Long delays around Lake Crescent halted for summer months

LAKE CRESCENT — Olympic National Park has suspended four-hour delays on U.S. Highway 101 at Lake Crescent on weekdays for the next three and a half months.

The announcement this week is an about-face from earlier plans.

Drivers should continue to expect half-hour delays at the lake from Mondays through Fridays during work hours.

The four-hour delays from Mondays through Thursdays will resume Sept. 3.

“To avoid excessive impacts on summer traffic, the road restoration repairs will begin after Labor Day,” park officials said in a Wednesday announcement.

“The work will require four-hour delays Monday through Thursday beginning Sept. 3. This work is anticipated to be completed within the 20-day closure (five work weeks) allowed by the contract,” according to the park’s press release.

The first plan was to avoid four-hour delays between Memorial Day and Labor Day to limit impacts on summer travel. But last week, park officials announced that the four-hour delays would continue on weekdays through June 13 to expedite the final phase of the $27.5 million, three-year project.

The four-hour delays, which began Monday and ended Thursday, are necessary for crews to restore the roadway width and shoulder area in front of a rock wall near milepost 229.

During construction this week, it became apparent that the June 13 target for completion was “not going to be feasible,” said Lisa Turecek, Olympic National Park chief of facility management.

“If we continued, we were committed to it,” Turecek said in a telephone interview.

“We decided it was too much risk of having extended traffic impacts into the summer.”

Park officials originally had planned to begin the four-hour delays mid-April, but it lacked a permit from the U.S. Army Corps of Engineers to work below the ordinary high water mark. That permit was received last week, allowing for construction earlier this week.

Crews this week stabilized slopes and placed riprap where gating baskets had failed near milepost 229.

“We were able to look at the site conditions a little more closely,” Turecek said

It was determined that that the remaining work would be “a little bit more involved” than previously thought, she said.

“We appreciate everyone’s patience,” Turecek said.

The Lake Crescent project is being managed by the Federal Highway Administration and the National Park Service.

Strider Construction Inc. of Bellingham is the contractor.

Remaining work that will occur this spring and summer includes sign replacement, paving the final 2½-inch layer of asphalt and striping.

Paving is set to begin June 3 and will last for six to eight weeks depending on weather, park officials said.

Paving near the rock wall will take place in the fall.

Weekday half-hour delays are restricted to two hours after sunrise to two hours before sunset.

________

Reporter Rob Ollikainen can be reached at 360-452-2345, ext. 56450, or at rollikainen@peninsuladailynews.com.

More in News

Quilcene schools, Clallam Bay fire district measures passing

Voters in Jefferson and Clallam counties appear to have passed measures for… Continue reading

Tribe seeking funds for hotel

Plans still in works for downtown Port Angeles

Clallam County eyes second set of lodging tax applications

Increase more than doubles support from 2023

Olympic Medical Center reports operating losses

Hospital audit shows $28 million shortfall

Jefferson County joins opioid settlement

Deal with Johnson & Johnson to bring more than $200,000

Ballots due today for elections in Clallam, Jefferson counties

It’s Election Day for voters in Quilcene and Clallam… Continue reading

Jefferson PUD has clean audit for 2022

Jefferson County Public Utility District #1 has received a… Continue reading

Jefferson Transit opens survey on climate action plan

Jefferson Transit Authority will conduct a survey through June… Continue reading

Three volunteers sought for Clallam County Disability Board

The Clallam County Disability Board is seeking volunteers to… Continue reading

Pictured, from left, are Mary Kelso, Jane Marks, Barbara Silva and Linda Cooper.
School donation

The Port Angeles Garden Club donated $800 to the Crescent School in… Continue reading

Clayton Hergert, 2, along with is mother, Mandy Hergert of Port Angeles, sit at the bow of a U.S. Coast Guard response boat on display during Saturday’s Healthy Kids Day at the Port Angeles YMCA. The event, hosted by all three Olympic Peninsula YMCA branches, featured children’s activities designed to promote a healthy lifestyle and a love for physical activity. (Keith Thorpe/Peninsula Daily News)
Captain on deck

Clayton Hergert, 2, along with is mother, Mandy Hergert of Port Angeles,… Continue reading

Clallam County Fire District 3 commissioners agreed on April 2 to seek a real estate market analysis for Lost Mountain Station 36 after multiple attempts to seek volunteers to keep the station open. They’ll consider selling it and using funds for emergency supplies in the area, and offsetting construction costs for a new Carlsborg fire station. (Matthew Nash/Olympic Peninsula News Group)
Fire District to seek market analysis for station

Proceeds could help build new building in Carlsborg