Port of Port Angeles cuts cost of wash-down facility

Chris Hartman

Chris Hartman

PORT ANGELES — Port of Port Angeles commissioners have agreed to spend $46,855 to have an Everett engineering company revise bid documents for a planned $1.8 million self-service, vessel wash-down facility that will be built at the port’s still-vacant Marine Trades Industrial Park.

Reid Middleton Inc. had estimated construction of the project at the 19-acre former K-Ply plywood mill site just west of downtown Port Angeles on Marine Drive would cost, as port Director of Engineering Chris Hartman put it, a “staggering” $2.46 million.

The estimate “was significantly higher than what was included in the port’s capital budget and more than can be currently justified,” he said in the report to the board.

“We ended up with a Cadillac that was far too expensive,” he explained Monday at the port commissioners’ meeting. “We, as a staff, have to own that.”

Commissioners and staff Monday repeatedly used the metaphor.

“We didn’t indicate we wanted the Chevy model,” Commissioner Colleen McAleer said.

Hartman said Tuesday that Reid Middleton should have been better managed by port staff as they put together estimates for the project.

Hartman said the company’s estimate for full construction was $1.52 million when 60 percent of it was designed and was $2.46 million when fully designed.

“That’s where we built our initial capital budget, on that [lower] estimate,” he said. “Where things went awry was, we got blindsided a bit about the construction cost.”

A Reid Middleton company official did not return a call for comment late Tuesday afternoon.

The project cost is $1.6 million for construction alone, not including $200,000 for bid-document revisions, construction administration and a 5 percent construction contingency fund, Hartman said in his report to commissioners.

In anticipation of Monday’s meeting, port commissioners had reduced construction costs by $870,000.

Among the changes were deleting a $565,000 water treatment plant, opting instead to have effluent trucked to the port’s Boat Haven marina treatment facility about a mile west down Marine Drive.

Infrastructure for a treatment plant will be included that can be completed when funding is available.

“When there is enough use of that system, and the additional cost makes sense, then they’ll install that treatment facility,” Hartman said Tuesday.

Commissioners also shortened the wash pad, cutting its length nearly in half from 175 feet to 93 feet and saving $239,000.

That means the largest vessels carried by mobile lifts operated by Westport Shipyard and Platypus Marine, the wash-down facility’s two main users, will have to be moved around in stages once they are set on the wash pad for a complete cleaning rather than being set in one place while non-port employees clean the boats.

Hartman predicted the average-length boat will be 65 feet, although the yachts that non-port-tenant Westport builds are far longer than that, he said.

Port tenant Platypus, which as a boatbuilding and repair company will use the facility more than Westport, has a 300-ton lift.

Westport, with its own facility and purely a boatbuilder, has a 500-ton lift.

Hartman said a shoreline permit for the wash-down facility is being reviewed by the city Department of Community and Economic Development.

Grading and clearing permits also are needed from city public works.

Hartman expects permit approval will lead to construction that will begin in June and end in August.

When completed, “it’s not going to look like much,” Hartman said.

“It’s going to be a really large concrete pad with low points in the middle where water will wash down and drain into an underground tank.”

Users of the wash-down facility will operate it on their own in a manner not dissimilar from a self-service car wash, Hartman said, by wielding a wand-like hose — but one that pumps out 3,000 psi of water at 3.5 gallons per minute, Hartman said.

Fees for usage have not been set.

“We don’t anticipate the wash-down facility being a revenue generator for the port,” he added.

“It will be a bit of a loss leader, but at this point any boat repair company needs access to a wash-down facility.”

An anchor tenant for the industrial park that had been interested late last year in locating at the site has stepped back, Hartman added.

“Right now, it’s still a possibility, but it’s not as likely as it was,” Hartman said.

________

Senior Staff Writer Paul Gottlieb can be reached at 360-452-2345, ext. 55650, or at pgottlieb@peninsuladailynews.com.

More in News

From left to right are Indigo Gould, Hazel Windstorm, Eli Hill, Stuart Dow, Mateu Yearian and Hugh Wentzel.
Port Townsend Knowledge Bowl team wins consecutive state championships

The Knowledge Bowl team from Port Townsend High School has… Continue reading

Bob Edgington of 2 Grade LLC excavating, which donated its resources, pulls dirt from around the base of an orca sculpture at the Dream Playground at Erickson Playfield on Thursday during site preparation to rebuild the Port Angeles play facility, which was partially destroyed by an arson fire on Dec. 20. A community build for the replacement playground is scheduled for May 15-19 with numerous volunteer slots available. Signups are available at https://www.signupgenius.com/go/904084DA4AC23A5F85-47934048-dream#/. (Keith Thorpe/Peninsula Daily News)
Site preparation at Dream Playground

Bob Edgington of 2 Grade LLC excavating, which donated its resources, pulls… Continue reading

Rayonier Inc. is selling more than 115,000 acres in four units across the West Olympic Peninsula last week as the company looks to sell $1 billion worth of assets. (Courtesy photo / Rayonier Inc.)
Rayonier to sell West End timberland

Plans call for debt restructuring; bids due in June

Port Angeles port approves contract for Maritime Trade Center bid

Utilities installation, paving part of project at 18-acre site

Port Angeles to hire personnel to operate day ambulance

The Port Angeles Fire Department will be able to… Continue reading

Port Angeles City Hall parking lot closed for construction

Work crews from Bruch and Bruch Construction, Inc. will… Continue reading

Teen photo contest open for submissions

The Jefferson County Library is accepting submissions for Teen… Continue reading

Letters of inquiry for grant cycle due May 15

The Olympic View Community Foundation and the Seattle Foundation will… Continue reading

Amy DeQuay of Port Angeles, right, signs up for information at a table staffed by Christopher Allen and Mary Sue French of the Port Angeles Arts Council during a Volunteer Fair on Wednesday at Vern Burton Community Center in Port Angeles. The event, organized by the Port Angeles Chamber of Commerce, brought together numerous North Olympic Peninsula agencies that offer people a chance to get involved in their communities. (Keith Thorpe/Peninsula Daily News)
Volunteer fair in Port Angeles

Amy DeQuay of Port Angeles, right, signs up for information at a… Continue reading

Luncheon to raise funds for women with cancer

The Kathleen Sutton Fund will host its third spring… Continue reading

Among those volunteering are rowers from Port Townsend, Port Angeles and Sequim. Pictured from left to right are WendyRae Johnson of Port Angeles; Gail Clark and Lynn Gilles, both of Sequim, Jean Heessels-Petit of Sequim; Christi Jolly, Dennis Miller, Carolyn DeSalvo and Frank DeSalvo, all of Sequim; and Rudy Heessels, Amy Holms and Guy Lawrence, all of Sequim.
Sequim Bay Yacht Club to host opening day ceremonies

The Sequim Bay Yacht Club will host free boat rides… Continue reading

Serve Washington presented service award

Serve Washington presented its Washington State Volunteer Service Award to… Continue reading