Mill dock removal starts Monday

Ennis Creek concerns

PORT ANGELES — After a week’s delay, workers will start Monday on the full-on dismantling of the 1,050-foot Rayonier pulp mill dock that juts into Port Angeles Harbor east of the city’s downtown core.

Floating equipment arrived at the site Thursday, Warren Snyder, director of legacy sites for Rayonier Advanced Materials, the current land owner, said Friday in an email.

The initial removal of about 800 concrete panels as part of the overall environmental cleanup of the 75-acre site will occur from a barge before equipment is staged onshore, Rayonier AM spokesperson Ryan Houck said last week in an email.

The panels will be stacked for potential future reuse on the site.

“The panel removal typically occurs first, with the staging to follow after they have enough panels on the barge to offload (likely later in the week),” Houck said. “All of this is subject to unforeseen changes, but that’s the plan.”

Work will include removal of a warehouse on the 250-foot-wide pier and removal of a 120-foot-long, 14-foot-wide railroad trestle across Ennis Creek, an urban, fish-bearing stream that empties into the harbor.

Robbie Mantooth, co-founder of the environmental stewardship group Friends of Ennis Creek, had expressed concerns about work conducted at the mouth of the waterway.

Snyder told Mantooth in an email that the concrete piers under the trestle are not new and that logs were not placed there by Rayonier but appear to have floated in from the harbor.

“The work we are planning to start [this] week is just removal of the above water decking, from the trestle,” Snyder said.

“No work will be done on the concrete abutments or concrete piers in the creek channel, no pilings will be removed and no sediment or gravel will be disturbed.”

Houck has said the panels, some of which were removed in November, will be completely removed by the end of July. More than 5,000 toxic creosote pilings will be pulled out of the harbor at an unspecified date in the future.

“We are finalizing plans to remove the remainder of the dock,” Houck said in an email.

“Essentially, we’re working in coordination with [the Department of Natural Resources] and [Department of] Ecology to pursue a ‘phased’ approach. The current dock work is the first phase.”

Ecology officials have predicted that overall cleanup of the parcel, which Rayonier AM is funding at an cost of $26.6 million, will begin in 2023.

“We’ll defer to Ecology on the timeline since they’re leading this process,” Houck said.

Debris from deck and warehouse removal will be transported off-site for disposal or recycled.

The project is part of a cleanup that’s in its 21st year.

________

Senior Staff Writer Paul Gottlieb can be reached at 360-452-2345, ext. 55650, or at [email protected].

More in News

Bret Allen Kenney was in court on Friday.
$5 million bail set in officer assault

Man also a person of interest in homicide of his mother

Candidate filing week ends with list of hopefuls

Three contests to be on primary ballot

Housing, fish passage topics at county meetings

Government entities gather on North Olympic Peninsula

Clallam Farm Family of the Year nominations sought

The Clallam County Fair invites the public to submit… Continue reading

Brian King, left, and Marc Titterness.
Candidates for sheriff debate during forum

Wraparound services, staffing among issues discussed

Dick Richardson, volunteer coordinator of the U.S. Light House Society, shows off the 1880’s French made fresnel lens at the top of the Point Wilson Light at Fort Worden State Park. The society is the caretaker of the lighthouse, under a license from the U.S. Coast Guard. Public tours are conducted from 11 a.m. to 4 p.m. on Saturdays and Sundays. Because of liability issues and Coast Guard regulations, the top floor, where the lens is located, will be off limits. (Steve Mullensky/for Peninsula Daily News)
Lighthouse tours

Dick Richardson, volunteer coordinator of the U.S. Light House Society, shows off… Continue reading

Port sunsets discount program

Storage had been half price if prepaid

The Worthington Mansion restoration includes 9,000 cedar shingles that were hand dipped bay volunteers two years ago. They are installed on the mansard roof. The top floor of the mansion which is the interior of the roof area is envisioned to become a library area and meeting space. (Peninsula Daily News file)
Worthington Mansion volunteers to cut the ribbon

Overnight stays expected to begin in June

Construction tentatively finishes this week at the new Woodcock Road roundabout. (Bob Lampert)
Woodcock Road roundabout to tentatively finish May 20

Work on the Woodcock Road/Sequim-Dungeness Way roundabout is expected to… Continue reading

Most Read