Construction crews work to rebuild the Rialto Beach jetty as seen from across the Quillayute River from LaPush. (Lonnie Archibald)

Construction crews work to rebuild the Rialto Beach jetty as seen from across the Quillayute River from LaPush. (Lonnie Archibald)

Work underway on damaged section of Rialto revetment at La Push

U.S. Army Corps of Engineers estimates that the repairs on the 300-foot-long section of the protective jetty will be finished in about three weeks.

LA PUSH — Work continues on a 300-foot-long damaged section of the Rialto revetment near La Push, with the U.S. Army Corps of Engineers estimating repairs will be completed in about three weeks.

Coastal revetments are sloping structures placed on banks or cliffs that absorb the energy of incoming water in order to prevent erosion. The damaged barrier is essentially a rocky jetty that protects La Push.

A 300-foot-long stretch of the revetment has failed on the west side, according to the Corps, and only the underlying gravel berm remains.

So far, the project is slated to cost about $1.6 million, said Patricia C. Graesser, U.S. Army Corps of Engineers public affairs supervisor for the Greater Seattle area.

The repairs are being conducted by Bruch & Bruch Construction Inc. of Port Angeles, Columbia Granite LLC of Olympia, and SEA Construction LLC of Raymond.

“A crew of three from the Corps is overseeing repairs to the revetment and expect to complete work in the next few weeks,” Graesser said.

It isn’t clear exactly when or how the revetment was damaged, but officials believe winter storms last year were likely the cause, said Bill Dowell, U.S. Army Corp of Engineers spokesperson.

Noticed in spring

The damage was first noticed in late March or early April of this year, he said.

Before construction crews and heavy equipment could access the revetment, a damaged stretch of Mora Road in Olympic National Park — the only access road to the site — needed to be repaired and widened, Graesser said.

A Corps team began widening the road Oct. 14 to allow trucks to haul material to the revetment for the needed repairs.

As of Friday, contractors were delivering stone to the site that will be used to strengthen the barrier, Graesser said.

The 3,000-foot-long revetment was built in 1974 and last rehabilitated after a breach in 1996, Graesser said.

The structure’s crest in the damaged area is between four and six feet lower than the design elevation and adjacent structure elevation, according to the Corps. Given the revetment’s condition, if no action was taken a breach in the damaged area would be highly probable.

Emergency repair efforts were prompted by a series of storms that arrived in the Pacific Northwest beginning Oct. 13, according to Graesser.

If the revetment had been breached during the storms, it could have exposed the Quileute reservation riverward shoreline, Coast Guard Station, training wall and Quileute Marina to direct wave action, Graesser said.

A training wall is an artificial embankment or wall for directing the course of a stream or river, in this case the Quillayute River, which runs to the east of Rialto Beach.

The training wall is not designed to protect the marina or other facilities from wave action and likely would have been destroyed if exposed to ocean waves and debris, Graesser said.

Because the marina is the only safe harbor for 60 miles along the Pacific Ocean, the Corps initiated emergency repairs to the revetment, Graesser said.

“Because of the threat of a breach, we received emergency funding to address the immediate threat,” she said.

“Additional work will still be required after storm season.”

The threat underscores efforts by the Quileute tribe to move much of its community. Much of the reservation — including the existing school site adjacent to First Beach, the Quileute Tribal Center, the Quileute Senior Center and many homes — is directly in the path of possible tsunamis or flooding from the Quillayute River, according to the Quileute tribe.

________

Features Editor Chris McDaniel can be reached at 360-452-2345, ext. 56650, or at cmcdaniel@peninsuladailynews.com.

Reporter Jesse Major contributed to this report.

Road closed signs are set up at the Mora Ranger Station on the Mora Road as the road from that point on to Rialto Beach is closed due to work being done on the rialto Beach jetty. (Lonnie Archibald)

Road closed signs are set up at the Mora Ranger Station on the Mora Road as the road from that point on to Rialto Beach is closed due to work being done on the rialto Beach jetty. (Lonnie Archibald)

More in News

John Brewer.
Former editor and publisher of PDN dies

John Brewer, 76, was instrumental in community

Randy Perry and Judy Reandeau Stipe, volunteer executive director of Sequim Museum & Arts, hold aloft a banner from "The Boys in the Boat" film Perry purchased and is loaning to the museum. (Michael Dashiell/Olympic Peninsula News Group)
‘Boys in the Boat’ banner to be loaned to museum

Sequim man purchases item shown in film at auction

Charisse Deschenes, first hired by the city of Sequim in 2014, departed this week after 10 years in various roles, including most recently deputy city manager/community and economic development director. (City of Sequim)
Deputy manager leaves Sequim

Community, economic development position open

Hoko River project seeks salmon recovery and habitat restoration

Salmon coaltion takes lead in collaboration with Makah, Lower Elwha tribes

Clallam Transit’s zero-fare program off to successful start

Ridership is up and problems are down, general manager says

Motor rider airlifted to Seattle hospital after wreck

A Gig Harbor man was airlifted to a Seattle hospital… Continue reading

Traffic light project to begin Monday

Work crews from Titan Earthwork, LLC will begin a… Continue reading

From left to right are Indigo Gould, Hazel Windstorm, Eli Hill, Stuart Dow, Mateu Yearian and Hugh Wentzel.
Port Townsend Knowledge Bowl team wins consecutive state championships

The Knowledge Bowl team from Port Townsend High School has… Continue reading

Bob Edgington of 2 Grade LLC excavating, which donated its resources, pulls dirt from around the base of an orca sculpture at the Dream Playground at Erickson Playfield on Thursday during site preparation to rebuild the Port Angeles play facility, which was partially destroyed by an arson fire on Dec. 20. A community build for the replacement playground is scheduled for May 15-19 with numerous volunteer slots available. Signups are available at https://www.signupgenius.com/go/904084DA4AC23A5F85-47934048-dream#/. (Keith Thorpe/Peninsula Daily News)
Site preparation at Dream Playground

Bob Edgington of 2 Grade LLC excavating, which donated its resources, pulls… Continue reading

Rayonier Inc. is selling more than 115,000 acres in four units across the West Olympic Peninsula last week as the company looks to sell $1 billion worth of assets. (Courtesy photo / Rayonier Inc.)
Rayonier to sell West End timberland

Plans call for debt restructuring; bids due in June

Port Angeles port approves contract for Maritime Trade Center bid

Utilities installation, paving part of project at 18-acre site