Port Angeles’ 2012 budget deficit could hinder some plans, but water development project to go through

PORT ANGELES — The city of Port Angeles’ $900,000 estimated deficit for next year is not expected to hinder its waterfront redevelopment plans, though street paving and other infrastructure-related projects may suffer.

“We’ll have to reduce some of our focus on infrastructure, street maintenance and improvements,” said City Manager Kent Myers on Thursday.

“We’re looking at decreases in some of that area.”

City Council members were told of a possible $900,000 deficit for 2012 at a budget work session Tuesday.

Disparity in deficits

The disparity in the projected deficit’s impact on projects mainly has to do with how they are funded, Myers said.

The waterfront development project is funded through the economic development and lodging tax funds, while the deficit itself is limited mainly to the general fund.

The general fund supports core city services, such as police, fire, streets, parks and recreation.

It can also be used to support other funds, including the capital facilities fund, which covers large infrastructure projects.

But this year, because of the projected deficit, no such contribution to capital projects is expected to be made.

Operating expenses

City Finance Director Yvonne Ziomkowski said the projected deficit is made up almost entirely of the city’s operating expenses.

Only one infrastructure-related project, a citywide wireless network for the police and fire departments, is a factor.

That project is budgeted at $300,000 and will be funded by the Port Angeles Police Department’s reserves.

The city’s Waterfront and Transportation Improvement Plan, which includes redevelopment of the waterfront, is expected to cost the city $1.7 million to develop.

No general fund contributions are expected to be made.

Nathan West, city economic and community development director, said he is requesting $500,000 from the economic development fund to begin construction of an esplanade, a portion of the waterfront plan.

$3.5 million fund

The fund has $3.5 mill­ion.

The esplanade is budgeted at $1.9 million, and West said the city would need to receive grant funding to cover the additional cost and break ground.

“Our hope is that goes to a grant match,” he said of the funding request.

The entire waterfront plan is estimated to cost around $17 million to implement.

Myers said the city is breaking the project up into phases, so there is no comm­itment to spend the entire amount.

But he said the city is pursuing the project even while facing budget constraints because the public is behind it.

Myers: Residents pro

“Based upon public hearings and public input, the citizens want to continue the project over the next several years,” Myers said.

The city this week started looking at how to reduce the deficit.

Myers said cuts will likely affect all services supp­orted by the general fund.

But he said proposed program cuts have not been decided.

“It’s too early to tell on that,” Myers said.

The budget will be approved in December.

Public hearings on the budget are scheduled for Sept. 27, Nov. 1, Nov. 15 and Dec. 6.

________

Reporter Tom Callis can be reached at 360-417-3532 or at tom.callis@peninsuladailynews.com.

More in News

U.S. Rep. Emily Randall.
US Rep. Randall speaks on House floor about insurance

Example of fictional family shows premium increase of more than 1,000 percent

Spending patterns led to pool audit

Office identifies $33K in unsupported payments

Comments oppose plan against Port Townsend zoning changes

Option would increase maximum limit on units per 40,000 square feet

x
Sequim program uses grant for utilities, rent

Community support through Peninsula Home Fund gives $10,000 to organization

Firefighters Tyler Gage and Tatiana Hyldahl check out the light connections on the 1956 fire truck that will travel the streets of Port Angeles during the 41st Operation Candy Cane beginning Monday. Santa and his helpers will pass out candy canes to those who donate food items or cash. The runs will begin at 5:30 p.m. and include the following areas: Monday, west of I street and M street; Tuesday, I and L streets to C street; Wednesday, C Street to Lincoln Street; Thursday, Chase Street to Chambers Street; Friday, Jones Street to Golf Course Road; Dec. 13, above Lauridsen Boulevard. It will be stationary from 5:30 p.m. to 7 p.m. on Dec. 14 at the Port Angeles Grocery Outlet and during the same time on Dec. 15 at Lower Elwha Food and Fuel. (Dave Logan/for Peninsula Daily News)
Operation Candy Cane

Firefighters Tyler Gage and Tatiana Hyldahl check out the light connections on… Continue reading

Online survey launched for Sequim parks access

The city of Sequim has launched an online survey to… Continue reading

Crews work to remove metal siding on the north side of Field Arts & Events Hall on Thursday in Port Angeles. The siding is being removed so it can be replaced. (Dave Logan/for Peninsula Daily News)
Siding to be replaced

Crews work to remove metal siding on the north side of Field… Continue reading

Tsunami study provides advice

Results to be discussed on Jan. 20 at Field Hall

Chef Arran Stark speaks with attendees as they eat ratatouille — mixed roasted vegetables and roasted delicata squash — that he prepared in his cooking with vegetables class. (Elijah Sussman/Peninsula Daily News)
Nonprofit school is cooking at fairgrounds

Remaining lectures to cover how to prepare salmon and chicken

Port Townsend Main Street Program volunteers, from left, Amy Jordan, Gillian Amas and Sue Authur, and Main Street employees, Sasha Landes, on the ladder, and marketing director Eryn Smith, spend a rainy morning decorating the community Christmas tree at the Haller Fountain on Wednesday. The tree will be lit at 4 p.m. Saturday following Santa’s arrival by the Kiwanis choo choo train. (Steve Mullensky/for Peninsula Daily News)
Decoration preparation

Port Townsend Main Street Program volunteers, from left, Amy Jordan, Gillian Amas… Continue reading

Port Angeles approves balanced $200M budget

City investing in savings for capital projects