The Polar Resolution, an oil tanker from Long Beach, Calif., moors Thursday at the Port of Port Angeles-owned Terminal 1, where $4.9 million in improvements were recently completed. (Jesse Major/Peninsula Daily News)

The Polar Resolution, an oil tanker from Long Beach, Calif., moors Thursday at the Port of Port Angeles-owned Terminal 1, where $4.9 million in improvements were recently completed. (Jesse Major/Peninsula Daily News)

Port of Port Angeles completes repairs of Terminal 1

PORT ANGELES — The Port of Port Angeles has completed nearly $5 million in repairs and improvements on Terminal 1, its oldest piece of infrastructure.

During the $4.9 million project, crews replaced more than 380 wooden piles with coated steel piles, contracted a new barge dolphin and made major repairs to the head tie dolphin, said Chris Hartman, director of engineering.

Dolphins are mooring points not attached to the dock.

The dock was built in 1927 and many of the pilings were nearly 90 years old.

“Terminal 1 is the port’s oldest piece of infrastructure,” Hartman said. “It’s why the port was created in the first place.”

The terminal is primarily used for topside repairs of oil tankers, typically traveling between Alaska and California, he said.

“The biggest customers are oil tankers,” he said. “They come down here when they need work done, anything other than coming out of water.”

Vigor Industrial, a shipbuilding and ship repair company with 12 locations in the Pacific Northwest and Alaska, uses the terminal to repair ships that don’t need to go into dry dock, Hartman said.

“Terminal 1 is an extremely important piece of infrastructure to marine repair companies here in Port Angeles,” he said. “That piece of infrastructure is vital for them.”

The project was first approved in July of 2015 and reached substantial completion Oct. 31 of this year.

Work was originally anticipated to be finished by the end of March, but there were numerous delays in procuring steel piling.

The contractor also encountered extremely dense soil conditions when installing piling for the new barge dolphin.

A list of punch list items was completed in late November, and port commissioners officially put the project to rest Monday.

The port replaced the wood piles with steel piles primarily for environmental reasons, Hartman said.

“When it was originally constructed, they used creosote coating so they could last,” he said. “That’s no longer allowed.”

Hartman said there are other approved coats for wood piles but that it made more sense to choose steel, which lasts much longer.

The project was partially funded by a $1,500,000 grant from the U.S. Department of Commerce.

The port paid $850,670.38 out of pocket in 2015 and another $2,528,256.55 this year, for a total of $3,378,926.93.

The port budgeted $3 million toward the project this year. Even with more than $375,000 in change orders, the project came in roughly $475,000 under budget.

“We were anticipating [extra costs], it being as old of a structure as it is,” Hartman said. “You anticipate finding additional repairs.

“We put a significant contingency on top of it to be sure we were covered.”

That 7.8 percent increase from change orders came after crews found more things that needed repairs and as some damage was caused during construction.

Among those repairs was for dock damage on Terminal 3 after a ship went in too hard, Hartman said. Terminal 3 is the port’s loading dock and is adjacent to Terminal 1.

________

Reporter Jesse Major can be reached at 360-452-2345, ext. 56250, or at jmajor@peninsuladailynews.com.

More in News

From left to right are Indigo Gould, Hazel Windstorm, Eli Hill, Stuart Dow, Mateu Yearian and Hugh Wentzel.
Port Townsend Knowledge Bowl team wins consecutive state championships

The Knowledge Bowl team from Port Townsend High School has… Continue reading

Bob Edgington of 2 Grade LLC excavating, which donated its resources, pulls dirt from around the base of an orca sculpture at the Dream Playground at Erickson Playfield on Thursday during site preparation to rebuild the Port Angeles play facility, which was partially destroyed by an arson fire on Dec. 20. A community build for the replacement playground is scheduled for May 15-19 with numerous volunteer slots available. Signups are available at https://www.signupgenius.com/go/904084DA4AC23A5F85-47934048-dream#/. (Keith Thorpe/Peninsula Daily News)
Site preparation at Dream Playground

Bob Edgington of 2 Grade LLC excavating, which donated its resources, pulls… Continue reading

Rayonier Inc. is selling more than 115,000 acres in four units across the West Olympic Peninsula last week as the company looks to sell $1 billion worth of assets. (Courtesy photo / Rayonier Inc.)
Rayonier to sell West End timberland

Plans call for debt restructuring; bids due in June

Port Angeles port approves contract for Maritime Trade Center bid

Utilities installation, paving part of project at 18-acre site

Port Angeles to hire personnel to operate day ambulance

The Port Angeles Fire Department will be able to… Continue reading

Port Angeles City Hall parking lot closed for construction

Work crews from Bruch and Bruch Construction, Inc. will… Continue reading

Teen photo contest open for submissions

The Jefferson County Library is accepting submissions for Teen… Continue reading

Letters of inquiry for grant cycle due May 15

The Olympic View Community Foundation and the Seattle Foundation will… Continue reading

Amy DeQuay of Port Angeles, right, signs up for information at a table staffed by Christopher Allen and Mary Sue French of the Port Angeles Arts Council during a Volunteer Fair on Wednesday at Vern Burton Community Center in Port Angeles. The event, organized by the Port Angeles Chamber of Commerce, brought together numerous North Olympic Peninsula agencies that offer people a chance to get involved in their communities. (Keith Thorpe/Peninsula Daily News)
Volunteer fair in Port Angeles

Amy DeQuay of Port Angeles, right, signs up for information at a… Continue reading

Luncheon to raise funds for women with cancer

The Kathleen Sutton Fund will host its third spring… Continue reading

Among those volunteering are rowers from Port Townsend, Port Angeles and Sequim. Pictured from left to right are WendyRae Johnson of Port Angeles; Gail Clark and Lynn Gilles, both of Sequim, Jean Heessels-Petit of Sequim; Christi Jolly, Dennis Miller, Carolyn DeSalvo and Frank DeSalvo, all of Sequim; and Rudy Heessels, Amy Holms and Guy Lawrence, all of Sequim.
Sequim Bay Yacht Club to host opening day ceremonies

The Sequim Bay Yacht Club will host free boat rides… Continue reading

Serve Washington presented service award

Serve Washington presented its Washington State Volunteer Service Award to… Continue reading