Long delays around Lake Crescent halted for summer months

LAKE CRESCENT — Olympic National Park has suspended four-hour delays on U.S. Highway 101 at Lake Crescent on weekdays for the next three and a half months.

The announcement this week is an about-face from earlier plans.

Drivers should continue to expect half-hour delays at the lake from Mondays through Fridays during work hours.

The four-hour delays from Mondays through Thursdays will resume Sept. 3.

“To avoid excessive impacts on summer traffic, the road restoration repairs will begin after Labor Day,” park officials said in a Wednesday announcement.

“The work will require four-hour delays Monday through Thursday beginning Sept. 3. This work is anticipated to be completed within the 20-day closure (five work weeks) allowed by the contract,” according to the park’s press release.

The first plan was to avoid four-hour delays between Memorial Day and Labor Day to limit impacts on summer travel. But last week, park officials announced that the four-hour delays would continue on weekdays through June 13 to expedite the final phase of the $27.5 million, three-year project.

The four-hour delays, which began Monday and ended Thursday, are necessary for crews to restore the roadway width and shoulder area in front of a rock wall near milepost 229.

During construction this week, it became apparent that the June 13 target for completion was “not going to be feasible,” said Lisa Turecek, Olympic National Park chief of facility management.

“If we continued, we were committed to it,” Turecek said in a telephone interview.

“We decided it was too much risk of having extended traffic impacts into the summer.”

Park officials originally had planned to begin the four-hour delays mid-April, but it lacked a permit from the U.S. Army Corps of Engineers to work below the ordinary high water mark. That permit was received last week, allowing for construction earlier this week.

Crews this week stabilized slopes and placed riprap where gating baskets had failed near milepost 229.

“We were able to look at the site conditions a little more closely,” Turecek said

It was determined that that the remaining work would be “a little bit more involved” than previously thought, she said.

“We appreciate everyone’s patience,” Turecek said.

The Lake Crescent project is being managed by the Federal Highway Administration and the National Park Service.

Strider Construction Inc. of Bellingham is the contractor.

Remaining work that will occur this spring and summer includes sign replacement, paving the final 2½-inch layer of asphalt and striping.

Paving is set to begin June 3 and will last for six to eight weeks depending on weather, park officials said.

Paving near the rock wall will take place in the fall.

Weekday half-hour delays are restricted to two hours after sunrise to two hours before sunset.

________

Reporter Rob Ollikainen can be reached at 360-452-2345, ext. 56450, or at rollikainen@peninsuladailynews.com.

More in News

Port Angeles teachers’ union votes to honor paraeducators’ picket line on April 8

Members of the Port Angeles Education Association voted overwhelmingly… Continue reading

Funding needed for Port Townsend homeless shelter

Operation at Legion Hall to close April 30

Port of Port Angeles renews lease for Composite Recycling Technology Center

Agreement covers 26,000 square feet at airport business park

Fire district volunteers lauded

Clallam County Fire District No. 3 recently recognized seven members… Continue reading

Clallam to continue providing deputy to Forks

Contract includes wages, mileage and maintenance reimbursement

Maintenance closes section of Olympic Discovery Trail

A portion of the Olympic Discovery Trail is closed… Continue reading

Hanna Paoluccu of Alexander, N.Y., and Rosie Berg of Nevada City, Calif., members of the Hood Canal Salmon Enhancement Group and working with the Jefferson County Noxious Weed Board, remove poisonous hemlock weed from along the Larry Scott Trail in Port Townsend on Monday. (Steve Mullensky/for Peninsula Daily News)
Poison hemlock removal in Port Townsend

Hanna Paoluccu of Alexander, N.Y., and Rosie Berg of Nevada City, Calif.,… Continue reading

YMCA to build childcare facility

$1-2M still needed for $6.7M project

Port Townsend Police Department recognizes award recipients

The Port Townsend Police Department recognized officers, employees, volunteers… Continue reading

Port Angeles High School evacuated due to bomb threat

Nothing suspicious found, principal says

A tree that has grown out of its tree box and shattered a nearby curb and sidewalk in the 100 block of North Oak Street is among those targeted for removal and replacement in downtown Port Angeles. (Keith Thorpe/Peninsula Daily News)
Port Angeles tree and sidewalk replacement to begin Monday

The Port Angeles downtown tree and sidewalk replacement project… Continue reading

Grant for Forks treatment plant to be discussed

The Clallam County Opportunity Fund Advisory Board will discuss… Continue reading