Point Hudson Marina project delayed at least a year

QUILCENE — Construction of a Point Hudson Marina moorage and facilities improvement project must wait at least a year because Port of Port Townsend officials have hit snags involving dredging and timing.

The result, said Port Executive Director Larry Crockett, is delaying construction until after the 2006 Wooden Boat Festival.

“People say, ‘I thought you are going to have all the dock in this winter,”‘ Crockett told Port commissioners Wednesday.

“Well, this is Washington state and we have to do certain permits.”

Process taking longer

During a Port commissioners meeting at the Quilcene Harbor Yacht Club on Quilcene Bay, Deputy Director Jim Pivarnik said Corps of Engineers approval of dredging proposed near the marina entrance was taking far longer than anticipated.

“What we thought would be a 30-day process has turned into a four-month process,” Pivarnik said.

The Corps of Engineers must review Port engineers’ proposal, plus marina dredge samples were required, said Pivarnik.

He added that the work delay could not all be blamed on the Corps of Engineers.

The Port also faces time constraints to schedule work, with the Wooden Boat Festival this September and visitor traffic to the marina popular with boaters throughout Puget Sound.

“We have a small window of opportunity to accommodate the customers,” Pivarnik said.

While construction is stalled, Pivarnik and Crockett said they would work with the Port’s Marina Committee about cost issues facing the project’s proposed amenities.

Port Finance Director Don Taylor said securing bond financing is also an issue, with the possibility of selling bonds this fall.

Taylor said with interest rates low, the Port could take advantage of the current bond market to refinance the project.

The marina currently has 45 boat slips and 800 feet of linear docks.

The new marina would add docks and have about 1,000 linear feet of moorage, with additional moorage for boats 40 feet long or less.

More in News

U.S. Rep. Emily Randall.
US Rep. Randall speaks on House floor about insurance

Example of fictional family shows premium increase of more than 1,000 percent

Spending patterns led to pool audit

Office identifies $33K in unsupported payments

Comments oppose plan against Port Townsend zoning changes

Option would increase maximum limit on units per 40,000 square feet

x
Sequim program uses grant for utilities, rent

Community support through Peninsula Home Fund gives $10,000 to organization

Firefighters Tyler Gage and Tatiana Hyldahl check out the light connections on the 1956 fire truck that will travel the streets of Port Angeles during the 41st Operation Candy Cane beginning Monday. Santa and his helpers will pass out candy canes to those who donate food items or cash. The runs will begin at 5:30 p.m. and include the following areas: Monday, west of I street and M street; Tuesday, I and L streets to C street; Wednesday, C Street to Lincoln Street; Thursday, Chase Street to Chambers Street; Friday, Jones Street to Golf Course Road; Dec. 13, above Lauridsen Boulevard. It will be stationary from 5:30 p.m. to 7 p.m. on Dec. 14 at the Port Angeles Grocery Outlet and during the same time on Dec. 15 at Lower Elwha Food and Fuel. (Dave Logan/for Peninsula Daily News)
Operation Candy Cane

Firefighters Tyler Gage and Tatiana Hyldahl check out the light connections on… Continue reading

Online survey launched for Sequim parks access

The city of Sequim has launched an online survey to… Continue reading

Crews work to remove metal siding on the north side of Field Arts & Events Hall on Thursday in Port Angeles. The siding is being removed so it can be replaced. (Dave Logan/for Peninsula Daily News)
Siding to be replaced

Crews work to remove metal siding on the north side of Field… Continue reading

Tsunami study provides advice

Results to be discussed on Jan. 20 at Field Hall

Chef Arran Stark speaks with attendees as they eat ratatouille — mixed roasted vegetables and roasted delicata squash — that he prepared in his cooking with vegetables class. (Elijah Sussman/Peninsula Daily News)
Nonprofit school is cooking at fairgrounds

Remaining lectures to cover how to prepare salmon and chicken

Port Townsend Main Street Program volunteers, from left, Amy Jordan, Gillian Amas and Sue Authur, and Main Street employees, Sasha Landes, on the ladder, and marketing director Eryn Smith, spend a rainy morning decorating the community Christmas tree at the Haller Fountain on Wednesday. The tree will be lit at 4 p.m. Saturday following Santa’s arrival by the Kiwanis choo choo train. (Steve Mullensky/for Peninsula Daily News)
Decoration preparation

Port Townsend Main Street Program volunteers, from left, Amy Jordan, Gillian Amas… Continue reading

Port Angeles approves balanced $200M budget

City investing in savings for capital projects