accessory functions that can occur in relation to a cargo terminal, but this went beyond that.”

Since it is not a cargo terminal use, “we need to talk to the port about what the most appropriate use classification is and then determine what that permit process would be like,” Stevens said.

“The next step is for the Port [of Seattle] to communicate with us if they plan on continuing to move forward or not,” Stevens said.

The ensuing permitting process, “depending on where that conversation goes, could be anywhere from a few weeks to several months,” Stevens noted.

“It really depends on how that use is classified and whether it somehow triggers a public permit process or not.”

That could mean the Polar Pioneer may stay in Port Angeles indefinitely until a new permit is granted, though Shell Oil has not publicly commented on what it plans to do next.

“We are reviewing the interpretations” of the code statement, said Megan Baldino, Shell spokeswoman.

“I expect the port to obtain all required city permits before any moorage or work begins at T5 on offshore oil drilling equipment,” Murray said.

“While requiring a new permit may not stop the port’s plans, it does give the port an opportunity to pause and rethink this issue.”

The Noble Discoverer, a drill ship also on its way to Seattle, is expected to arrive there in mid-May.

It will not moor in Terminal 5, According to the Department of Planning and Development.

Information about what terminal the Noble Discoverer is slated for, and if it too will be affected by the code interpretation, was not available Monday.

The code interpretation will be formally posted online to the Department of Planning and Development website later this week.

When that happens, there will be a 14-day appeal period to reverse the decision.

If Shell Oil decides to leave the Polar Pioneer here while the permitting process proceeds, or to reroute the Noble Discoverer here, there would be plenty of space to accommodate them both.

“There is five anchorages in the harbor,” said Lt. Dana Warr, a Coast Guard spokesman based in Seattle.

“It works kind of like a hotel. The ships would make reservations in advance” with the Coast Guard traffic service.

“However, if the Noble Discoverer was to arrive, it can be accommodated with the Polar Pioneer in place as long as other commercial traffic isn’t already there.”

Such a presence would be welcomed by the Port of Port Angeles.

“We are delighted to have them here while they are here,” said Port of Port Angeles Executive Director Ken O’Hollaren.

“There is no question that the Polar Pioneer’s presence here in the harbor has had a significant economic impact on the area, so we hope to be able to accommodate that line of the business here in the future.”

________

Sequim-Dungeness Valley Editor Chris McDaniel can be reached at 360-681-2390, ext. 5052, or cmcdaniel@peninsuladailynews.com.

More in News

A massive kinetic skulpture called Maxtivity’s GLORY-ous Chocolate Turtle from Corvallis, Ore., negotiates a turn on Water Street during the 40th Kinetic Skulpture Parade and Race in downtown Port Townsend on Saturday. (Steve Mullensky/for Peninsula Daily News)
Kinetic Skulpture race

A massive kinetic skulpture called Maxtivity’s GLORY-ous Chocolate Turtle from Corvallis, Ore.,… Continue reading

The fireworks display, seen over Carrie Blake Community Park on July 4, 2023, started after the ban on the discharge of fireworks in the city of Sequim. City council members host a public hearing on whether or not to ban the sale of fireworks on Oct. 14. (Michael Dashiell/Olympic Peninsula News Group)
Sequim to host fireworks hearing

City council to consider banning sales

Staff with PNNL-Sequim plan to expand the laboratory space by demolishing two temporary buildings by Washington Harbor along Sequim Bay and build a three-story structure. They also intend to add Sequim utilities along West Sequim Bay Road in the coming years. (Andrea Starr/Pacific Northwest National Laboratory)
PNNL-Sequim expansion linked to West Sequim Bay Road utility additions

City water, sewer improvements could go to bid mid-2025

Fire districts focus on smoke alarms during prevention week

Fire districts across Clallam and Jefferson counties are gearing… Continue reading

Weekly flight operations scheduled

There will be field carrier landing practice operations for aircraft… Continue reading

State and local officials toured Dabob Bay forests in 2022. Back row, left to right, Mary Jean Ryan of Quilcene; Rachel Bollens; Bill Taylor, Taylor Shellfish Co.; Jeromy Sullivan, Port Gamble S’Klallam Tribe; Justin Allegro, The Nature Conservancy; and Greg Brotherton, Jefferson County Commissioner. Front row, left to right, Duane Emmons, DNR staff; Jean Ball of Quilcene; Hilary Franz, state Commissioner of Public Lands; Mike Chapman, state Representative; and Peter Bahls, director of Northwest Watershed Institute. (Keith Lazelle)
Dabob Bay conservation area expands by nearly 4,000 acres

State, local partners collaborate on preservation effort

Three bond options on table for Sequim

School board considering February ballot

State EV rebate program proving to be popular

Peninsula dealerships participating in Commerce project

Scott Curtin.
Port Angeles hires new public works director

Scott Curtin says he will prioritize capit al plan

KEITH THORPE/PENINSULA DAILY NEWS
Shelby Vaughan, left, and her mother, Martha Vaughan, along with a selection of dogs, plan to construct dog shelters at Fox-Bell farm near Sequim in an effort to assist the Clallam County Humane Society with housing wayward canines.
Fox-Bell Humane Society transforming property

Goal is to turn 3 to 4 acres into new place for adoptable dogs

Phone policy varies at schools

Leaders advocating for distraction-free learning