Nine bids received for $3 million Port Townsend Boat Haven project

PORT TOWNSEND — A contract is expected to be awarded June 15 after Port of Port Townsend leaders on Thursday opened nine contractor bids on a project to replace the AB Docks at Boat Haven marina.

The apparent lower bidder was Redside Construction LLC of Port Gamble at $3.08 million, said port Executive Director Larry Crockett, but he and port officials must ensure the contractor would be both “responsive and responsible” to carry out the work.

The project will replace aging recreational boat docks and slips for about 100 boats.

All but one of the bids opened at the port offices Thursday were under the port’s engineering estimate of $3.96 million.

About 24 firms contacted the port in recent weeks about bidding on the project, but nine actually submitted bid packages.

“We’ve got a lot of due diligence to do,” said port Deputy Director Jim Pivarnik.

Port of Port Townsend Commissioner John Collins, who attended the bid opening with contractor representatives, said he was pleased by the number of bidders and the lower-than-estimated bids.

Out-of-water work is expected to begin shortly after the contract is awarded, but actual removal of the old and installation of the new docks cannot take place until after the annual Wooden Boat Festival ends Sept. 12.

In-water work would have to be completed by Feb. 15 when the state closes the allowable in-water work period intended to protect migrating salmon.

Crockett said the port has met with moorage tenants at the marina to orchestrate moving their boats to temporary moorage until the docks are replaced.

Boats will be temporarily moved to Point Hudson Marina and other locations at the Boat Haven.

Electrical work and installation of gangways can be done when the fish window closes to in-water work because it is above water and does not disturb the salmon migration.

Boats should be allowed to return to the new marina after project completion in mid to late April 2011, Crockett said.

Financing has been secured for renovation of the AB Docks built in 1967, Crockett said, with the revenue bonds at lower prices because of the stock market decline.

The docks were given a life of 25 years when they were built, Crockett said, which meant they should have been replaced in the early 1990s.

With little demand form marina tenants to replace them, it never happened.

However, Crockett said, the docks are slowly decaying and are in places made of materials that are not environmentally sound, such as Styrofoam.

While it has been figured that the port’s bond debt would come to about $400,000 a month, port officials said it is possible that payments could be lowered initially to $250,000 for two years.

The AB Docks project, like Point Hudson Marina’s upgrade in 2006-2007, would be upgraded to Americans with Disabilities Act specifications and city building codes, although space for about 13 boats would be lost.

Crockett said the port would likely go out to bid in January or February for a project to replace the 70-ton heavy haulout pier, moving it next to the existing 300-ton heavy haulout pier.

The port is still working through the heavy-haulout project permitting process with the Corps of Engineers, Crockett said.

________

Port Townsend-Jefferson County Editor Jeff Chew can be reached at 360-385-2335 or at jeff.chew@peninsuladailynews.com.

More in News

State Treasurer Mike Pellicciotti, in cab, gets guidance operating a Develon DX300LL-5 log loader on Tuesday from Port of Port Angeles log yard equipment operator Jodie O’Neel. The port purchased the $449,000 log loader through the Office of the State Treasurer LOCAL government financing program, which provides municipalities with low-cost loans for equipment and real estate purchases. Pellicciotti visited Port Angeles to talk about the LOCAL program. (Paula Hunt/Peninsula Daily News)
Log loader financing

State Treasurer Mike Pellicciotti, in cab, gets guidance operating a Develon DX300LL-5… Continue reading

Clallam awards lodging tax grants

Seven organizations to benefit

Matt Butler performs at Camden County Correctional Facility in 2018 in New Jersey. (Mario Diurno)
Singer to perform at Field Hall, Clallam Bay Corrections Center

Butler has been performing at jails, prisons for nearly a decade

Two hospitalized after collision on Highway 104

Two people were taken to hospitals following a collision on… Continue reading

Dee Norlin, right, of Port Townsend and host at Pasture House, one of the eight homes on the AAUW Kitchen Tour on Marrowstone Island, points out the cabinetry, red alder, madrona and cedar and counter surfaces in a recently remodeled home and kitchen using the latest technologies to make the home eco-friendly and efficient. (Steve Mullensky/for Peninsula Daily News)
Kitchen tour

Dee Norlin, right, of Port Townsend and host at Pasture House, one… Continue reading

Utilizing funding from the Institute of Museum and Library Services, tabletop game programming is offered at the North Olympic Library System.
Libraries bracing for loss of funding

Online resources are on chopping block

Poplars to be removed on Sims Way next month

Work to begin a multi-year project to expand port’s boatyard

Chimacum Elementary to get new playground

Half-million-dollar project expected to be installed at school later this week

Fire in transient encampment closes Tumwater Truck Route

The Port Angeles Fire Department and a crew from… Continue reading

Man flown to Harborview after car strikes pole

A 20-year-old man was flown to a Seattle hospital… Continue reading

Two sent to hospitals after rear-end collision

Two people were taken to hospitals following a rear-end collision… Continue reading

Security exercise planned for Friday

Naval Magazine Indian Island will conduct a security training… Continue reading